  Test-Stand, Page 35 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Monday, May 26, 2014, 14:15, Aurelia Laxdal, SiC#30, HP-FEBIAD, ITE, TM3, , , Done, SiC#30 HV and Heaters Conditioning  SiC#30_Conditioning_2nd_time.docx

HV and Heaters Conditioning for SiC#30 was completed Friday, May 23, 2014. The target was cooled down and it's ready for the on-line installation.

    Reply  Friday, June 13, 2014, 08:43, Anders Mjos, SiC#30, HP-FEBIAD, ITE, TM3, 38481-8, 39956-5, Done, SiC#30 HV and Heaters Conditioning  

Aurelia Laxdal wrote:

HV and Heaters Conditioning for SiC#30 was completed Friday, May 23, 2014. The target was cooled down and it's ready for the on-line installation.

 Friday, June 13, 2014, 08:43: Turbos stopped. Vacuum at 1.2E-7 T


Monday, June 16, 2014, 08:26: Venting. Water purged.

Monday, June 16, 2014, 09:00: Target removed

Entry  Friday, July 18, 2014, 11:30, Anders Mjos, UC#10, LP-SIS, ITE, TM4, 40282-5, 40316-1, Done, UC#10 Heat Shield Conditioning 

Friday, July 18, 2014, 11:30: Roughing

Friday, July 18, 2014, 11:51: Starting turbos

Friday, July 18, 2014, 11:59: Turbos at speed.

Friday, July 18, 2014, 12:01: Vacuum at 1.4E-5 T


Monday, July 21, 2014, 08:51: Opened water for HS circuit. Small vacuum "bump" recovered to 1.5E-7 T

Monday, July 21, 2014, 09:17: Starget TGHT autoramping to 580A @ 2 A/min

Monday, July 21, 2014, 14:05: TGHT @ 580A 7.47V.


Tuesday, July 22, 2014, 10:41: Data logger installed

Device
 
Temp
[C]
Flow
[lpm]
HS + MSP 37.6 3.7
TBHT 28.5 6.1
COIL + EE 28.7 4.8
TGHT 31.0 5.4

 Tuesday, July 22, 2014, 13:41: BIAS / EZL / EE to 30 / 14 /2 kV. EE:RDCUR 695 uA

Tuesday, July 22, 2014, 14:23: Starting cool down of TGHT 2A/min. Vacuum at 2.7E-7 T 


Wednesday, July 23, 2014, 09:05: BIAS / EZL / EE off. Turbos off. Vacuum at 1.3E-7 T.

Device Temp
[C]
Flow
[lpm]
HS + MSP 28.5 3.7
TBHT 28.3 6.1
COIL + EE 29.2 5.2
TGHT 28.4 5.7

 Wednesday, July 23, 2014, 14:05: Purged HS water line.

Wednesday, July 23, 2014, 14:07 : Venting

Wednesday, July 23, 2014, 14:33: Heat Shield removed

Entry  Friday, August 08, 2014, 12:45, Anders Mjos, ZrC#6, LP-SIS, ITW, TM1, 40282-3, 39230-5, Done, Condictioning ZrC#6 

Friday, August 08, 2014, 12:44: Stopped turbos

Friday, August 08, 2014, 14:42: Venting 

Target assembly inserted

Friday, August 08, 2014, 15:08: Roughing

Friday, August 08, 2014, 15:29: Turbos started

Friday, August 08, 2014, 15:37: Turbos at speed

Friday, August 08, 2014, 15:39: Vacuum at 1.4E-5 T


Monday, August 11, 2014, 08:58: Opened HS cooling water. Vacuum stable at 1.6E-7 T


Tuesday, August 12, 2014, 10:31: IV4 Opened

Tuesday, August 12, 2014, 10:35: EZL / EE / BIAS to 14 / -1.5 / 30 kV

Tuesday, August 12, 2014, 10:39: Starting target heat to 300 A / 96 (115) A


Wednesday, August 13, 2014, 08:03 : Continue heating to 580 A / 190 (228) A

Wednesday, August 13, 2014, 08:24: Aborting target heating. Cu-LCW pressure and flow is reduced due to a problem with a pump.

