Message ID: 108     Entry time: Wednesday, January 31, 2018, 15:28
Author: Keith C Ng 
Category: Primary Beamlines 
Type: Repair 
Subject: Q15 repair 

Beamlines has changed out another 2 insulators on Q15 after discovering two additional leaks. Insulators #2 & #4 were replaced. One of them failed on installation (broken ceramic?)  and was replaced by another stocked replacement. Magnet was pressure tested and now enegerized as part of power testing. Doug P. expects repairs to be complete and to cover up the area by tomorrow.