Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_2, Page 8 of 34  Not logged in ELOG logo
ID Date Author Target Material Target Oven W.O# Source Status Subject Text Attachments
  539   Thursday, March 25, 2021, 07:57 Aaron Schmidt    Re - Ta test. Leak check.Thursday, March 25, 2021, 07:55: Vacuum
@ 5.12e-07T. Waterlines opened.
  
  538   Tuesday, March 23, 2021, 11:28 Marla CervantesEmpty44489-6 DoneRe-coating test 3Objective: Coating the inner surface of
a short tantalum boat with rhenium.
Result:
  
  537   Tuesday, March 23, 2021, 08:07 Aaron Schmidt    Re - Ta test. Leak check. Modified HS installed with new brackets
as per Marla.
Tuesday, March 23, 2021, 08:02: Vacuum
  
  536   Tuesday, March 16, 2021, 08:29 Darwin Ortiz RosalesTaC TARGET BOATDonesintering of TaC on Caps and springs Tuesday, March 16, 2021, 08:28 
Each endcap is separated with
  
  535   Tuesday, March 09, 2021, 11:54 Darwin Ortiz RosalesTaC42464-1HP-FEBIADDoneTaC coating/sinteringTuesday, March 09, 2021, 11:54 
 Container coated with
  
  534   Friday, March 05, 2021, 10:48 Darwin Ortiz RosalesTaC44691-1LP-SISDoneTaC coating/sintering Friday, March 05, 2021, 10:47
Ta tube was coated with TaC
 2021-03-07_090107-44691-1_Tac_Sintering.png 
  533   Tuesday, March 02, 2021, 11:32 Darwin Ortiz RosalesTaC44691-5LP-SISDoneTaC coating/sinteringTuesday, March 02, 2021, 11:26 
Ta tube was coated with TaC
  
  532   Monday, March 01, 2021, 13:58 Aaron Schmidt    Flex - line HS installedFlex-Line HS had been fully scrubbed out
earlier. All gaskets replaced.
Empty. Quick check for leaks.
  
  531   Friday, February 26, 2021, 09:28 Ferran Boix PamiesEmptynone DoneParasitic target thermal tests Tests were performed with external
power supply. No target boat or container.
Small power on heating small heating
  
  530   Tuesday, February 23, 2021, 08:59 Marla Cervantes NA (Cu-tube) DoneRe coating Test 2 Tuesday, February 23, 2021, 08:49
Yesterday a heat shield was washed
and when dry it was installed in the EVAP2,
  
  529   Saturday, February 13, 2021, 08:14 Darwin Ortiz RosalesSiC41992-1TARGET BOATDone Sintering of SiC discs for SEM Saturday, February 13, 2021, 08:10
Ta boat loaded with 80 discs
 Screenshot_2021-02-14_114713.png 
  528   Thursday, February 11, 2021, 10:57 Marla Cervantes NA DoneRe coating Test 1Thursday, February 10, 2021, 12:00
Objective: Heat a Re wire to evaporate
it and deposit a layer of Re on the inner
  
  527   Tuesday, February 09, 2021, 06:48 Aaron Schmidt NA DoneTa coating testMonday, February 08, 2021, 17:00: Installed
brackets w/ Ta wire and a small piece of
Re to test voltage drop.
  
  526   Monday, February 01, 2021, 13:57 Darwin Ortiz RosalesSiC40282-4TARGET BOATDoneSintering of SiC discs for SEMMonday, February 01, 2021, 13:52  
  
  525   Tuesday, November 24, 2020, 12:56 Marla Cervantes 44139-8-SK TARGET BOATDoneGraphite casting conditioningTuesday, November 24, 2020, 09:23
A batch of 60 discs of 18 mm diameter
were loaded in a tantalum tube. The tantalum
 2020-11-24-IGP1.JPG2020-11-24IGP1-zoom_out.png2020-11-24-IGP1-stable.JPG2020-11-24-ConditioningProcess.JPG 
  524   Tuesday, November 24, 2020, 08:13 Aaron Schmidt    Flex - line HS installedMonday, November 23, 2020, 17:01: Flex-line
HS installed.

Tuesday, November 24, 2020,
  
  523   Thursday, November 05, 2020, 15:13 Ferran Boix PamiesEmpty41882-2TARGET BOATDonecleaning treatment. 2020-11-05 15:44 empty and naked
boat in for heating up system and clean up.
Turbo on.
  
  522   Wednesday, November 04, 2020, 17:31 Ferran Boix PamiesEmpty41882-2TARGET BOATDoneParasitic target graphite outgassing. 2020-11-04 17:31: target installed
with boat containing graphite container for
outgassing. Roughing pump on.
  
  521   Monday, November 02, 2020, 18:32 Ferran Boix PamiesEmpty44139-7-SKTARGET BOATDoneHEA heat treatment2020-11-02 6:32: roughing on
2020-11-02 7:21: Turbo on for a while,
IGP1:1.8e-5T . water leak check ok.
 20201104_102925.jpg20201104_144831.jpg 
  520   Tuesday, October 27, 2020, 10:25 Ferran Boix PamiesEmpty44139-7-SKTARGET BOATDoneparasitic target commissioning 2020-10-27 10:24 setup introduced
yesterday. Pumping over night IGP1: 5.7e-7T.
Water leak check ok. Performing heating elements
  
ELOG V2.9.2-2455