Message ID: 17     Entry time: Monday, October 22, 2012, 15:48
Author: Keith C Ng 
Category: M9 
Type: Repair 
Subject: M9 T2 clean up and shield restoration 

Today;

Restoring shielding at M9 T2 area and cleaning up RH setup.

 

- RH workbench, pole tray and bridges removed from work site.

- 18' x 6' by 3' bridging block removed (at 14:25) to reveal the T2 monument. No apparent change in vacuum, will monitor as shielding is restored.

- Magnet power tests completed by beamlines group, no issues reported.

- Rubber testing ring installed between M9 Q1 and T2, see photo.

- Spring eye gaps appear to be the same as on Friday (after 48h), see photos and video.

 

Work continues re covering the M9 T2 site tomorrow.

Attachment 1: 20121022_RH1_02_0092.JPG  3.843 MB  | Show | Hide all
Attachment 2: 20121022_RH1_02_0081.JPG  3.811 MB  | Show | Hide all
Attachment 3: 20121022_RH1_02_0082.JPG  3.727 MB  | Show | Hide all
ELOG V2.9.2-2455