Entry  Friday, February 22, 2013, 17:27, Keith C Ng, M9, Repair, M9 Q1 Q2 removal, Q2 joint dissassembly 20130222_m9q1q2remove_P1020840.JPG20130222_m9q1q2remove_P1020832.JPG20130222_m9q1q2remove_P1020831.JPG
M9 Q2 15" pin drive was removed and disconnected.
- Pin drive retention screw had to be completely removed to be able to remove pin drive completely.
- Had to make tools to remove pin drive and retention screw, see photos.
Entry  Monday, February 25, 2013, 16:37, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, Q2 seal disassembly 7x
Removed Q2 15" indium seal ring, discovered seal contained rubber on both sides instead of indium.
- Some kind of oil residue seen at the bottom of the sealing ring and inside of the Q2 vacuum box. (Note: Oil residue was from downstream vacuum
roughing pumps. They were connected when T2 M9 joint was leaking. Oil got into the vacuum pump back streamed into the beam line.)
Entry  Wednesday, February 27, 2013, 16:15, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, rad waste pit prep 
Radioactive waste pit uncovered, red barrel with unknown contents taken out for assessment. R. Ralea from RPG determined barrel was too active to be
removed from pit and therefore replaced into storage pit.
M. Kinakin took the aluminum samples from the two indium test rings and the stainless steel bolt taken from Q1 for analysis. Will return the stainless
Entry  Friday, March 01, 2013, 15:28, Keith C Ng, M9, Maintenance, Radadioactive Waste Pit Organizing 20130301_radwastepit_P1020865.JPG20130301_radwastepit_P1020869.JPG20130301_radwastepit_P1020873.JPG
Successfully stacked old m20 q2 q2 magnet assembly on top of old M9 Q1 Q2 magnet and M11 septum magnet. See photos.
- Done to create room for current m9 Q1,2 magnet.
- Used 6' remote handling bridge on north end of open pit for shielding.
Entry  Monday, March 04, 2013, 16:48, Keith C Ng, M9, Maintenance, M9 Q1 Q2 removal, preparation 6x
Preparing for M9 Q1,2 move:
1. Re-arranged/organized cables on top of magnet.
Entry  Tuesday, March 05, 2013, 14:15, Keith C Ng, M9, Maintenance, M9 Q1, 2 removal 7x
Removed M9 Q1 Q2 from beam line 1A via crane and transferred from beam line to radiation waste storage.
Magnet craned out of position in front of T2 monolith and then placed into bunker next to work site.
- Bunker pre-lined with plastic enough to envelope magnet.
Entry  Thursday, March 07, 2013, 08:35, Keith C Ng, M9, Repair, M9 T2 flange blank off 
Work on blank off of M9 T2 started: Cleared away blocks making up bagging bunker. R. Kuramoto took some initial photos of the M9 T2 area post Q1Q2 removal;
See Remote Handling network drive for photos.
G. Morris posted photos of M9 Q1Q2 just after removal from beam line 1A. Click here for link: http://trshare.triumf.ca/~gmorris/BL1A/M9/2013.3.5/
Entry  Tuesday, March 12, 2013, 16:33, Keith C Ng, M9, Maintenance, M9 T2 flange blank off, preparation  
Scraped M9 T2 flange, removed what little indium was left on flange.
- Completed two passes, some indium still remains on flange. R. Kuramoto deems this sufficient for now.
- Scraping tool did not fit properly over flange, was forced into place and had to be pried off when scraping finished.
Entry  Wednesday, March 13, 2013, 16:21, Keith C Ng, M9, Maintenance, M9 T2 blanking off preparation  
1. Re-scraped M9 T2 flange after reviewing video of flange.
- Some indium remains on inside of counter bore of flange, indium hard to remove due to current tooling.
 
