1693
|
Wednesday, March 07, 2018, 10:36 |
David Wang | ITE/ITW Cooling | Development | | | HALCW resin can flow meter replacment | HALCW resin can flow meter replacement
is done. Less that 100 mL water was drained
to a small tray during the job. RPG checked |
|
|
2763
|
Monday, February 03, 2025, 13:10 |
David Wang | Cooling | Standard Operation | | | HALCW pump ITC:MP1 has been started. | HALCW pump ITC:MP1 has been started. water
are supplied to both ITE and ITW system.
all water signals for individual circuits |
|
|
2776
|
Friday, February 21, 2025, 09:18 |
David Wang | Cooling | Standard Operation | | | HALCW pump ITC:MP1 and MP2 phase current draw measurement. | HALCW pump ITC:MP1 and MP2 phase current
draw measurement result: water supplied to
both station. MP1: Black 17.0A, blue 16.9A, |
|
|
2433
|
Monday, April 24, 2023, 10:18 |
David Wang | Cooling | Maintenance | | | HALCW flowmeter transmotters inspetion and calibration. | ITW, ITE, ITW +ITE total , and low active
cooling water return flow meter transmitters
are inspected and calibrated. Result: |
|
|
2424
|
Wednesday, March 08, 2023, 06:32 |
David Wang | Cooling | Maintenance | | | HALCW flow sensors replacement. | HALCW flow sensors replacement job is done.
All ITE/ITW(except ITE HS) return line water
flow sensors including paddle wheels and |
|
|
2692
|
Wednesday, September 25, 2024, 07:25 |
David Wang | Cooling | Maintenance | | | HALCW O2 level sensor maintenance. | HALCW O2 level sensor annual maintenance
is done. sensor membrane has been changed
and electrolyte has been refilled. gauge |
|
|
2426
|
Wednesday, March 08, 2023, 13:57 |
David Wang | Cooling | Standard Operation | | | HALCW ITC:MP1/MP2 pump and motor temerature measurements | HALCW ITC:MP1/MP2 pump and motor temperature
measurements result:
MP1: pump discharging port: |
|
|
2425
|
Wednesday, March 08, 2023, 09:19 |
David Wang | Cooling | Standard Operation | | | HALCW ITC:MP1/MP2 motor phase current measurement. | HALCW ITC:MP1/MP2 motor phase current measurement
is done by Joel from electrician group. MP1:17.1A/17.2A/16.7A.
MP2: 17.9A/17.9A/17.3A. 19.5A |
|
|
558
|
Wednesday, November 27, 2013, 12:50 |
Bevan Moss | South Hot-Cell | Standard Operation | TM3 | | Ground devices wiring check | Travis and I completed an electrical
check on the wiring harness for the devices
on the ground plane. All lines passed 500V |
|
|
688
|
Tuesday, June 24, 2014, 15:45 |
Anders Mjos | South Hot-Cell | Standard Operation | TM3 | TiC#4 | Ground Electrode and Extraction Electrode dirty after last run | See attached pdf and DocuShare for
more photos. It may be possible to clean
some of it from the Ground Electrode. |
|
|
257
|
Wednesday, March 13, 2013, 07:22 |
chad fisher | South Hot-Cell | Repair | TM4 | | Ground Electrode Leak / Inspection Results | Further attempts to localize the leak were
unsucessful. The circuit was pressurized
with 60 psi air and snoop solution was applied |
    |
|
256
|
Tuesday, March 12, 2013, 09:18 |
chad fisher | South Hot-Cell | Repair | TM4 | | Ground Electrode Leak | On Monday, March 11 the containment box
was removed from TM4 and a vacuum leak check
preformed in an attempt to locate the leak |
|
|
258
|
Wednesday, March 13, 2013, 11:23 |
chad fisher | South Hot-Cell | Repair | TM4 | | Ground Electrode Leak | The containment box has been re-installed
and the window waterlines reconnected and
leak checked. |
|
|
696
|
Friday, June 27, 2014, 11:26 |
Anders Mjos | South Hot-Cell | Standard Operation | TM3 | | Ground Electrode Cleaned |
|
|
|
315
|
Tuesday, April 23, 2013, 15:52 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | N/A | Further HV Testing | Further HV testing was completed
today from ~2:00 until 3:00. The resistivity
of the water was 11.7 - 12.7 Mohm. The EE |
 |
|
2501
|
Friday, November 17, 2023, 11:12 |
Adam Newsome | Spent Target Vault | Standard Operation | | | Four pails moved from main storage to mini storage | The following four pails were moved from
the main storage vault to the mini storage
vault, to stage for shipping in Jan. 2024: |
|
|
1529
|
Tuesday, May 09, 2017, 07:00 |
David Wang | Conditioning Station | Repair | TM3 | | Follow up Aurelia's entry, TM3 and TCS current limits investigation. | Aurelia and I investigated this current
limit issue May 8th. First, By separating
TM3 from TCS. we found the problem is on |
|
|
639
|
Friday, April 04, 2014, 16:59 |
Anders Mjos | ITW | Development | | | Flow meters installed on Heat Shield and Coil water return | David W. has installed two SST Proteus
flow meters, model OV7006FTA32, on ITW Heat
Shield and Coil. The flow meters are connected |
|
|
651
|
Wednesday, April 16, 2014, 10:16 |
Anders Mjos | ITW | Development | TM3 | Ta#42 | Flow meters installed on Heat Shield and Coil water return |
|
|
|
682
|
Friday, June 13, 2014, 10:33 |
Anders Mjos | ITW | Development | TM1 | UC#9 | Flow meter data | Coil not used on TM1. Data and plots on DocuShare
Friday, June 13, 2014, 10:30. ITE |
|