  2017   Tuesday, October 29, 2019, 10:00 Adam NewsomeSafe Module ParkingDevelopment  SMP Updates to E-stop circuit and feedback signalsThe SMP main control panel and remote control
module were updated in  order to implement
the following items which were deemed desirable
  
  2027   Tuesday, November 12, 2019, 10:02 Adam NewsomeITEStandard OperationTM2SiC#38TM2 MoveTM2 was moved from the Conditioning Station
to ITE, with SiC#38 target. 
  
  2036   Tuesday, December 03, 2019, 12:45 Adam NewsomeSpent Target VaultStandard Operation SiC#38SiC#38 in Pail 205 moved to Storage Vault: 4BSiC#38 in Pail 205 was moved to section 4B
of the storage vault. Dose rate when retrieving
from Hot Cell was 22.2 mSv/h. 
 Target_Index_2019-12-03.pdf 
  2040   Friday, January 03, 2020, 13:15 Adam NewsomeCraneRepair  Target Hall Crane PLC Module/Battery ReplacementThe Target Hall Crane bridge and trolley motion
was lost after a period of the crane having
power disconnected over winter holidays.
  
  2063   Thursday, February 06, 2020, 13:31 Adam NewsomeSpent Target VaultStandard Operation UC#29UC#29 moved to vault location 6A, in pail 225 UC#29 in pail 225 was moved to the
storage vault, location 6A. Field measured
at 22.4 mSv/hr at ~1m. 
  
  2064   Thursday, February 06, 2020, 13:32 Adam NewsomeSouth Hot-CellMaintenanceTM4 TM4 moved from Conditioning Station to South Hot Cell TM4 was moved from conditioning station
to south hot cell in preparation for wiring
replacement. No target.
  
  2111   Friday, June 26, 2020, 10:43 Adam NewsomeSpent Target VaultStandard Operation  Routine mechanical inspection: storage vault and mini-storage drive systemsAn inspection was performed on drive systems
for both storage vaults (main and mini) by
Adam Newsome and Dan McDonald. The functionality
 IMG_20200626_092538.jpgIMG_20200626_093208.jpgIMG_20200626_093924.jpgIMG_20200626_093951.jpg 
  2125   Thursday, July 16, 2020, 10:20 Adam NewsomeSafe Module ParkingMaintenance  SMP: Annual Electrical InspectionAn electrical systems check was performed
on the SMP by Adam Newsome and Travis Cave.
Overall, there were no issues to
  
  2126   Tuesday, July 21, 2020, 14:22 Adam NewsomeSpent Target VaultStandard Operation  Emergency Close Mechanism TestThe emergency close mechanism for the Storage
Vault door was tested by Adam Newsome and
Travis Cave. The door was opened to its fully
  
  2132   Thursday, August 06, 2020, 14:33 Adam NewsomeSpent Target VaultDevelopment  Safety Group Relay Interface InstallationA relay contact-based interface module
was installed in between Safety Group's storage
vault door enable junction box and Remote
 IMG_20200806_091438.jpg 
  2134   Tuesday, August 18, 2020, 09:57 Adam NewsomeConditioning StationStandard OperationTM2 TM2 Moved to Conditioning StationTM2 was moved from ITW to the Conditioning
Station. 
  
  2135   Wednesday, August 19, 2020, 10:17 Adam NewsomeSouth Hot-CellStandard Operation  ITW Entrance Module moved to SHCITW Entrance Module was moved from west
station to South Hot Cell.
  
  2136   Monday, August 24, 2020, 10:11 Adam NewsomeITWStandard Operation  Entrance Module to ITWEntrance Module was moved from South Hot
Cell to ITW Station.
Note: weight of entrance module,
  
  2164   Tuesday, November 17, 2020, 10:17 Adam NewsomeSouth Hot-CellStandard OperationTM2 Module MoveTM2 has been moved from ITW to the South
Hot Cell. 
  
  2167   Thursday, November 19, 2020, 12:00 Adam NewsomeSpent Target VaultStandard Operation C#2Spent Target MoveC#2 has been moved from the south hot cell
to the spent target  vault. It is in spot
8A of the vault in pail # 235 and was 185
  
  2168   Tuesday, November 24, 2020, 09:37 Adam NewsomeITWStandard OperationTM2 Module MoveTM2 has been moved from
the Conditioning Station to ITW. 
  
  2170   Wednesday, November 25, 2020, 09:05 Adam NewsomeSouth Hot-CellStandard OperationTM3 Module MoveTM3 has been moved from
the Silo to the South Hot Cell.
  
  2171   Monday, December 07, 2020, 12:20 Adam NewsomeConditioning StationDevelopmentTM3 TM3 MoveTM3 has been moved from
the South Hot Cell to the
Conditioning Station. No containment box.
  
  2172   Thursday, December 10, 2020, 15:07 Adam NewsomeSouth Hot-CellDevelopmentTM3 TM3 MoveTM3 was remotely moved from the conditioning
station to the South Hot Cell. No containment
box.
  
  2173   Monday, December 21, 2020, 11:22 Adam NewsomeCraneStandard Operation  Crane Shutdown for Power OutageThe Target Hall Crane has been shut down
in preparation for the power outage tomorrow
(Dec 22). Power will be restored on Dec 23.
  