Entry  Friday, January 26, 2018, 13:59, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, HV test 1 2018_HV_test_1.docx
Entry  Monday, January 29, 2018, 10:07, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, Power outage / HV test 2 2018_HV_test_2.docx
Entry  Tuesday, January 30, 2018, 06:51, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, HV test 3 2018_HV_test_3.docx
Entry  Wednesday, January 31, 2018, 09:53, Aaron Schmidt, , , , , (Blank), 42752-3, Done, Wire moved. 
Entry  Wednesday, January 31, 2018, 12:58, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, In progress, HV test 4 2018_HV_test_4.docx
Entry  Monday, February 05, 2018, 09:17, Aaron Schmidt, , , , , , , Problems/Solutions, Epics loss 
Entry  Wednesday, February 07, 2018, 08:46, Aaron Schmidt, , , , , , , , BIAS Power supply installation BIAS_PS_off_top_switch.jpgBIAS_PS_70kV_rear_bottom.jpgBIAS_PS_70kV_Front_bottom.jpg
Entry  Friday, February 23, 2018, 08:50, Aaron Schmidt, , , , , , , , New Al Corona  
Entry  Wednesday, February 28, 2018, 11:50, Aaron Schmidt, , , , , , , , HV Test Np 2018_HV_test_Np.docx
Entry  Monday, March 12, 2018, 10:07, Aaron Schmidt, , , , , , , , HV Test w-gas 
Entry  Tuesday, March 13, 2018, 06:00, Aaron Schmidt, UC#22, LP-SIS, ITE, TM4, , , In progress, Conditioning Heat Shield for UC#22 
Entry  Friday, March 16, 2018, 08:15, Aaron Schmidt, Nb#8, HP-SIS, ITW, TM2, 38817-2, 42738-12, In progress, Conditioning Nb#08 6x
Entry  Tuesday, March 20, 2018, 09:14, Aaron Schmidt, , , , , , , Problems/Solutions, Optics issue 
Entry  Wednesday, April 11, 2018, 10:19, Aaron Schmidt, , , , , , , , Pump down empty chamber 
Entry  Tuesday, April 17, 2018, 09:59, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, , , Test FEBIAD 
Entry  Tuesday, April 17, 2018, 11:02, Aaron Schmidt, , , , , , , Done, Roughing pump issue. 
Entry  Wednesday, April 25, 2018, 09:50, Aaron Schmidt, Ta (test), LP-SIS, , , 41177-3, , In progress, Ta test and window change TS-2018-04-25-14-55.rgaTa_target_heating_test_-_Test_stand.docx
Entry  Monday, April 30, 2018, 12:07, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, Test ready 
Entry  Tuesday, May 08, 2018, 10:36, Aaron Schmidt, , LP-FEBIAD, , , 41790-9, 42752-5, In progress, C-seal Test 
Entry  Monday, May 28, 2018, 08:46, Aaron Schmidt, , LP-FEBIAD, , TM2, 41790-9, 42752-5, In progress, New TM source tray swap out.  New_TM_Source_Tray_2018.docxTS-2018-05-30-06-30.rgaER-580-310-30kV-m28.txtER-580-320-30kV-M39.txt2018_TM2_Source_Tray_in_Test_Stand_-_Test_Results.docx