Device Flow
[lpm]

Temp
[C]

HS + MSP 1.9 27.7
TBHT 4.1 23.9
COIL + EE 3.5 25.1
TGHT 3.7 25.6
SUPPLY   24.4

Supply pressure ~ 52 psi
Return pressure ~ 11 psi

 Wednesday, August 13, 2014, 08:31: Starting cool down as flow rate on HS + MSP is low. A low flow trip of the TGHT should be avoided.

Wednesday, August 13, 2014, 11:54 : Curtis Ballard contacted me and asked if they could valve off the Cu-LCW circuit to the Test Stand. Heaters had been previously brought down. Bias off and power supplies are switched off. IV4 closed.

Wednesday, August 13, 2014, 12:00: Cooling water syupply valved off to Test Stand.


 

Flow rates are back to normal since yesterday evening

Device Flow
[lpm]
Temp
[C]
HS + MSP 3.1 27.8
TBHT 5.9 27.4
COIL + EE 5.0 28.3
TGHT 5.4 27.6
SUPPLY   28.1

Thursday, August 14, 2014, 08:00: Conditioning on hold due to FC0 problem


Wednesday, August 20, 2014, 07:50: Conditioning  continues. Auto-ramping to 400 / 150 ( 180) A @ 4/2 A/min

Wednesday, August 20, 2014, 09:35 : Continue heating to 580 / 165 (200) A @ 2/1 A/min

Wednesday, August 20, 2014, 09:50 

 

Device Flow
[lpm]
Temp
[C]
HS + MSP 3.6 32.9
TBHT 6.5 28.5
COIL + EE 5.4 29.2
TGHT 5.8 29.7
SUPPLY   28.8

 Wednesday, August 20, 2014, 15:15: Power lost to TBHT, TGHT and EE during nominal operation (580/ 183 (220) A). Fault report submitted.


PLC cabinet work finished. Resuming conditioning.

Tuesday, August 26, 2014, 16:35:EZL / EE / BIAS to 14 / -1.5 / 30 kV

Tuesday, August 26, 2014, 16:35: Starting target heat to 50 A / 25 A


Wednesday, August 27, 2014:  

Continued conditioning. Heating to 580 /190 (228) A


Thursday, August 28, 2014, 08:34 

Device Flow
[lpm]
Temp
[C]
HS + MSP 3.5 38.0
TBHT 6.4 28.0
COIL + EE 5.5 29.8
TGHT 5.8 30.3
SUPPLY   28.2

 


Friday, August 29, 2014, 10:30: EE conditioned for ~20 min @ 2kV.

Friday, August 29, 2014, 10:32 : Starting cool down at 4/2 A/min

Friday, August 29, 2014, 11:55: Closed IV4

Friday, August 29, 2014, 11:56: BIAS, EE and EZL to 0

Friday, August 29, 2014, 13:10: Stopped turbos.

Friday, August 29, 2014, 14:06: Venting

Friday, August 29, 2014, 14:51: Target removed

Entry  Friday, August 29, 2014, 14:52, Anders Mjos, Ta#44, HP-SIS, ITE, TM4, 38817-9, 40316-11, Done, Conditioning Ta#44 

Friday, August 29, 2014, 14:51: Roughing

Friday, August 29, 2014, 15:11: Starting turbos.

Friday, August 29, 2014, 15:19: Turbos at speed

Friday, August 29, 2014, 15:21: Vacuum at 1.6E-5 T


Tuesday, September 02, 2014, 08:36: HS cooling water supply opened. Vacuum stable at 1.4E-7 T

Tuesday, September 02, 2014, 08:50 : BIAS/ EZL / EE to 30 / 14 / -1.5 kV. Started auto ramping to 500 / 150 (180) A

Tuesday, September 02, 2014, 09:23 

Supply ~97psi, Return ~7psi

Device

Flow
[lpm]
Temp
[C]
HS + MSP 3.9 28.0
TBHT 6.5 27.6
COIL + EE 5.4 28.6
TGHT 5.8 27.8
SUPPLY   28.2

 


Thursday, September 04, 2014, 12:38 : Starting cool-down

Thursday, September 04, 2014, 15:20: Closed IV4

Thursday, September 04, 2014, 15:37 : BIAS / EZL / EE to 0


Friday, September 05, 2014

Target cooled down. Power supplies switched off.


