12
|
Tuesday, October 16, 2012, 19:50 |
Grant Minor | M9 | Repair | M9T2 Joint Repair - Status Update 16 Oct 2012 | See attached. |
|
|
10
|
Monday, October 15, 2012, 17:03 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Today:
- Removed pins and removed indium
through ring. Joint fully open at 14.5 to |
|
|
13
|
Thursday, October 18, 2012, 08:26 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Yesterday:
Installed indium blank off at M9
T2 joint and pumped down at 15:20 to 15:45 |
|
|
14
|
Thursday, October 18, 2012, 16:28 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Today:
Completed leak check of M9 T2 area:
joint(s) are He leak tight. Remote He lines |
|
|
50
|
Tuesday, March 12, 2013, 16:33 |
Keith C Ng | M9 | Maintenance | M9 T2 flange blank off, preparation | Scraped M9 T2 flange, removed what little
indium was left on flange.
- Completed two passes, some indium |
|
|
49
|
Thursday, March 07, 2013, 08:35 |
Keith C Ng | M9 | Repair | M9 T2 flange blank off | Work on blank off of M9 T2 started: Cleared
away blocks making up bagging bunker. R.
Kuramoto took some initial photos of the |
|
|
55
|
Wednesday, April 10, 2013, 16:20 |
Keith C Ng | M9 | Repair | M9 T2 flange blank off | Continued with work on T2 M9 exit port
and area; Vacuum started after 13:00 hours
(due to vacuum pump issues at T2). He leak |
|
|
17
|
Monday, October 22, 2012, 15:48 |
Keith C Ng | M9 | Repair | M9 T2 clean up and shield restoration | Today;
Restoring shielding at M9 T2 area
and cleaning up RH setup. |
|
|
51
|
Wednesday, March 13, 2013, 16:21 |
Keith C Ng | M9 | Maintenance | M9 T2 blanking off preparation | 1. Re-scraped M9 T2 flange after reviewing
video of flange.
- Some indium remains on inside of |
|
|
18
|
Wednesday, October 24, 2012, 11:53 |
Keith C Ng | M9 | Repair | M9 T2 blank off complete | Shielding around m9 t2 restored as of 11:45,
vacuum levels still the same since 19 October.
- Work permit returned. |
|
|
9
|
Friday, October 12, 2012, 15:12 |
Keith C Ng | M9 | Repair | M9 T2 Joint Repair cont. | Joint repair continues.
Leak Check: |
|
|
15
|
Friday, October 19, 2012, 16:48 |
Keith C Ng | M9 | Repair | M9 T2 Joint Repair cont. | Today:
Cleaned up work site and removed
extraneous poles and tooling. Radioactive |
|
|
53
|
Tuesday, March 26, 2013, 09:04 |
Keith C Ng | M9 | Repair | M9 Q1Q2 void inspection | Yesterday: did visual, video inspection
and still imaging of T2 M9 Q1Q2 void. G.
Morris came down to work site for visual |
|
|
128
|
Monday, August 10, 2020, 16:08 |
Keith C Ng | M9 | Development | M9 Q1Q2 magnet assembly installed in pit | The M9 Q1Q2 magnet assembly was installed
in the M9 beam line today.
Attached to elog is an inspection |
|
|
48
|
Tuesday, March 05, 2013, 14:15 |
Keith C Ng | M9 | Maintenance | M9 Q1, 2 removal | Removed M9 Q1 Q2 from beam line 1A via
crane and transferred from beam line to radiation
waste storage. |
7x |
|
31
|
Friday, February 01, 2013, 14:15 |
Keith C Ng | Primary Beamlines | Maintenance | M9 Q1 Q2; storage pit assessment | Uncovered radioactive waste storage pit
to see contents. Assessing viability of moving
contents inside to facilitate storage of |
|
|
35
|
Thursday, February 07, 2013, 16:02 |
Keith C Ng | M9 | Repair | M9 Q1 Q2 removal, site prepration | Started work on removing M9 Q1 Q2 magnets;
area clean up and preparation, removing shielding
above Q1 and Q2 and remote handling setup |
|
|
36
|
Friday, February 08, 2013, 15:31 |
Keith C Ng | M9 | Repair | M9 Q1 Q2 removal, site prepration | Completed remote handling/shielding setup
over T2 M9, see photos for setup.
- Rad levels at 16' above Q2 were |
|
|
45
|
Wednesday, February 27, 2013, 16:15 |
Keith C Ng | M9 | Maintenance | M9 Q1 Q2 removal, rad waste pit prep | Radioactive waste pit uncovered, red barrel
with unknown contents taken out for assessment.
R. Ralea from RPG determined barrel was too |
|
|
37
|
Wednesday, February 13, 2013, 15:49 |
Keith C Ng | M9 | Maintenance | M9 Q1 Q2 removal, preparation | Local and remote leak checks on M9 T2 area
were done today to confirm leak; Leak was
still present at T2 M9 joint. M9 Q1 and Q2 |
|