12
|
Friday, February 06, 2015, 13:32 |
Isaac Earle | 100KW Beam Dump | Development | TEL5079 Hose Modification | When the EHDT shielding service stand shield
plug was installed in January it was found
that the Beam Dump Outlet Hose (TEL5079) |
|
13
|
Friday, March 20, 2015, 11:45 |
Isaac Earle | 100KW Beam Dump | Development | Lower Half of BD EHDT Shielding Installed | The lower half of the beam dump EHDT
shielding was installed yesterday by Plant
Group. After installation of the service |
|
14
|
Friday, April 17, 2015, 14:37 |
Isaac Earle | 100KW Beam Dump | Development | RH Clamp Delivered to Beamlines Group | A 4" Remote Handling Marman
Flange Clamp was delivered to Doug Preddy
today to be used to clamp the EHDT beam pipe |
|
15
|
Wednesday, May 06, 2015, 14:19 |
Isaac Earle | 100KW Beam Dump | Development | EHDT Beam Pipe Section Installed | - On May 4th the EHDT beam pipe section
was installed by Mike Vogel of Beamlines
Group |
|
16
|
Thursday, May 07, 2015, 16:23 |
Isaac Earle | 100KW Beam Dump | Development | RH Clamp Installed with Used Seal | The remote handling 4" marman flange
clamp was reinstalled today with a used seal.
It is "Clamp B" as tested |
|
17
|
Friday, May 15, 2015, 11:06 |
Isaac Earle | 100KW Beam Dump | Development | BD and Upper Pb Shield Water Hoses Replaced | The beam dump and upper lead shield
flexible hose assemblies have been replaced
with smaller diameter versions to allow for |
|
18
|
Thursday, May 28, 2015, 16:08 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Vac Seal RH Test & Installation | The following work was performed on
May 27 & 28, 2015:
- The beam dump 10kW Remote Handling |
|
19
|
Tuesday, June 02, 2015, 16:42 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Water Block RH Test & Installation | Beam dump waterblocks #1 (BD
Inlet) and #3 (Upper Pb Inlet) were removed |
|
20
|
Monday, June 08, 2015, 15:15 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Vacuum Leak | - On Thurdsay June 4th the EHDT beamline
section was vented by Vacuum Group so that
they could install a new pump |
|
21
|
Monday, June 08, 2015, 15:23 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Seal Re-Install | On Monday June 8 the following work
was performed by Isaac Earle and Keith Ng:
- EHDT beamline vented |
|
22
|
Wednesday, June 10, 2015, 14:57 |
Isaac Earle | 100KW Beam Dump | Development | BD Water System Leak Test | A leak test was performed on the beam dump
water system on June 9 in the afternoon.
- Pipe segments tested: The entire |
|
23
|
Friday, June 12, 2015, 10:16 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Vac Seal Vent & Test | - Vacuum has been pumping steadily on the
EHDT section since June 8, reaching 3.2E-8
Torr at 8am today (June 12) |
|
24
|
Monday, June 15, 2015, 17:08 |
Isaac Earle | 100KW Beam Dump | Development | E-Dump Shielding Installation | - The hoist rings were removed from the
upper lead shield
- Two standard lock-blocks were installed |
|
25
|
Wednesday, June 24, 2015, 15:19 |
Isaac Earle | 100KW Beam Dump | Development | Remainder of BD Shielding Installed | The location of the already installed blocks
including the TSH0392 protruding lift bails
were remeasured, and it was found that modification |
|
26
|
Tuesday, November 03, 2015, 13:15 |
Isaac Earle | 100KW Beam Dump | Development | Initial tests of beam dump water system controls | During the maintenance period today the
E-Hall tunnel was accessed to begin controls
tests on the beam dump water system and initial |
|
28
|
Thursday, April 07, 2016, 11:25 |
Isaac Earle | 100KW Beam Dump | Development | Result of VCR Gasket Corrosion Test | In August 2014 gasket corrosion tests
were prepared by placing a 1" Swagelok
VCR gasket in a 500mL beaker with de-ionized |
|
33
|
Tuesday, May 02, 2017, 16:52 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender stand hardened parts tested | Hardness testing was performed on
1 sample each of parts TBP1822 and TBP1823
(part of the 35-deg magnet stand assembly |
|
35
|
Thursday, June 01, 2017, 15:25 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender adjustment blocks modified to fit magnet | Adjustment blocks were installed on the
second dipole bender today (labeled "No.
03" "C15-III-57/15"). The |
|
36
|
Monday, June 05, 2017, 16:16 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender stand assembly complete | Assembly
of two complete bender stands was completed |
14x |
37
|
Wednesday, June 28, 2017, 17:37 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender "No. 1" installed on magnet stand | BL4N 35-deg bender magnet "No.
1" has been installed onto the magnet
stand with "stand leg" configuration |
|