Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 18 of 140  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Category Type Module Target/Number Subjectdown Text Attachments
  2382   Tuesday, November 01, 2022, 12:40 Frank SongNorth Hot-CellStandard OperationTM2UCx#39electrical check TM2 with spent target UCx#39 had
an electric check in NHC.
After UCx 39# target was removed
 electical_check_for_TM2_with_spent_target_UCx39_on_NHC.png 
  2383   Wednesday, November 02, 2022, 11:11 Frank SongNorth Hot-CellStandard OperationTM2UCx#40electrical checkan electrical check was done on NHC, TM2
with new target UCx40 is ready moving to
TCS.
 TM2_with_UCx40_electrical_check_on_NHC.png 
  2390   Tuesday, November 22, 2022, 12:41 Frank SongNorth Hot-CellStandard OperationTM4C#4electrical check TM4 with C#4 is checked on NHC
right after moving from ITE.
 TM4_with_C#4_electrical_check_right_after_moving_to_NHC.png 
  2456   Tuesday, June 13, 2023, 11:45 Frank SongNorth Hot-CellStandard OperationTM4TiC#5electrical check TM4 with spent target TiC#5 electric
check after moving from ITE to NHC.
 TM4_with_spent_target_electric_check_right_after_moving_to_NHC.png 
  2466   Wednesday, July 19, 2023, 08:09 Frank SongNorth Hot-CellStandard OperationTM4UCx#42electrical check An electrical check was made after
new target installed on TM4.
 E__check_after_UCx42_installed_on_TM4.pdf 
  2481   Tuesday, August 29, 2023, 09:07 Frank SongITWRepairTM2Nb#11electrical check TM2 with new target Nb#11 replaced
has been electric checked one more time in
ITW.
 TM2_with_Nb#11_electical_check_in_ITW_2023-08-28.pdf 
  2491   Tuesday, October 03, 2023, 14:28 Frank SongSouth Hot-CellStandard OperationTM2Nb#11electrical check An electric checked right after TM2
was moved from ITW. 
 TM2_with_spent_target_Nb#11_electrical_check_right_after_moving_from_ITW_to_SHC.pdf 
  2355   Wednesday, August 10, 2022, 08:10 Frank SongNorth Hot-CellStandard OperationTM4Sic#44electrical and leak check  TM4 with Sic#44 installed and had
an electrical / leak check at NHC. 
 TM4_with_Sic#44_eletrical_and_leak_check.jpg 
  2480   Monday, August 28, 2023, 12:16 Frank SongNorth Hot-CellRepairTM2Nb#11electric/leak check TM2 with new target Nb#11 has been
E/L checked sitting on NHC.
 TM2_with_Nb#11_electical_and_leak_check_in_NHC_2023-08-28.pdf 
  2392   Wednesday, November 23, 2022, 11:27 Frank SongNorth Hot-CellStandard OperationTM4UCx#41electric and leak check after new target installed an electric check and leak check
done on NHC, TM4 with new target UCx#41 is
ready moving to TCS.
 TM4_with_UCx#41_electric_and_leak_check_on_NHC.png 
  2381   Tuesday, November 01, 2022, 12:37 Frank SongITWStandard OperationTM2UCx#39disconnection TM2 with spent target UCx#39 was
disconnected in ITW then moved to NHC.
 TM2_with_UCx39_disconnection_in_ITW.png 
  791   Tuesday, November 18, 2014, 11:14 David WangSouth Hot-CellStandard Operation UCx11crane down UCx 11 target into SHC from THI craned down UCx11 target from TH into
SHC. Chad was in SHC service area watching
on it. The source tray moving jig was installed
  
  2329   Thursday, June 09, 2022, 09:47 Matthew GareauSouth Hot-CellRepairTM2SiC#42containment box repair, Einzle lens, multi pinOn June 2 2022, while attempting to install
target SiC#42 a gasket fell off the water
line. I attempted to remove the target to
  
  812   Thursday, December 04, 2014, 16:37 David WangConditioning StationDevelopmentTM2 connected TM2 and CS vacuum system .I connected TM2 and CS vacuum system. All
vacuum pumps on TM2 and CS are started .The
pumping down is good so .far
  
  79   Monday, April 02, 2012, 08:17 David WangConditioning StationDevelopment  conditioning station IMC pump down.I pumped down conditioning station IMC
today. The inside bellow pressure is -20
psi on the gauge.Visually checked the bellow
  
  83   Thursday, April 12, 2012, 14:40 David WangConditioning StationDevelopmentTM1 conditioning staion and TM1 is under TP1 and TP2 pumping now.TM1 moved to conditioning station to today.
After moving, I connected the vacuum system
which include all gauges ,vacuum lines ,
  
  121   Friday, June 08, 2012, 11:07 David WangConditioning StationStandard OperationTM1Ta38conditioning staion and TM1 is under TP1 and TP2 pumping now.I connected vacuum system to TM1 and conditioning
station and started two turbo pumps yesterday.
The pumping an d vacuum readings  are
  
  95   Thursday, April 26, 2012, 09:23 David WangITERepairTM4 changed flow wheel on ITE TM4 contaiment box water circuitThe the magnetic field on ITE TM4 flow
wheel  was gone yesterday.So there is
no water signal on this circuit. The water
  
  2730   Wednesday, December 04, 2024, 09:00 David WangFacilitiesStandard OperationTM2 all water lines on TM2 have been purged.all water lines on TM2 have been purged.
Refilled them(except HS ) with 60psi nitrogen
for module silo storage before next year
  
  1160   Wednesday, March 02, 2016, 09:51 David WangITWStandard OperationTM2 all water lines on TM2 and TM4 are purged.All water lines on TM2 and TM4 are purged
for upcoming water lines helium pressure
test.
  
ELOG V2.9.2-2455