  12   Tuesday, October 16, 2012, 19:50 Grant MinorM9RepairM9T2 Joint Repair - Status Update 16 Oct 2012

See attached.

Attachment 1: M9T2_Joint_Repair_-_Status_Update_16_Oct_2012.pdf
M9T2_Joint_Repair_-_Status_Update_16_Oct_2012.pdf
  10   Monday, October 15, 2012, 17:03 Keith C NgM9RepairM9 T2 joint repair cont.

Today:

- Removed pins and removed indium through ring. Joint fully open at 14.5 to 15 turns of retraction mechanism.

- Did initial video inspection of T2 and Q1 flanges, some residual indium on knife surfaces, did initial scraping of T2 flange. (see videos on RH group folder)

- One blank off prepared with indium ready for installation.

 

Will continue tomorrow with Q1 scrape and re inspection.

  13   Thursday, October 18, 2012, 08:26 Keith C NgM9RepairM9 T2 joint repair cont.

Yesterday:

Installed indium blank off at M9 T2 joint and pumped down at 15:20 to 15:45 overnight. 1ACG7 (T2 vacuum pressure) reads between 6.0E-3mT and 2.0E-2 mT as of 8:15 today.

- Before installing, an attempt was made to set the bellows in a position to correct for some of the misalignment. This was done by closing the joint with no ring and pinning the east flange ear and leaving it for ~1 hour.

- Blank off installation began at 12:30

- A universal joint installation tool was used to install the East pin. This was due to the very small gap available to install the pin on the East side. The east side of the flange was also pried upon in order to close the east side of the joint. As a result the pin leans North once installed. West pin was installed with no issues.

- Installation finished at 14:30 (roughly two hours, not including flange prep work)

- An inspection after installation revealed the lower lug to be in tension an hour after installation of the pins and blank off.

- Spring eye gaps on installation appeared to be 0.05" to 0.06" on the west side and ~0.2" on the east side.

 

Will be doing inspection and leak check later today.

  14   Thursday, October 18, 2012, 16:28 Keith C NgM9RepairM9 T2 joint repair cont.

Today:

Completed leak check of M9 T2 area: joint(s) are He leak tight. Remote He lines checked as well, see attached.

 

- Indium blank off ring was cut free from the string tethers.

- Removed extra tooling and equipment, West side pin threaded cap installed. East side needs new capping device since the lean of the pin is beyond installation parameters.

- Vacuum pressure still running higher than normal but stable (see previous e log).

- Water leak in the M9 Q2 magnet return header was discovered. Very slow leak (> 10 minutes per drop). See attached photo and videos on RH group drive.

 

Cleanup continues tomorrow.

Attachment 1: T2_Remote_Leak_Check.PDF
T2_Remote_Leak_Check.PDF
Attachment 2: 20121018_m9q2_waterleak.jpg
20121018_m9q2_waterleak.jpg
  50   Tuesday, March 12, 2013, 16:33 Keith C NgM9MaintenanceM9 T2 flange blank off, preparation

Scraped M9 T2 flange, removed what little indium was left on flange.

- Completed two passes, some indium still remains on flange. R. Kuramoto deems this sufficient for now.

- Scraping tool did not fit properly over flange, was forced into place and had to be pried off when scraping finished.

- Will temporarily blank off with rubber sealed blank off plate until area is cleaned of debris. Semi permanent blank off to be installed by end of week.

- See videos of flange scraping in Remote Handling group folder.

  49   Thursday, March 07, 2013, 08:35 Keith C NgM9RepairM9 T2 flange blank off

Work on blank off of M9 T2 started: Cleared away blocks making up bagging bunker. R. Kuramoto took some initial photos of the M9 T2 area post Q1Q2 removal; See Remote Handling network drive for photos.

