Message ID: 1781     Entry time: Wednesday, September 12, 2018, 15:30
Author: Isaac Earle 
Category: North Hot-Cell 
Type: Development 
Module:  
Target/Number:  
Subject: Installation of NHC operator-level lighting completed 

 Installation of of operator-level lighting in the NHC was completed today according to drawing IRH1801.  2" x 2" Panduit was mounted to the wall on aluminum brackets to support the power cables.  These lights can be replaced remotely by unplugging the power cords using the manipulators, lifting the cable out of the Panduit with a hooked pole tool through the manipulator slave end removal roof hatch, lifting the light fixture off the support bracket with the pole tool, then installing a new fixture in the opposite order.  This RH procedure will be tested at a later date as part of NHC commissioning.

 

 LEDs_and_manipulators.jpg

 

LEDs.jpg

 

cords.jpg