Monday, September 08, 2014, 14:07: Turbos stopped.

Monday, September 08, 2014, 15:15: Venting. HS cooling water lines purged.

Monday, September 08, 2014, 16:00: Target removed.

Entry  Monday, September 08, 2014, 16:23, Anders Mjos, UC#11, , , TM4, 40282-5, , Done, UC#11 Heat Shield Conditioning Thermocouples.xlsx

T/C installed

CH 1: Attached to TGHT outside middle
CH 2: Through HS outside TGHT right
CH 3: Through HS inside TGHT  right
CH 4: Attached to HS on left gripper. Does not read temp

Monday, September 08, 2014, 16:22: Roughing

Monday, September 08, 2014, 16:43: Started turbos

Monday, September 08, 2014, 16:51: Turbos at speed

Monday, September 08, 2014, 16:53: Vacuum at 2.7E-5 T


Tuesday, September 09, 2014, 08:20 : Opened HS water supply. Vacuum stable at 3.7E-7 T

Tuesday, September 09, 2014, 08:21: Starting auto ramping. TGHT to 580 A at 2A/min

Tuesday, September 09, 2014, 08:50 :

Device Flow
[lpm]
Temp
[C]
HS + MSP 3.8 26.7
TBHT 6.5 26.2
COIL + EE 5.3 26.9
TGHT 5.8 26.3
SUPPLY   27.0

 


Wednesday, September 24, 2014, 11:30: T/C attached to tube does no longer read a correct temperature. Cooling down.


Thursday, September 25, 2014, 08:50: Turbos stopped.

Thursday, September 25, 2014, 11:07: Venting

Thursday, September 25, 2014, 14:00: Heat shield removed

Entry  Thursday, September 25, 2014, 15:44, Anders Mjos, ThO#1, , ITW, TM1, 40282-5, , Done, ThO#1 Heat Shield Conditioning 

Thursday, September 25, 2014, 15:44: Roughing

Thursday, September 25, 2014, 16:06: Starting turbos

Thursday, September 25, 2014, 16:14: Turbos at speed.

Thursday, September 25, 2014, 16:28: Vacuum at 1.9E-5 T


Vacuum was coming down slowly yesterday. Vented this morning to clean o-ring on door.

Friday, September 26, 2014, 08:40: Roughing

Friday, September 26, 2014, 09:02: Starting turbos

Friday, September 26, 2014, 09:10: Turbos at speed

Friday, September 26, 2014, 09:12: Vacuum at 9.7E-6 T


Monday, September 29, 2014, 08:40: Water opened for HS circuit. Vacuum stable at 1.8E-7 T

Monday, September 29, 2014, 13:51: Opened and closed IV4


Wednesday, October 01, 2014, 13:13 : Target cooled down.


Monday, October 06, 2014, 09:10: Turbos stopped. Vacuum at 1.3E-7 T

Monday, October 06, 2014, 10:49: Venting


Tuesday, October 07, 2014, 09:31: Heat Shield removed

Entry  Thursday, April 02, 2015, 15:42, Anders Mjos, TM2 Test Target, LP-FEBIAD, , TM2, , 39230-1, Done, TM2 Test Target Conditioning TM2_FEBIAD_Test_Target.docxER_Scans.zip

Thursday, April 02, 2015, 15:42: Roughing

Thursday, April 02, 2015, 16:12: Turbos started

Thursday, April 02, 2015, 16:22: Turbos at speed. Vacuum at 8.7E-6 T


Tuesday, April 07, 2015, 08:24: Opened water for HS. Vacuum stable at 1.1E-7 T

Tuesday, April 07, 2015, 08:25: Pumping on gas lines.

Tuesday, April 07, 2015, 08:37: Finished pumping.

Tuesday, April 07, 2015, 08:41: Opening gas valve to vacuum chamber

Tuesday, April 07, 2015, 08:42: RGA filament on.