G. Morris posted photos of M9 Q1Q2 just after removal from beam line 1A. Click here for link: http://trshare.triumf.ca/~gmorris/BL1A/M9/2013.3.5/

  55   Wednesday, April 10, 2013, 16:20 Keith C NgM9RepairM9 T2 flange blank off

Continued with work on T2 M9 exit port and area; Vacuum started after 13:00 hours (due to vacuum pump issues at T2). He leak checked flange at 14:30, determined to be He leak tight. Vacuum pressure as of 14:45 in T2 volume (1ACG7) was at 36mT.

  17   Monday, October 22, 2012, 15:48 Keith C NgM9RepairM9 T2 clean up and shield restoration

Today;

Restoring shielding at M9 T2 area and cleaning up RH setup.

 

- RH workbench, pole tray and bridges removed from work site.

- 18' x 6' by 3' bridging block removed (at 14:25) to reveal the T2 monument. No apparent change in vacuum, will monitor as shielding is restored.

- Magnet power tests completed by beamlines group, no issues reported.

- Rubber testing ring installed between M9 Q1 and T2, see photo.

- Spring eye gaps appear to be the same as on Friday (after 48h), see photos and video.

 

Work continues re covering the M9 T2 site tomorrow.

Attachment 1: 20121022_RH1_02_0092.JPG
20121022_RH1_02_0092.JPG
Attachment 2: 20121022_RH1_02_0081.JPG
20121022_RH1_02_0081.JPG
Attachment 3: 20121022_RH1_02_0082.JPG
20121022_RH1_02_0082.JPG
  51   Wednesday, March 13, 2013, 16:21 Keith C NgM9MaintenanceM9 T2 blanking off preparation

1. Re-scraped M9 T2 flange after reviewing video of flange.

- Some indium remains on inside of counter bore of flange, indium hard to remove due to current tooling.

 

2. Installed rubber spring loaded blank off flange to prevent debris from entering M9 T2 port.

- Will be removed once Q1Q2 void is cleaned and indium blank off plate is tested and prepared for use.

 

3. Continued cleaning of M9 Q1Q2 void.

- Attempted to wipe residue from bottom dead center of B1 15"knife  flange.  Did not fully clean, R. Kuramoto observed a thick viscous residue, "like tar"

- Started vacuuming of M9 Q1Q2 void

  18   Wednesday, October 24, 2012, 11:53 Keith C NgM9RepairM9 T2 blank off complete

Shielding around m9 t2 restored as of 11:45, vacuum levels still the same since 19 October.

- Work permit returned.

- A dose record of the job is attached as a spread sheet. Total dose for all workers is 1.89 mSv for the job.

- A Small gap in shielding near T1 filled in by plant group in addition to the shielding restoration (neutron radiation).

Attachment 1: 201211_m9t2repair.xlsx
  9   Friday, October 12, 2012, 15:12 Keith C NgM9RepairM9 T2 Joint Repair cont.

Joint repair continues.

 

Leak Check:

- Local leak check performed around area of T2, M9-Q1. All seals other than T2 Q1 were leak tight. Largest source of leak was the T2 Q1 joint area.

- Leak check done in quadrants around joint, response times were <2 sec of applying helium. Leak detector also responded when He probe was near joint (before actually applying He).

 

Video and Physical inspection:

- Bottom weld lug bolt found in tension/captive (ie. not free to move). Confirmed static by poking bolt. (Videos of this in RH group folder).

- Top weld lug had > 0.2" of gap.

- East and West pins seen leaning slightly toward North (toward Q1).

 

Loading Test:

At 13:30 a load test was performed to observe the effects of loading nearby blocks around T2 (see photo). Two 12 x 6 x 3 shield blocks were stacked one on top of the other and vacuum was observed, one then the other. There was no observable effect on the vacuum each time. Bottom weld lug bolt was still frozen when poked.

Blocks were replaced to their original locations once test was complete.

 

The T2 volume was vented at ~14:15 in preparation for disassembly to be performed on Monday.

