  1780   Wednesday, September 12, 2018, 15:22 Isaac EarleNorth Hot-CellDevelopment  NHC air and gas supply lines - test and leak checkTesting was completed today on the NHC
air and gas supply lines.  For each
line a Staubli plug was installed on the
  
  1781   Wednesday, September 12, 2018, 15:30 Isaac EarleNorth Hot-CellDevelopment  Installation of NHC operator-level lighting completed Installation of of operator-level
lighting in the NHC was completed today according
to drawing IRH1801.  2" x 2"
 LEDs_and_manipulators.jpgLEDs.jpgcords.jpg 
  1782   Thursday, September 13, 2018, 16:57 Isaac EarleNorth Hot-CellDevelopment  NHC grounding and mili-ohm testing The
following equipment has been connected to
the building ground located in the Target
  
  1825   Thursday, November 22, 2018, 14:38 Isaac EarleNorth Hot-CellDevelopment  NHC design approved by High Voltage EngineerTo satisfy RS 101 from the NHC requirements
specification (Document-131915) Tomislav
Hurskovec was consulted regarding high voltage
 NHCHV.pdf 
  1830   Wednesday, November 28, 2018, 07:04 David WangITEDevelopmentTM4LpTa 56New high current flexible cables inspection after LpTa#56 beam run.Inspected new high current flexible cables
during TM4 disconnection. The new cables
and adapters work fine.
 new_flexibble_cable_in_ITE_after_Ta#56_run_001.JPGnew_flexibble_cable_in_ITE_after_Ta#56_run_004.JPG 
  1839   Monday, December 10, 2018, 15:31 Isaac EarleNorth Hot-CellDevelopment  NHC remote connection testing with manipulators The following tests have been successfully
completed using the NHC manipulators:

    Ventilation pre-filter
  
  1841   Tuesday, December 18, 2018, 11:13 Isaac EarleNorth Hot-CellDevelopment  NHC manipulator slave-end swap, RH test, and various other workThe following
North Hot Cell work was completed over the
last week under work permit I2018-12-12-1:
  
  1847   Friday, January 04, 2019, 14:38 Isaac EarleNorth Hot-CellDevelopment  NHC cameras testedThe NHC module support flange cameras (4
total) as well as the NHCSA camera were tested
today and confirmed to be working properly. 
 NHC_flange_East_and_West_views.JPGNHC_flange_North_and_South_views.JPGCamera_view_through_operator_viewing_window.JPG 
  1857   Friday, January 11, 2019, 13:59 Isaac EarleSafe Module ParkingDevelopment  SMP motor selection decisionSMP drivetrain design work is currently
underway.  Alejandro has selected a
suitable 1200:1 reducer which will give a
  
  1859   Friday, January 18, 2019, 10:26 Isaac EarleNorth Hot-CellDevelopment  NHC sealing improvements and repeat of RH test for LED lightsThe following NHC development work was
completed under WP I2019-01-09-4:

    Location of RH feature
  
  1860   Monday, January 21, 2019, 16:27 Isaac EarleNorth Hot-CellDevelopment  NHC in-cell camera wired to right side monitor The NHC right side monitor has been
wired to display the signal from the in-cell
camera.  This was tested using a snake
 20190121_154407.jpg 
  1864   Thursday, January 31, 2019, 14:16 Isaac EarleNorth Hot-CellDevelopment  NHC grounding approval Franco Mammarella was consulted regarding
electrical grounding of the NHC design (RS103
of Document-131915).  After discussing
 NHC_grounding.pdf 
  1865   Monday, February 11, 2019, 10:26 Isaac EarleSafe Module ParkingDevelopment  SMP shield box and vacuum vessel moved to Target Hall  On February 8th the SMP shield
box (IRH1675) and the vacuum vessel (IRH1806)
were both raised from a horizontal to vertical
 6x 
  1873   Thursday, February 21, 2019, 15:10 Isaac EarleSafe Module ParkingDevelopment  Seismic requirements for SMPDragan Mitrovic, TRIUMF structural engineer,
was consulted earlier this week regarding
seismic requirements for the SMP assembly. 
  
  1903   Monday, April 01, 2019, 14:56 Isaac EarleSafe Module ParkingDevelopment  SMP shield box and vacuum vessel installed in final location Last week drilling of the additional
required holes in the SMP shield box was
completed in the Target Hall.  This
 20190401_101459.jpg20190401_110433.jpg20190401_144133.jpg20190401_110353.jpg 
  1904   Thursday, April 04, 2019, 14:49 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum vessel support roller friction checkWith the SMP vacuum vessel now installed
inside the shield box, a test was performed
to measure the torque required to rotate
 CRR_check_for_as-built_SMP_-_April_4_2019.pdf 
  1905   Friday, April 05, 2019, 13:44 chad fisherSpent Target VaultDevelopment  2019 Pail drop tests
    Drop test performed January
8, 2019 with 25 lb target, UN pail and lug
cover. Drop failed. Lug cover half removed.
  
  1909   Monday, April 29, 2019, 07:56 chad fisherSouth Hot-CellDevelopment  Pail transfersTwo pail transfers took place April 25th.
Ta#47 transfered from pail 137 to
pail 201. existing plastic bag from 137 showed
 20190425_133750.jpg20190425_134106.jpg 
  1921   Wednesday, May 15, 2019, 16:06 Isaac EarleSafe Module ParkingDevelopment  SMP module support flange installed and leak checkedThe SMP module support flange sub-assembly
(IRH1755) was installed today according to
drawing IRH1683.  Dow Corning 111 sealing
 20190515_094730.jpg20190515_094740.jpg20190515_103253.jpg20190515_103824.jpg 
  1925   Friday, May 17, 2019, 16:46 Adam NewsomeSafe Module ParkingDevelopment  SMP Controls Installation Update 
The following controls-related
 IMG_20190417_100838.jpgIMG_20190417_100843.jpgIMG_20190517_162230.jpgIMG_20190517_162305.jpg 