Message ID: 530     Entry time: Tuesday, February 23, 2021, 08:59
Author: Marla Cervantes 
Target Material:  
Target Oven W.O#: NA (Cu-tube) 
Source:  
Status: Done 
Subject: Re coating Test 2 

 Tuesday, February 23, 2021, 08:49

Yesterday a heat shield was washed and when dry it was installed in the EVAP2,

A 1mm thick rhenium wire was held within two copper brackets to pass through a Cu tube with the intention of coating its inside face


Tuesday, February 23, 2021, 08:58  IGP1 = 7.7e-7 Torr

Pressure 5.88e-7 Torr, current rate set to 10 A @ 0.5 A/min


Pressure 6.1e-7 Torr, current rate set to 20 A @ 0.5 A/min


Pressure 8.51e-7 Torr current rate set to 30 A @ 0.5 A/min, temperature corrected 1800 degC (measured with filament pyrometer)

After 10 min the current and voltage are stable and the pressure is going down


Tuesday, February 23, 2021, 16:25

It seems like the wire is touching the tube so the system will be cool down.

Pressure 6.8e-7 Torr current rate set to 0A at -0.1 A/min


 Tuesday, February 23, 2021, 17:38

Pressure 6e-7 Torr, TGHT = 23.3 A, 4.854 V, Temp 1788 deg C Omega, 1540 degC filament

current rate set to 0A at 0.2A/min 


Wednesday, February 24, 2021, 09:37

Venting EVAP2 


Wednesday, February 24, 2021, 16:47

The wire and Cu tube were  fix such that the wire's deformation does not lead it to touch the tube, then the assembly was attached again and the EVAP2 was pumped down.

IGP1 = 9.3e-7 Torr, current rate is set to 5 A at 0.5 A/min

Wednesday, February 24, 2021, 17:04

IGP1 = 9e-7 Torr TGHT = 5.175A, 0,749 V

current rate is set to 10 A at 0.5 A/min


Wednesday, February 24, 2021, 17:23

IGP1 = 8.8e-7 Torr, TGHT = 10A, 1.78V

current rate is set to 20 A at 0.5 A/min

Since the wire seemed to be touching the tube, the system was vented.

The tube was shifted and the heat shield installed again, the system was pumped over nigth.


Thursday, February 25, 2021, 09:15

A water leak was performed and no leak was observed

IGP1= 4.95e-7 Torr

Thursday, February 25, 2021, 09:32  The current is increased at 0.5 A/min to 5 A


Thursday, February 25, 2021, 10:00

The current was tapped manually at 0.5 A to 6 A the wire is now glowing dimmly

Current rate set to 10A at .5 A/min

Current rate set to 20 A at 0.5A/min


Current rate set to 30 A at 0.5A/min

Thursday, February 25, 2021, 11:17  IGP1= 5.7e-7 Torr, TGHT=30.5A, 6.718V, filament=1740 degC

voltage and current stable, pressure going down.


Thursday, February 25, 2021, 11:21

Current rate set to 40 A at 0.4 A/min


Thursday, February 25, 2021, 11:53 IGP1 = 5.9e-7 Torr, TGHT = 9.267V, 39.15A, filament = 2060 degC

voltage and current stable, pressure going down.

Current rate set to 50 A @ 0.2A/min

During ramping the voltage reduced a bit and I decided to stop the ramp and reduce the current, the voltage stayed constant but the current started increasing slowly without me inputting it so I decided to ramp down the current at 0.2A/min.

When the current reached 0A the power supplies and the pumps were turned off, after an ~1h when the turbo pump had already stopped, the EVAP2 was vented and open.


The wire sintered to the copper tube confirming that the wire was in contact with the tube during heating.

The Cu tube present a grey metallic coloration indicating a Re coating.

The set up together with the copper heat shield were removed from the