ID Date Author Category Typedown Module Target/Number Subject Text Attachments
  523   Thursday, October 24, 2013, 11:31 Travis CaveSpent Target VaultStandard Operation UC#7Spent target moveUC #7 has been moved from the south hot
cell to the spent target vault, it was placed
in pail #110 and put in slot 8B of the vault,
 Vault_Storage_October_24_2013.pdf 
  524   Thursday, October 24, 2013, 11:32 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule moveTM#4 with no target has been moved from
the conditioning station to the south hot
cell.
  
  525   Thursday, October 24, 2013, 15:43 Anders MjosSouth Hot-CellStandard OperationTM4Ta#41Target conductanceThe conductance check on the electrical
check was found to be outside of accepted
values for the TBHT at 7.0 mOhm. A successful
 Ta#41_electrical_measurement_TGHT_in_SHC.pdf 
  526   Thursday, October 24, 2013, 15:54 Grant MinorSouth Hot-CellStandard OperationTM4Ta#41Target conductance

    

       
            
  
  527   Friday, October 25, 2013, 06:58 David WangSouth Hot-CellStandard OperationTM4 Leak check on TM4 target heat shieldMaico and I leak checked HS circuit after
Chad installed the target. The circuit was
a little bit difficult o pump down because
  
  528   Friday, October 25, 2013, 10:26 Travis CaveITWStandard OperationTM4Ta#41module moveTM#4 with Ta#41 has been moved from the
south hot cell to the west target station.
  
  529   Friday, October 25, 2013, 13:39 Anders MjosITEStandard OperationTM3NiO#2Padlle wheel frequency measurementswith TM4 in ITW as measured today in the
electrical room by David and Anders.
 
 ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow_wITW-TM4.pdf 
  530   Friday, October 25, 2013, 14:09 Travis CaveSouth Hot-CellStandard OperationTM4Ta#41Target conductance

    

       
            
 TM#4_Ta#41_elec_test_SHC.PDF 
  531   Thursday, October 31, 2013, 10:36 David WangITWStandard OperationTM4 I moved 5 shielding blocks from ITE to ITW.I moved 5 shielding blocks from ITW to
ITE. The ITW  is configured to take
proton beam.
  
  532   Thursday, October 31, 2013, 11:38 Anders MjosITEStandard OperationTM3NiO#2Padlle wheel frequency measurementswith TM4 in ITW as measured today in the
electrical room by David and Anders.
 ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow_EOB.pdf 
  533   Friday, November 01, 2013, 09:08 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule moveTM#2 has been moved from the north west
silo to the south hot cell. The module has
a field of about 3.1mSv/hr when it was lowered
  
  537   Tuesday, November 12, 2013, 09:51 David WangITEStandard OperationTM3 TM3 disconnectionTM3 has been disconnected this morning
and  purged all HV water lines. I found
the power plug for all turbo pump fans wasnt
  
  538   Tuesday, November 12, 2013, 10:59 Bevan MossSouth Hot-CellStandard OperationTM2 Electrical Test Don Jackson and Myself completed
started an electrical test on TM2. All lines
passed the with OL to ground. When testing
 tm2_elec_test.pdf 
  539   Tuesday, November 12, 2013, 12:43 Bevan MossConditioning StationStandard OperationTM2 TM2 moved from SHC to TCS TM2 was moved by myself and David
from the SHC to the TCS. Move went well.
Curiously the fields on the module were measured
  
  540   Tuesday, November 12, 2013, 14:31 Bevan MossConditioning StationStandard OperationTM2 Turbo pumps started The turbo pumps have been started
on TM2 and the conditioning station.
  
  544   Friday, November 15, 2013, 16:48 Bevan MossConditioning StationStandard OperationTM2 HV Testing High voltage testing was started
on TM2 with no source tray today. The maximum
stable for 1 minute voltage reached was 47.5kV
 TM2_conditioning_15112013.JPG15112013_TM2_No_source_tray_HV_test.txt 
  546   Monday, November 18, 2013, 16:42 Bevan MossConditioning StationStandard OperationTM2 HV Testing The Glory of TM2 continues 100V at
a time. Today I brought the module to 46kV
and left it there for 1 hour. During this
 the_glory_of_TM2.JPG18112013_TM2_No_source_tray_HV_Test.txt 
  547   Monday, November 18, 2013, 16:44 Bevan MossConditioning StationStandard Operation  Testing of cooling package I have tested all of the compressors
for TCS. All are operational and cycled as
they should. 
  
  548   Tuesday, November 19, 2013, 10:52 Travis CaveSouth Hot-CellStandard OperationTM3NiO#2module moveTM#3 with NiO#2 moved from ITE to the south
hot cell.
  
  550   Tuesday, November 19, 2013, 16:55 Bevan MossConditioning StationStandard OperationTM2 HV conditioning HV conditioning of TM2 continued
today. At ~53.5kV the module started to spark
externally to the HV cover. This is the first
 external_sparking.JPG19112013_HV_conditioning_TM2.JPG19112013_TM2_No_source_tray_HV_Test_no_cover.txt19112013_TM2_No_source_tray_HV_Test.txt 