 

Attachment 1: 20121012_RH2_01_0002.JPG
20121012_RH2_01_0002.JPG
Attachment 2: 20121012_RH2_01_0004.JPG
20121012_RH2_01_0004.JPG
  15   Friday, October 19, 2012, 16:48 Keith C NgM9RepairM9 T2 Joint Repair cont.

Today:

Cleaned up work site and removed extraneous poles and tooling. Radioactive parts stored in lead flask now located on TNF.

- Two pins, an RH bullet bolt and indium ring (tb22148) were put into lead flask for storage, flask now located on TNF.

- Took photos of spring eye gaps and some video inspection, looks roughly the same as yesterday (see photos).

- Installed a dust cover over the east spring pin (see photos).

 

Looking at placement of indium rings loaded with EPDM and Buna N at joint for radiation exposure. Will install the test rig on Monday & clean up site for covering up.

Attachment 1: 20121019_RH1_01_0081.JPG
20121019_RH1_01_0081.JPG
Attachment 2: 20121019_RH1_01_0082.JPG
20121019_RH1_01_0082.JPG
Attachment 3: 20121019_RH2_02_0004.JPG
20121019_RH2_02_0004.JPG
  53   Tuesday, March 26, 2013, 09:04 Keith C NgM9RepairM9 Q1Q2 void inspection

Yesterday: did visual, video inspection and still imaging of T2 M9 Q1Q2 void. G. Morris came down to work site for visual inspection, noticed and was concerned about a few of the shielding blocks that were "contacting" the T2 monolith. Of note are the known "crumbling blocks" directly North and West of the T2 monolith and the pointy shielding block (2MB2, DWG# D-3399) North of the monolith which sits on top of a crumbling block. It was not certain if these shielding blocks were touching the monolith but there was no visible gap. See photos.

20130325_t2m9q1q2void_RHB_5726.JPG20130325_t2m9q1q2void_RHB_5728.JPG

 

 

Also installed an aluminum sheet metal dust cover over open B1 15" flange. See photo.

20130325_t2m9q1q2void_RHB_5742.JPG

 

 

 

Photos are located on: \\trwindata\groups\remote handling\Photos\2013\2013_m9q1q2_void

Videos are located on: \\trwindata\groups\remote handling\Videos\2013\2013_m9q1q2_inspection

  128   Monday, August 10, 2020, 16:08 Keith C NgM9DevelopmentM9 Q1Q2 magnet assembly installed in pit

The M9 Q1Q2 magnet assembly was installed in the M9 beam line today. 

Attached to elog is an inspection report of the indium ring that will be used in the M9 T2 Q1 joint.

Attachment 1: RHB_9237.JPG
RHB_9237.JPG
Attachment 2: 20200810_indiumringinspectionreport.pdf
20200810_indiumringinspectionreport.pdf 20200810_indiumringinspectionreport.pdf 20200810_indiumringinspectionreport.pdf 20200810_indiumringinspectionreport.pdf 20200810_indiumringinspectionreport.pdf
  48   Tuesday, March 05, 2013, 14:15 Keith C NgM9MaintenanceM9 Q1, 2 removal

Removed M9 Q1 Q2 from beam line 1A via crane and transferred from beam line to radiation waste storage.

Magnet craned out of position in front of T2 monolith and then placed into bunker next to work site.

- Bunker pre-lined with plastic enough to envelope magnet.

20130305_m9q1q2remove_IMG_0323.JPG

 

Magnet craned over to radioactive storage and landed in south end of storage pit.

- Magnet did not sit on pit floor.

- Supported by a length of pipe on west of pit floor, Q1 leaning against south of pit wall and alignment bracket braced against a magnet on the east side of pit. See photos.

