  246   Friday, February 22, 2013, 13:02 Bevan MossConditioning StationDevelopmentTM4CS Test Target #1HV test with Water Hello Ray and Yi
Completed a HV test with the water
flowing today.
 vacuum_for_40k.JPG 
  247   Friday, February 22, 2013, 13:13 Bevan MossConditioning StationDevelopmentTM4CS Test Target #1Broken Turbo Pump Today while putting the cover on
the cord that goes to the controller was
bumped. This bent the connector down and
 IMG_0528.JPG 
  259   Wednesday, March 13, 2013, 14:30 Bevan MossConditioning StationDevelopment  Faraday Cup Dave Morris and I investigated the
Faraday Cup today. It was found to be plumed
in the wrong direction (fails in). This is
  
  261   Wednesday, March 13, 2013, 15:26 Bevan MossConditioning StationDevelopmentTM4CS Test Target #1Roughing Started Roughing pumps were turned on at
15:23 13/03/2013.
  
  273   Friday, March 22, 2013, 18:49 Aurelia LaxdalConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 1Today, the commissioning of the TCS went
well. The water/vacuum interlocks were checked
OK. Then, the TCS was HV conditioned up to
  
  274   Saturday, March 23, 2013, 18:14 Aurelia LaxdalConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 2 CompletedAfter few hickups the TCS was successfuly
commissioned.
In the morning, in the middle of
  
  276   Monday, March 25, 2013, 10:59 Bevan MossConditioning StationDevelopmentTM4FEBIAD HP with Dummy TargetCommissioning TCS - Part 2 Completed

    

       
            
 IRH1511.pdfISK4574D-rev7.pdf 
  318   Wednesday, April 24, 2013, 09:00 Bevan MossConditioning StationDevelopment  New user testing Controls has created a new user group
that can operate the conditioning station
but cannot use any of the bypasses or forces.
  
  334   Thursday, May 09, 2013, 10:13 chad fisherSouth Hot-CellDevelopment  Mock-up ProgressThe source tray for the mock-up has been
setup for waterline bending and soldering/brazing.
Thanks to Travis for finding the
 IMG_1056[1].JPGIMG_1057[1].JPGIMG_1058[1].JPG 
  372   Wednesday, May 29, 2013, 12:07 chad fisherSouth Hot-CellDevelopment SiC#28 RFQRFQ AutopsyMajor portions of the RFQ target have now
been sucessfully dismantled. More minor dismantling
with conclude this afternoon.
  
  379   Thursday, June 13, 2013, 09:21 chad fisherSouth Hot-CellDevelopment  Warm Cell Mock-upthe warm cell mock-up has been inserted
into the warm cell and final preparation
for the remote test are being made.
 20130613_084421[1].jpg20130613_084426[1].jpg 
  380   Tuesday, June 18, 2013, 14:00 chad fisherSouth Hot-CellDevelopmentTM3 Mock-up testing / water block connectionsThe testing of the mock-up and tooling
has commenced.
Source tray mock-up has been driven
  
  381   Wednesday, June 19, 2013, 08:15 chad fisherSouth Hot-CellDevelopmentTM3 Mock up water block connectionsAll water block connections on the mock-up
have bben achieved. It is now ready for leak
checking.
 20130619_080806[1].jpg20130619_080808[1].jpg 
  383   Friday, June 21, 2013, 09:26 chad fisherSouth Hot-CellDevelopmentTM3 Mock-up Leak Check ResultsThe Mock-up has been leak tested after
the remote connection of the water blocks
and is leak tight!
  
  390   Thursday, June 27, 2013, 14:27 chad fisherSouth Hot-CellDevelopment  Polishing Cleaning tool - Water blocksThe polishing/cleaning tool prototype is
now finished and appers to work great.
Thanks to Dan and Maico for the great
 20130626_144941.jpg 
  391   Tuesday, July 02, 2013, 09:37 chad fisherSouth Hot-CellDevelopmentTM3 TM3 Rev.2 Source Tray DisposalTm3 Rev.2 source tary has been transfered
to the vault tunnel storage.
  
  401   Wednesday, July 17, 2013, 08:29 David WangConditioning StationDevelopmentTM3 TM3 leak check in CS without source tray.Leak checked TM3 without source tray in
CS this morning. The CS and TM3 vacuum: IG1(top
of the TM3 service cap)4.9x E-7Torr, IG2(diagnostic
  
  402   Wednesday, July 17, 2013, 10:10 David WangConditioning StationDevelopmentTM3 CS cooling and vacuum system have been turned off CS water cooling and vacuum system have
been turned off at 10:00 AM this morning.The
TM3 will be disconnected and moved to silo
  
  434   Thursday, August 29, 2013, 06:48 David WangConditioning StationDevelopmentTM3 TM3 leak check in CS with new source tray.A huge leak had been found on HS circuit
during 60 psi helium pressurize test. Other
circuits are free of obvious major leak at
 TM3_leak_check_at_CS_2013__AUG_27th.pdf 
  444   Friday, September 06, 2013, 16:41 Bevan MossSouth Hot-CellDevelopmentTM3 C-Seal crush investigation  Today Maico completed the new leak
testing tool and blank off. He tested  them
with C-seals without springs and all was
 6x 