Tuesday, April 07, 2015, 08:55: BIAS/EZL/EE to 30/14/1.5 kV

Tuesday, April 07, 2015, 08:55: COIL to 50 A,  ANODE to 200 V

Tuesday, April 07, 2015, 09:01: Started auto-heating to 580/250 A at 2 A/min

Tuesday, April 07, 2015, 13:25 : Opened IV4

Tuesday, April 07, 2015, 15:10: Ramping TBHT to 290A


Wednesday, April 08, 2015, 09:27: Opening for Ne gas

Wednesday, April 08, 2015, 12:05: BIAS/EZL to 40/18.5 kV

Wednesday, April 08, 2015, 13:15 :BIAS/EZL/EE to 50/23.5/2.0 kV

Wednesday, April 08, 2015, 15:15: BIAS/EZL/EE to 30/14/1.5 kV


Thursday, April 09, 2015, 11:19: Starting target cool down

Thursday, April 09, 2015, 16:54: BIAS/EZL/EE to 30/30/1.5 kV

Thursday, April 09, 2015, 17:58: BIAS and source off.


Friday, April 10, 2015, 08:21: Closed gas supply

Friday, April 10, 2015, 08:23: Stopped turbos

Entry  Friday, September 11, 2015, 11:43, Anders Mjos, Ta#46, HP-SIS, ITE, TM4, , , Done, Ta#46 conditioning Ta#46.docx

EE is ST-200 material (AlN)

Friday, September 11, 2015, 11:0: Roughing

Friday, September 11, 2015, 12:12: Turbos started.

Friday, September 11, 2015, 12:22: Turbos at speed. Vacuum at 2.2E-5 T

Friday, September 11, 2015, 14:02: RGA on.


Monday, September 14, 2015, 08:05: Opened water for HS circuit. Vacuum stable at 2.3E-7 T. No response on RGA.

Monday, September 14, 2015, 08:08: Opened IV4

Monday, September 14, 2015, 08:11: Starting Target Heat. TGHT/TBHT 580 / 200 A at 2 / 1 A/min. Good/bad vacuum 4E-6 / 6E-6 T

Monday, September 14, 2015, 08:12: Interlock for BIAS does not clear although EE is on. Interlock cleared when beam line elements were turned on

Monday, September 14, 2015, 08:20: BIAS/EZL/EE at 30 / 15 / 1.5 kV

Monday, September 14, 2015, 08:25: Returned MB1 to remote control

Monday, September 14, 2015, 13:28: Target at temperature

Monday, September 14, 2015, 15:06: Heating TBHT to 230 A 


Tuesday, September 15, 2015, 15:03: EE to 2 kV

Tuesday, September 15, 2015, 16:39: EE to 1.5 kV

Tuesday, September 15, 2015, 17:01: Starting target cool down


Wednesday, September 16, 2015, 09:01: HV and source off. Closed IV4. Turbos off

Wednesday, September 16, 2015, 12:52: RGA off. Venting

Entry  Friday, September 30, 2016, 11:11, Aaron Schmidt, SiC#35, HP-FEBIAD, ITW, TM2, 39530-9, 41120-8, Done, Conditioning SiC#35 6x

Friday, September 30, 2016, 10:00: Roughing.

Friday, September 30, 2016, 10:01: Roughing stopped. RP1 failure. Breaker tripped.

Friday, September 30, 2016, 11:49: Roughing continued.

Friday, September 30, 2016, 12:37: Turbos started -AM


Monday, October 03, 2016, 09:00: RGA on.

Monday, October 03, 2016, 09:05: Waterline opened. No response on RGA. Vacuum stable @1.70E-7T.

Monday, October 03, 2016, 09:20: Power/Sources on. Gas sources opened/closed.

Monday, October 03, 2016, 09:39: Optics switched on. Monitor TMS:SX2

Monday, October 03, 2016, 09:47: Anode on @ 200 V

Monday, October 03, 2016, 09:49: Coil on @ 50A

Monday, October 03, 2016, 09:50: IV4 opened.