Entry  Wednesday, March 20, 2013, 08:59, Keith C Ng, Primary Beamlines, Development, T2 M9 off beamline activities 
Yesterday:
Did vacuum testing on MK2 8" indium blank off; installed w/indium on test stand and put under vacuum.
- After 1 turn on spring eye nuts, a soft vacuum seal was achieved but the throttle valve (old leak detector) could not be opened. Spring eye nuts
Entry  Tuesday, March 26, 2013, 09:04, Keith C Ng, M9, Repair, M9 Q1Q2 void inspection 20130325_t2m9q1q2void_RHB_5726.JPG20130325_t2m9q1q2void_RHB_5728.JPG20130325_t2m9q1q2void_RHB_5742.JPG
Yesterday: did visual, video inspection and still imaging of T2 M9 Q1Q2 void. G. Morris came down to work site for visual inspection, noticed and was
concerned about a few of the shielding blocks that were "contacting" the T2 monolith. Of note are the known "crumbling blocks" directly
North and West of the T2 monolith and the pointy shielding block (2MB2, DWG# D-3399) North of the monolith which sits on top of a crumbling block. It was
Entry  Tuesday, April 09, 2013, 16:41, Keith C Ng, M9, Maintenance, T2 M9 exit port blank off 20130409_t2m9blankoff_RHB_5782.JPG20130409_t2m9blankoff_RHB_5783.JPG20130409_t2m9blankoff_RHB_5784.JPG20130409_t2m9blankoff_RHB_5785.JPG
Blanked off T2 M9 exit port with indium seal blank off.
 
1. Removed temporary rubber blank off from T2 flange.
Entry  Wednesday, April 10, 2013, 16:20, Keith C Ng, M9, Repair, M9 T2 flange blank off 
Continued with work on T2 M9 exit port and area; Vacuum started after 13:00 hours (due to vacuum pump issues at T2). He leak checked flange at 14:30,
determined to be He leak tight. Vacuum pressure as of 14:45 in T2 volume (1ACG7) was at 36mT.
Entry  Thursday, April 11, 2013, 15:43, Keith C Ng, M9, Repair, T2 M9 exit port temporary shielding 10x
Installed shielding stand (TSH0094) for T2 M9 exit port as per drawing TSH0095; three steel blocks in total were lowered into the T2 M9 void. See photos.
Started to tear down RH  setup after shielding was lowered into place.
Entry  Thursday, December 12, 2013, 14:21, Keith C Ng, Primary Beamlines, Repair, T2 suck tube active/contaminated water removal 
Removed "suck tube" filled with active/contaminated water from top of 1A beam line blocks to meson extension hall warm cell lab. Highest activity
recorded was measured at 22mSv on contact, 2000µSv @ 1/2 m. Tube was bagged and craned over to warm cell lab for temporary storage and will be dealt
with at a later date. See work permit  2013-12-12-2 for more details.
Entry  Wednesday, January 14, 2015, 11:00, Keith C Ng, Primary Beamlines, Maintenance, 1VQ4 & 1VQ6 beamtube removal (WR #2686) 
Disconnected and removed beam tube from 1VQ4, 5, 6.  

- Q6 end had transition end removed with pin drive driven into the retracted position and left behind but indium joint was still intact.
Entry  Friday, January 23, 2015, 15:21, Keith C Ng, Primary Beamlines, Maintenance, 1VQ4 joint section (WR #2686)  20150123_ucnbuild_IMG_1197.JPG20150123_ucnbuild_IMG_1202.JPG20150123_ucnbuild_IMG_1205.JPG20150123_ucnbuild_IMG_1207.JPG20150123_ucnbuild_IMG_1209.JPG
1VQ4 & 1VQ6 beamtube was installed by UCN group. RH provisonally installed aluminum indium carrier ring with no indium into joint space with clamping
collar and pin drive. Joint is currently connected but not vacuum tight. Joint will be sealed with indium at a later date, tbd.
 
Entry  Tuesday, February 03, 2015, 16:35, Keith C Ng, Primary Beamlines, Development, UCN T1 shutdown work INBOX)3363.jpegINBOX)33632.jpeg
RH bridge has been set up over T1 to Q1Q2 area, see images for radiation survey of work area. Joint is still intact, work will commence tomorrow.

Entry  Wednesday, February 04, 2015, 16:12, Keith C Ng, Primary Beamlines, Development, UCN T1 shutdown work 
UCN T1 work continues:
- Retracted Q1 T1 pindrive, took 34.5 turns. Pins left bolted to T1 monument.
Entry  Thursday, February 05, 2015, 16:06, Keith C Ng, Primary Beamlines, Development, T1 Q1Q2 blank off work 20150205_ucnbuild_IMG_1229.JPG20150205_ucnbuild_IMG_1228.JPG20150205_ucnbuild_IMG_1225.JPG0temp_bellowsblocker.JPG
Work continues on T1 M13Q1 joint:
- Discovered some sort of vacuum box brace restricting the collapse of the vacuum box when the air cylinders were actuated. Upon closer observation
the air cylinders appear to work, unsure if the "retract" and "extend" port markings work as labeled.