20130305_m9q1q2remove_IMG_0324.JPG20130305_m9q1q2remove_IMG_0328.JPG20130305_m9q1q2remove_IMG_0331.JPG

20130305_m9q1q2remove_IMG_0332.JPG20130305_m9q1q2remove_IMG_0330.JPG

 

 

 

Attachment 6: 20130305_m9q1q2remove_IMG_0329.JPG
20130305_m9q1q2remove_IMG_0329.JPG
  31   Friday, February 01, 2013, 14:15 Keith C NgPrimary BeamlinesMaintenanceM9 Q1 Q2; storage pit assessment

Uncovered radioactive waste storage pit to see contents. Assessing viability of moving contents inside to facilitate storage of M9 Q1 Q2 magnet. See below for some photos.

20130201_radwastepit_P1020704.JPG20130201_radwastepit_P1020720.JPG

20130201_radwastepit_P1020736.JPG20130201_radwastepit_RHB_5449.JPG

Additional photos are on the remote handling group drive.

  35   Thursday, February 07, 2013, 16:02 Keith C NgM9RepairM9 Q1 Q2 removal, site prepration

Started work on removing M9 Q1 Q2 magnets; area clean up and preparation, removing shielding above Q1 and Q2 and remote handling setup over magnet (moving blocks).

 

1. Covered T2 cooling package and top of monolith with plastic sheeting.

- In addition covered 1A triplet shielding as well.

- Installed 1AS1 18' shield block after sheeting was laid down.

20130207_m9q1q2remove_IMG_0155.JPG20130207_m9q1q2remove_IMG_0162.JPG

 

2. Discovered 1A Q14 indium ring thermocouple (TW# B1-378) & thermocouple coil circuit #1 (TW# B1-379) had cable insulation damage. Damage was down to bare wire.

- Wires located under east side of cooling package. See photo.

- Wires repaired with black electrical tape.

20130207_m9q1q2remove_IMG_0154.JPG20130207_m9q1q2remove_IMG_0157.JPG

  

3. Vacuum started on T2 volume @ 10:47, roughing pump only.

- @ 11:15 vacuum pressure leveled off at 1.5 T (1ACG4 reading). 11:15.

- @ 13:30 the roughing pump blower package was turned on.

- @14:45 vacuum level steady at 250 mT (1ACG4 reading) .

 

4. Uncovered and partially set up over T2 M9, Q1 Q2.

- This setup is similar to 2011 and 2012 setups.

- 1A Q12 and 13 were uncovered during setup and a visual check for water leaks was done. None were found.

- Setup uses two 12' x 6' x 4' blocks with 18' x 6' x 4' resting on top, spanning the joint; See photo.

- Will continue with set up next day.

 

20130207_m9q1q2remove_IMG_0165.JPG

  36   Friday, February 08, 2013, 15:31 Keith C NgM9RepairM9 Q1 Q2 removal, site prepration

Completed remote handling/shielding setup over T2 M9, see photos for setup.

- Rad levels at 16' above Q2 were 1.2 mSv/h. Shielding was built up to 20' level, same as the opposite side to minimize exposure.

20130208_m9q1q2remove_IMG_0172.JPG

20130208_m9q1q2remove_IMG_0174.JPG20130208_m9q1q2remove_IMG_0175.JPG

  45   Wednesday, February 27, 2013, 16:15 Keith C NgM9MaintenanceM9 Q1 Q2 removal, rad waste pit prep

Radioactive waste pit uncovered, red barrel with unknown contents taken out for assessment. R. Ralea from RPG determined barrel was too active to be removed from pit and therefore replaced into storage pit.

M. Kinakin took the aluminum samples from the two indium test rings and the stainless steel bolt taken from Q1 for analysis. Will return the stainless steel bolt when finished.

  37   Wednesday, February 13, 2013, 15:49 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparation

Local and remote leak checks on M9 T2 area were done today to confirm leak; Leak was still present at T2 M9 joint. M9 Q1 and Q2 power supply leads were disconnected (C. Yee). Next task is to find the ground fault on the Q1 magnet.

Indium one piece blank off plate (TB22267) for blanking off assembly (TB22265) was submitted into shop today.