Message ID: 1596     Entry time: Wednesday, August 09, 2017, 16:39
Author: Isaac Earle 
Category: North Hot-Cell 
Type: Development 
Module:  
Target/Number:  
Subject: NHC drain line into sump identified 

 The NHC drain line was tested by pouring approximately 10 gallons of water through the drain grate at the base of the NHC partition wall.  Water was seen a few minutes later pouring into the sump labeled "ACTIVE SUMP" from the light coloured pipe on the west side of the inside of the sump.  Rob Walker had previously said that the hot cells drain into the sump next to this one which is labeled "SANITARY SUMP", which appears to be incorrect.