666
|
Wednesday, June 06, 2018, 14:01 |
Aaron Schmidt | | | | | | | Problems/Solutions | Emittance scanner (E-rig) communication issues. | Wednesday, June 06, 2018, 13:50:
It was noted yesterday during the
TM2 Source HV tests that the E-rig was not |
|
667
|
Thursday, June 07, 2018, 09:21 |
Aaron Schmidt | | | | | | | Problems/Solutions | Pump down empty chamber. Anode check | TM2 Source tray still in.
Thursday, June 07, 2018, 09:20: Roughing.
Thursday, June 07, 2018, 12:42: Turbo |
|
668
|
Tuesday, June 12, 2018, 11:38 |
Aaron Schmidt | | | | | | | In progress | Source Tray re-installation | Re-installation of the ISAC Test Stand
Source tray. The TM2 ST was removed.
Tuesday, June 12, 2018, 10:15: Disconnect |
|
669
|
Tuesday, June 19, 2018, 10:30 |
Aaron Schmidt | | | | | | | Done | RGA repair | Monday, June 18, 2018, 10:00: RGA removed
from ISAC TS. Handed to Travis C. Communications
issues found |
|
671
|
Tuesday, July 03, 2018, 12:46 |
Aaron Schmidt | Ta#56 | HP-SIS | ITE | TM4 | 42218-9 | 42752-3 | In progress | Conditioning Ta#56 | Tuesday, July 03, 2018, 12:44: Roughing
Tuesday, July 03, 2018, 13:32: Turbo
pumps started. |
8x |
672
|
Monday, July 09, 2018, 10:44 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Coil Test July | Monday, July 09, 2018, 10:43: Rouging.
Monday, July 09, 2018, 13:14: Turbo
pumps on. |
|
673
|
Thursday, July 12, 2018, 08:24 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Power outage / restart | Power outage (07/11/2018 @ approx 21:53)
shut down the test stand.
|
|
674
|
Thursday, July 12, 2018, 10:11 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Coil Test #5 | *** REVIEW Elog entry #673 Power
outage & restart ***
Thursday, July 12, 2018, 10:10: Opened |
|
675
|
Monday, July 23, 2018, 14:25 |
Aaron Schmidt | UC#23 | LP-FEBIAD-CTL | ITE | TM2 | | | In progress | Conditioning Heat Shield for UC#23 | Monday, July 23, 2018, 14:20: Roughing.
Monday, July 23, 2018, 14:54: Turbo
pumps on. |
|
676
|
Friday, July 27, 2018, 14:44 |
Aaron Schmidt | UC#24 | LP-SIS | ITE | TM4 | 41177-3 | 42752-6 | In progress | Conditioning Heat Shield for UC#24 & voltage test prep | 4 Kapton wire routed into the 9-pin connector.
Unused pins are grounded on the bracket.
Friday, July 27, 2018, 14:25: Roughing |
|
677
|
Friday, August 10, 2018, 10:56 |
Aaron Schmidt | | | | | | | Problems/Solutions | New PS installation and Cathode BIAS set | Friday, August 10, 2018, 10:25: Remove
TBHT 500 PS and replace with TBHT 600 PS.
Friday, August 10, 2018, 10:50: Switch |
|
678
|
Tuesday, August 14, 2018, 11:03 |
Aaron Schmidt | | LP-SIS | | | 41177-3 | 42752-6 | | Voltage Tests (Ta target) | Tuesday, August 14, 2018, 10:55: Auto ramping
TGHT @ 6 A per min to 40 A.
Tuesday, August 14, 2018, 11:03: |
|
680
|
Wednesday, August 22, 2018, 15:20 |
Aaron Schmidt | | LP-SIS | | | 41177-3 | | | Voltage Tests (Ta Target) | Wires reconfigured / set
Wednesday, August 22, 2018, 13:10:
Roughing. |
|
681
|
Wednesday, August 29, 2018, 11:36 |
Aaron Schmidt | | | | | | | | Epics / putty crash. | Wednesday, August 29, 2018, 11:35: EPIC's
crashed.... epically.
Unable to restart Putty or TS controls. |
|
682
|
Friday, August 31, 2018, 10:16 |
Aaron Schmidt | | | | | | | Problems/Solutions | RGA connection loss. | Friday, August 31, 2018, 10:10: The RGA
will not re-connect to the computer. Manually
turned it off while under vacuum to protect |
|
683
|
Friday, August 31, 2018, 12:27 |
Aaron Schmidt | nSiC#1 | LP-SIS | ITW | TM2 | 43044-1 | 42752-4 | In progress | Conditioning nSiC#1 | Friday, August 31, 2018, 12:27: Roughing.
Friday, August 31, 2018, 13:19: Turbo
pumps started. |
15x |
684
|
Wednesday, September 12, 2018, 11:19 |
Aaron Schmidt | Ta#57 | LP-SIS | ITE | TM4 | 41177-3 | 42752-6 | In progress | Conditioning Ta#57 | Wednesday, September 12, 2018, 11:06: Roughing.
Help req'd. Doors wouldn't seal.
Wednesday, September 12, 2018, 11:52: |
9x |
685
|
Monday, September 17, 2018, 11:52 |
Aaron Schmidt | UC#25 | LP-SIS | ITW | TM2 | | 42752-9 | In progress | Conditioning Heat Shield for UC#25 | Monday, September 17, 2018, 11:47: Roughing*.
Doors not sealing, help acq'd
Monday, September 17, 2018, 11:51: |
|
686
|
Friday, September 21, 2018, 11:41 |
Aaron Schmidt | UC#26 | LP-IG-LIS | ITE | TM4 | | 42132-1 | In progress | Conditioning Heat Shield for UC#26 | Friday, September 21, 2018, 11:40: Roughing
Friday, September 21, 2018, 11:41:
Doors sealed for roughing. |
|
687
|
Tuesday, October 02, 2018, 13:39 |
Aaron Schmidt | | LP-FEBIAD | | | 41790-9 | 42752-5 | In progress | Test FEBIAD w/ Silver bolts & sealed end caps w/ stoppage | Silver bolts used on Coil, TGHT, &
TBHT.
End caps in target |
|
|