Message ID: 520     Entry time: Tuesday, October 27, 2020, 10:25
Author: Ferran Boix Pamies 
Target Material: Empty 
Target Oven W.O#: 44139-7-SK 
Source: TARGET BOAT 
Status: Done 
Subject: parasitic target commissioning 

 2020-10-27 10:24 setup introduced yesterday. Pumping over night IGP1: 5.7e-7T. Water leak check ok. Performing heating elements check.

 2020-10-27 10:43 Heating elements check show low cooling. Ramping up target 1A/15s to 200A.

 2020-10-27 11:54 all ok 200A, thermocouples show room temperature on cartridge and heat shield. Ramping up target 2A/10s to 300A.

 2020-10-27 11:54 all ok 300A, thermocouples show 28/25degC. Ramping up target 2A/10s to 400A.

 2020-10-27 11:54 all ok 400A, thermocouples show 36.5/29degC. Ramping up target 2A/10s to 500A.

 2020-10-27 11:54 all ok 500A, thermocouples show 48.9/33degC. Ramping up target 2A/15s to 550A.

 2020-10-27 12:43 all ok 550A, thermocouples show 55/34degC. Ramping up target 2A/15s to 600A.

 2020-10-27 12:43 all ok 600A, thermocouples show 61.5/35.2degC. Ramping up target 2A/15s to 625A.

 2020-10-27 13:14 all ok 625A, thermocouples show 64.6/34.2degC. Ramping up target 2A/15s to 650A.