Monday, October 03, 2016, 09:58: BIAS / EZL / EE @ 30 / 13 / 1.5 kV .

Monday, October 03, 2016, 10:08: Auto ramping TGHT / TBHT to 580 / 290 A @ 2A per min.

Monday, October 03, 2016, 10:12

 Device

  Temp
[C]
 Flow
[lpm]
 HS + MSP 27.0 3.99
 TBHT 27.5 3.21
 COIL + EE 26.8 5.26
 TGHT  26.9 5.78

Monday, October 03, 2016, 11:09: TMS:SX2 Fixed. No optics or sources affected.

Monday, October 03, 2016, 11:38: BIAS @ 30 kV. (Was actually set to 20 kV before). Ramping progress ok.

Monday, October 03, 2016, 15:56: TGHT / TBHT @ 580 / 290 A. RGA restarted.


Wednesday, October 05, 2016, 08:29: Optics found to be tripped : TMS:OCT4 , TMS:Q4 ,TMS:OCT3 ,TMS:SX3 ,TMS:Q3 ,TMS:SX2. Restarted

  Temp
[C]
 Flow
[lpm]
 HS + MSP 35.3 3.99
 TBHT 29.9 3.14
 COIL + EE 28.8 5.07
 TGHT  30.8 5.72

Wednesday, October 05, 2016, 09:20: Wire scanners reset. Emittance rig not reading properly.

Wednesday, October 05, 2016, 09:22: Auto ramping TBHT to 300 A @ 2A per min.


Thursday, October 06, 2016, 15:58: Auto-cooling TGHT / TBHT @ 2A per min.

  Temp
[C]
 Flow
[lpm]
 HS + MSP 35.4 3.95
 TBHT 29.4 3.09
 COIL + EE 28.8 5.05
 TGHT 30.8 5.70

 


Friday, October 07, 2016, 08:12: Source off - AM


Tuesday, October 11, 2016, 08:28: Turbos off. RGA off -AM

Tuesday, October 11, 2016, 13:38: Venting -AM

Entry  Wednesday, January 25, 2017, 09:48, Aaron Schmidt, , , , , 41882-4, 41751-6, Done, Out gas Heat Shield for Target cleaning test 7x

No EE. Insulators, gripper arms, and blank EE plate included

-New grounded 9 pins included in brackets

-TGHT included to out gas Heat shield


Wednesday, January 25, 2017, 09:45: Roughing

Wednesday, January 25, 2017, 10:04: Turbo pumps started.

Wednesday, January 25, 2017, 11:26: Ion gauge & RGA on.


Thursday, January 26, 2017, 08:25: RGA restarted. (Fatal communication error)

Thursday, January 26, 2017, 08:32: Water lines opened. No response on RGA. Vacuum stable @ 1.44e-07T.

Thursday, January 26, 2017, 08:35: Power/sources on.

Thursday, January 26, 2017, 08:37: Auto-ramping TGHT to 580A @ 2A per min. Vacuum @ 1.44e-07T.

  Device Temp
[C]
 Flow
[lpm]
 HS + MSP 23.5 4.02
 TBHT 23.3 3.13
 COIL + EE 23.3 5.18
 TGHT  23.4 5.78

Thursday, January 26, 2017, 13:11: RGA restarted. (Fatal communication error)

Thursday, January 26, 2017, 15:20: RGA restarted. (Fatal communication error)

Thursday, January 26, 2017, 15:26: RGA being shut down. (Fatal communication error)

Thursday, January 26, 2017, 15:31: RGA Restarted.


Friday, January 27, 2017, 08:06: RGA running ok.

  Device Temp
[C]
 Flow
[lpm]
 HS + MSP 30.2 4.06
 TBHT 21.2 3.14
 COIL + EE 21.4 5.11
 TGHT  23.3 5.78

Friday, January 27, 2017, 15:23: Auto-cooling started @ 2A per min.


Monday, January 30, 2017, 08:02: RGA off. Ion Gauge off. Turbo pumps off.

Monday, January 30, 2017, 08:05: Power/sources off. Water lines purged.

Monday, January 30, 2017, 09:09: Venting.

