Message ID: 947     Entry time: Wednesday, November 23, 2022, 13:52
Author: Aaron Schmidt 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#: 44378-14 
Status: In progress 
Subject: FEBIAD Coil Tests 

Sam G. & Navid N.

Work Permit# C2022-11-23--1

Wednesday, November 23, 2022, 13:51 FS#5 on (HS bypassed with a water loop)

Wednesday, November 23, 2022, 13:55: TSG:IG1 Bypass on

Wednesday, November 23, 2022, 14:03: Signage up. Main breaker on.

Wednesday, November 23, 2022, 14:07: FS#5 off & purged. Not needed.

 Wednesday, November 23, 2022, 15:01: measured magnetic field of coil at 8A

end test


 Monday, November 28, 2022, 11:45: start test set up the hall probe with the jig to move it on the table and centered the hall probe in the magnet. signage up Main breaker on

Monday, November 28, 2022, 13:17: start collecting data at 8 amps

Monday, November 28, 2022, 16:11: end test


 Tuesday, November 29, 2022, 10:50:Signage up Main Breaker on Testing started; with current of 8 amps

Taking measurements of temperature at 8A 9A and 10A

Tuesday, November 29, 2022, 15:25 : system locked out and took out magnet

end test


Wednesday, November 30, 2022, 12:40: Test started. Breaker on. signage up. put in low profile magnet with wire ties to keep coils together.

taking data with 8A of current

Wednesday, November 30, 2022, 16:25: end of test power supply off breaker off


 