ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
Text |
|
|
938
|
Monday, July 11, 2022, 09:17 |
Aaron Schmidt | | | | | | | In progress | Pump down empty chamber | Monday, July 11, 2022, 09:15: Roughing. |
|
|
939
|
Tuesday, August 30, 2022, 13:58 |
Aaron Schmidt | | | | | 44062-7 | 44378-25 | In progress | Conditioning UC#40 assembly | Conditioning the UC#40 LP-SIS assembly
& ISAC TS main vacuum chamber. Straight
/ round oven in use (TGHT only). |
|
|
941
|
Thursday, September 29, 2022, 13:50 |
Aaron Schmidt | | | | | | | In progress | Pump down empty chamber | Water loop installed.
Thursday, September 29, 2022, 13:50:
Roughing |
|
|
942
|
Tuesday, October 18, 2022, 13:25 |
Aaron Schmidt | C#5 | LP-SIS | | | 45235-5 | 44691-13 | In progress | Conditioning C#5 | Tuesday, October 18, 2022, 13:25: Roughing.
Tuesday, October 18, 2022, 13:28:
BV1A open |
|
|
943
|
Wednesday, October 19, 2022, 12:16 |
Aaron Schmidt | | | | | | | | Test Stand controls changed | genepicsas.triumf.ca
x11 enabled.
Then use login credentials. |
|
|
945
|
Tuesday, November 15, 2022, 15:32 |
Sam Gupta | | | | | | | | ATTS tantalum Bracket Heating test | Heated up sample 01 for the second time
and measured the temperature with increasing
current. Used pyrometre to measure temperature |
|
|
946
|
Wednesday, November 16, 2022, 13:28 |
Aaron Schmidt | | | | | | | Problems/Solutions | TSG:TP1A Replaced | See elog 944
Wednesday, November 16, 2022, 13:23:
TP1 A replaced |
|
|
947
|
Wednesday, November 23, 2022, 13:52 |
Aaron Schmidt | | | | | | 44378-14 | In progress | FEBIAD Coil Tests | Sam G. & Navid N.
Work Permit# C2022-11-23--1
Wednesday, November 23, 2022, 13:51 |
|
|
948
|
Monday, December 05, 2022, 15:41 |
Aaron Schmidt | | | | | | | | Source tray insulator replacement | Monday, December 05, 2022, 15:38:
Source Tray TGHT & TBHT insulators replaced.
Torqued @ 75 in-lbs. (Reference image |
7x |
|
949
|
Tuesday, December 06, 2022, 11:20 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | 43104-2 | 45235-12 | In progress | New anode routed FEBIAD Tests | Thermocouples installed:
O - O
O - Anode |
|
|
950
|
Tuesday, December 13, 2022, 16:12 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | 43104-2 | 45235-12 | In progress | New anode routed FEBIAD Test - 2 | Thermocouples installed (X):
O - O
O - Anode |
|
|
951
|
Friday, December 16, 2022, 10:32 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | 43104-2 | 45235-12 | In progress | New anode routed FEBIAD Test - 3 | Thermocouples installed (X):
O - O
O - Anode |
|
|
952
|
Monday, December 19, 2022, 12:49 |
Carla Babcock | | HP-FEBIAD | | | | | | HP-FEBIAD tests | Monday, December 19, 2022, 12:06 : Tomislav
changed the polarity of the anode power supply
last week and everything has been closed |
|
|
953
|
Wednesday, December 21, 2022, 17:06 |
Carla Babcock | | | | | | | | Prep for power outage | Source and beamline power supplies turned
off in EPICS
HV cage power off |
|
|
954
|
Tuesday, January 03, 2023, 10:03 |
Carla Babcock | | | | | | | | Recovery from power outage | Easy recovery after power outage, just
had to power cycle the ground PLC IOC and
the BiRa IOC. |
|
|
955
|
Thursday, January 12, 2023, 09:04 |
Aaron Schmidt | | LP-SIS | | | 44691-14 | 44378-20 | In progress | | Test for Aurelia L. Empty LP-SIS w/ end
caps in. Right side expanded.
Thermocouples installed (R - L): |
|
|
956
|
Monday, January 16, 2023, 16:02 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | | | In progress | HP-FEBIAD tests | Extra wraps of foil around the center block
(6) + 3 full wraps around the shield.
Monday, January 16, 2023, 15:40: |
|
|
957
|
Tuesday, January 17, 2023, 09:48 |
Aaron Schmidt | | | | | | | Problems/Solutions | TMS:RP2 Failure | Tuesday, January 17, 2023, 09:48: TMS:RP2
off. Audible failure was in progress. Also
observable on the strip tool. Vacuum group |
|
|
958
|
Tuesday, January 31, 2023, 10:42 |
Aaron Schmidt | | LP-SIS | | | 44062-1-SK | 45235-7 | In progress | Conditioning UC#x assembly | SK Series of LP-SIS targets are for conditioning
only.
Tuesday, January 31, 2023, 10:39: |
|
|
959
|
Thursday, February 02, 2023, 12:44 |
Aaron Schmidt | | LP-SIS | | | 44062-1-SK | 45235-1 | In progress | Conditioning UC#x assembly | SK Series of LP-SIS targets are for conditioning
only.
Thursday, February 02, 2023, 12:41: |
|