Entry  Wednesday, January 25, 2017, 14:54, Aaron Schmidt, , , , , 42218-9, 41751-6, Done, Target cleaning test HP-SIS CC Clean HP-SIS_CC_Clean.docxTS-2017-01-30-11-00.rgaOMEGA_OM-DAQPRO-5300_01-Feb-17_15.36.02.dlp

Target Test (Fully Cleaned vs Crystal Clean only).

For all tests:

-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.

- Ensure previous test turbos are off by 8:15 and started venting by 9:15am to meet timeline.

-Start Roughing by 10:10am +/- 1 minute.

-TGHT / TBHT ramping starts @ 8:30am. 2A per min to 580A / 200A

ALL START TIMES MUST BE CONSISTENT.


***Pre-outgassed*** Heat Shield W.O# 41751-6: Includes insulators, new Al grounded 9-pin, bracket, & gripper arms. Blank/Plate. No source cup/EE.


HP-SIS Target # 42218-9: Crystal Clean only.


Monday, January 30, 2017, 09:44: HS removed from test stand. Exchange target.

Monday, January 30, 2017, 10:01: Target # 42218-9 placed into test stand. Door open for 17 minutes.

Monday, January 30, 2017, 10:10: Roughing.

Monday, January 30, 2017, 10:10: Doors sealed for roughing.

Monday, January 30, 2017, 10:11: BV1B OPEN. Opened @ 350T.

Monday, January 30, 2017, 10:29: Both Turbo pumps started.

Monday, January 30, 2017, 10:34: Ion gauge on. TP1B @ speed 42 KRPM.

Monday, January 30, 2017, 10:37: TP1A @ speed 38 KRPM.

Monday, January 30, 2017, 10:40: RGA on. Vacuum @1.24E-05T.

Monday, January 30, 2017, 15:30: Vacuum @ 4.49E-07T.


Tuesday, January 31, 2017, 08:14: Water lines opened. No response on RGA. Vacuum stable @ 1.44E-07T.

Tuesday, January 31, 2017, 08:19: Power/Sources on.

Tuesday, January 31, 2017, 08:20: DAQPro loose. re-connected.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 20.9 3.95
 TBHT 20.7 3.08
 COIL + EE 20.9 5.13
 TGHT  21.1 5.72

Tuesday, January 31, 2017, 08:30: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.

Tuesday, January 31, 2017, 10:00: Check. Vacuum @ 7.73E-07T.

Tuesday, January 31, 2017, 11:40: Check. Vacuum @ 3.42E-07T.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 28.4 3.92
 TBHT 27.0 3.45
 COIL + EE 23.0 5.02
 TGHT  24.9 5.61

Tuesday, January 31, 2017, 13:30: Check. Vacuum @ 2.34E-07T

Tuesday, January 31, 2017, 15:30: Auto-cooling started @ 2A per min.


Wednesday, February 01, 2017, 08:10: Power/sources off.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 22.2 3.95
 TBHT 22.2 3.06
 COIL + EE 22.0 5.02
 TGHT  22.2 5.67

Wednesday, February 01, 2017, 08:14: Waterlines purged.

Wednesday, February 01, 2017, 08:15: RGA, Ion gauge, turbo pumps off.

Wednesday, February 01, 2017, 09:15: Venting.

Entry  Wednesday, January 25, 2017, 14:55, Aaron Schmidt, , , , , 42218-6, 41751-6, Done, Target cleaning test (Long) HP-SIS Full Clean HP-SIS_Full_Clean.docxOMEGA_OM-DAQPRO-5300_07-Feb-17_09.17.23.dlpTS-2017-02-01-10-40.rgaTS-2017-02-03-08-50.rga

Target Test (Fully Cleaned vs Crystal Clean only).

For all tests:

-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.

- Ensure previous test turbos are off by 8:15 and started venting by 9:15am to meet timeline.

-Start Roughing by 10:10am +/- 1 minute.

-TGHT / TBHT ramping starts @ 8:30am. 2A per min to 580A / 200A

ALL START TIMES MUST BE CONSISTENT.


***Pre-outgassed*** