1970
|
Friday, August 23, 2019, 14:27 |
Isaac Earle | Safe Module Parking | Development | | | SMP camera video cabling installed and tested | Installation of the video lines for
the SMP cameras was completed yesterday according
to IRH1670 Rev B. All four cameras |
|
1971
|
Tuesday, August 27, 2019, 13:12 |
Adam Newsome | Safe Module Parking | Development | | | SMP Remote Control Wiring Inspection | The wiring for the SMP remote control module
was inspected by Joel Semilla (TRIUMF electrician).
The module was plugged in to verify there |
|
1986
|
Tuesday, September 17, 2019, 07:37 |
Carla Babcock | ITE | Development | TM2 | ZrC#8 | end of run HV investigations | Ramping up HV to ~30kV, encountered problems
and had to drop back to 28kV. No response
on IG1 or anything else during sparks. Lots |
|
1990
|
Monday, September 30, 2019, 11:27 |
Isaac Earle | Safe Module Parking | Development | | | SMP vacuum vessel modifications completed | The SMP vacuum vessel welds were reinforced
to match the specifications on IRH1710 Rev
D. In addition a tube stub was added |
|
2006
|
Thursday, October 10, 2019, 16:17 |
Adam Newsome | Safe Module Parking | Development | | | SMP Main Panel: Relay Addition for E-Stop Circut | An update was made for the E-stop and power
supply system in the SMP main panel. Upon
testing remote control, it was determined |
|
2007
|
Tuesday, October 15, 2019, 16:42 |
Isaac Earle | Safe Module Parking | Development | | | SMP flange alignment tested using shield plug | As a preliminary test in preparation
for SMP commissioning, one of the steel module
shield plugs was installed into the SMP to |
|
2010
|
Tuesday, October 22, 2019, 16:26 |
Isaac Earle | Safe Module Parking | Development | | | SMP shield box grounding | A braided grounding strap was attached
to the aluminum gear box support on the SMP
shield box structure, and grounded by attaching |
|
2014
|
Friday, October 25, 2019, 06:43 |
David Wang | Safe Module Parking | Development | TM3 | | SMP vacuum | TM3 was moved into SMP Oct 25 morning.
After two nights pumping down, SMP CG1 read
30mtorr this morning. The pump is stopped. |
|
2016
|
Monday, October 28, 2019, 12:00 |
Isaac Earle | Safe Module Parking | Development | | | SMP shielding attenuation measured & compared to theoretical values | The attenuation of the SMP shielding was
measured as part of SMP commissioning (Document-170404,
R1, Section 4, Test #8) |
|
2017
|
Tuesday, October 29, 2019, 10:00 |
Adam Newsome | Safe Module Parking | Development | | | SMP Updates to E-stop circuit and feedback signals | The SMP main control panel and remote control
module were updated in order to implement
the following items which were deemed desirable |
|
2037
|
Thursday, December 12, 2019, 14:39 |
Isaac Earle | Safe Module Parking | Development | | | SMP assembly shifted 1.0" north | The SMP assembly was shifted approximately
1.0" north today by pushing it, braced
against the south wall, using a 100 Ton capacity |
|
2043
|
Wednesday, January 08, 2020, 10:34 |
David Wang | Assembly/Bench Test | Development | | | Module lifting assembly ITA0490 | The second module lifting assembly ITA0490
is moved into TH and installed onto TM3 .
It will stay with TM3. I adjusted the |
|
2065
|
Friday, February 07, 2020, 08:05 |
chad fisher | South Hot-Cell | Development | TM4 | | Containment box off for IGLIS | The containment box has been removed from
TM4 in prep for the IGLIS wiring job. |
|
2082
|
Thursday, March 12, 2020, 13:42 |
David Wang | ITE/ITW | Development | | | New ITE IGLIS cables installation | New IGLIS cables installation is done.
Two bundle of new cables are pulled from
ITE to electrical room. They are in one PVC |
|
2087
|
Tuesday, March 17, 2020, 12:58 |
David Wang | South Hot-Cell | Development | TM4 | | P2N target electrical check and leak check at SHC. | See attachment. Everything looks good.
|
|
2088
|
Tuesday, March 17, 2020, 14:59 |
David Wang | ITE | Development | TM4 | P2N | ITE turbopumps are started. | They work fine. Current draw on all pumps
are normal. I asked operator to switch on
IG1 , IG1S and PNG4. |
|
2089
|
Wednesday, March 18, 2020, 10:40 |
David Wang | ITE | Development | TM4 | | TM4 P2N target connection checklist. | TM4 has been connected in ITE. See checklist. |
|
2123
|
Tuesday, July 07, 2020, 17:43 |
Carla Babcock | ITE | Development | TM4 | | RF tests on new IG-LIS wiring | Tested RF from RF driver into new IGLIS
wires at ITE. Used 5V, 1MHz (2MHz setting
because of internal halving issue). |
|
2132
|
Thursday, August 06, 2020, 14:33 |
Adam Newsome | Spent Target Vault | Development | | | Safety Group Relay Interface Installation | A relay contact-based interface module
was installed in between Safety Group's storage
vault door enable junction box and Remote |
|
2171
|
Monday, December 07, 2020, 12:20 |
Adam Newsome | Conditioning Station | Development | TM3 | | TM3 Move | TM3 has been moved from
the South Hot Cell to the
Conditioning Station. No containment box. |
|