Message ID: 105     Entry time: Thursday, March 16, 2017, 15:50
Author: Keith C Ng 
Category: Primary Beamlines 
Type: Repair 
Subject: collimator b transition to t2 

On Monday found leaking joint was the ring directly downstream of T2. Vacuum group has been spraying Vacseal (http://www.vacseal.net/Pages/default.aspx) sealant over the last 3 days attempting to get it in between the flanges and have partial vacuum to draw in the fluid. Seven sprays have been completed as of March 16th.

Tomorrow, 2 more applications will be made and then Vacuum group will pump the T2 volume over the weekend.