539
|
Thursday, March 25, 2021, 07:57 |
Aaron Schmidt | | | | | Re - Ta test. Leak check. | Thursday, March 25, 2021, 07:55: Vacuum
@ 5.12e-07T. Waterlines opened. |
|
538
|
Tuesday, March 23, 2021, 11:28 |
Marla Cervantes | Empty | 44489-6 | | Done | Re-coating test 3 | Objective: Coating the inner surface of
a short tantalum boat with rhenium.
Result: |
|
537
|
Tuesday, March 23, 2021, 08:07 |
Aaron Schmidt | | | | | Re - Ta test. Leak check. | Modified HS installed with new brackets
as per Marla.
Tuesday, March 23, 2021, 08:02: Vacuum |
|
536
|
Tuesday, March 16, 2021, 08:29 |
Darwin Ortiz Rosales | TaC | | TARGET BOAT | Done | sintering of TaC on Caps and springs | Tuesday, March 16, 2021, 08:28
Each endcap is separated with |
|
535
|
Tuesday, March 09, 2021, 11:54 |
Darwin Ortiz Rosales | TaC | 42464-1 | HP-FEBIAD | Done | TaC coating/sintering | Tuesday, March 09, 2021, 11:54
Container coated with |
|
534
|
Friday, March 05, 2021, 10:48 |
Darwin Ortiz Rosales | TaC | 44691-1 | LP-SIS | Done | TaC coating/sintering | Friday, March 05, 2021, 10:47
Ta tube was coated with TaC |
|
533
|
Tuesday, March 02, 2021, 11:32 |
Darwin Ortiz Rosales | TaC | 44691-5 | LP-SIS | Done | TaC coating/sintering | Tuesday, March 02, 2021, 11:26
Ta tube was coated with TaC |
|
532
|
Monday, March 01, 2021, 13:58 |
Aaron Schmidt | | | | | Flex - line HS installed | Flex-Line HS had been fully scrubbed out
earlier. All gaskets replaced.
Empty. Quick check for leaks. |
|
531
|
Friday, February 26, 2021, 09:28 |
Ferran Boix Pamies | Empty | none | | Done | Parasitic target thermal tests | Tests were performed with external
power supply. No target boat or container.
Small power on heating small heating |
|
530
|
Tuesday, February 23, 2021, 08:59 |
Marla Cervantes | | NA (Cu-tube) | | Done | Re coating Test 2 | Tuesday, February 23, 2021, 08:49
Yesterday a heat shield was washed
and when dry it was installed in the EVAP2, |
|
529
|
Saturday, February 13, 2021, 08:14 |
Darwin Ortiz Rosales | SiC | 41992-1 | TARGET BOAT | Done | Sintering of SiC discs for SEM | Saturday, February 13, 2021, 08:10
Ta boat loaded with 80 discs |
|
528
|
Thursday, February 11, 2021, 10:57 |
Marla Cervantes | | NA | | Done | Re coating Test 1 | Thursday, February 10, 2021, 12:00
Objective: Heat a Re wire to evaporate
it and deposit a layer of Re on the inner |
|
527
|
Tuesday, February 09, 2021, 06:48 |
Aaron Schmidt | | NA | | Done | Ta coating test | Monday, February 08, 2021, 17:00: Installed
brackets w/ Ta wire and a small piece of
Re to test voltage drop. |
|
526
|
Monday, February 01, 2021, 13:57 |
Darwin Ortiz Rosales | SiC | 40282-4 | TARGET BOAT | Done | Sintering of SiC discs for SEM | Monday, February 01, 2021, 13:52
|
|
525
|
Tuesday, November 24, 2020, 12:56 |
Marla Cervantes | | 44139-8-SK | TARGET BOAT | Done | Graphite casting conditioning | Tuesday, November 24, 2020, 09:23
A batch of 60 discs of 18 mm diameter
were loaded in a tantalum tube. The tantalum |
|
524
|
Tuesday, November 24, 2020, 08:13 |
Aaron Schmidt | | | | | Flex - line HS installed | Monday, November 23, 2020, 17:01: Flex-line
HS installed.
Tuesday, November 24, 2020, |
|
523
|
Thursday, November 05, 2020, 15:13 |
Ferran Boix Pamies | Empty | 41882-2 | TARGET BOAT | Done | cleaning treatment. | 2020-11-05 15:44 empty and naked
boat in for heating up system and clean up.
Turbo on. |
|
522
|
Wednesday, November 04, 2020, 17:31 |
Ferran Boix Pamies | Empty | 41882-2 | TARGET BOAT | Done | Parasitic target graphite outgassing. | 2020-11-04 17:31: target installed
with boat containing graphite container for
outgassing. Roughing pump on. |
|
521
|
Monday, November 02, 2020, 18:32 |
Ferran Boix Pamies | Empty | 44139-7-SK | TARGET BOAT | Done | HEA heat treatment | 2020-11-02 6:32: roughing on
2020-11-02 7:21: Turbo on for a while,
IGP1:1.8e-5T . water leak check ok. |
|
520
|
Tuesday, October 27, 2020, 10:25 |
Ferran Boix Pamies | Empty | 44139-7-SK | TARGET BOAT | Done | parasitic target commissioning | 2020-10-27 10:24 setup introduced
yesterday. Pumping over night IGP1: 5.7e-7T.
Water leak check ok. Performing heating elements |
|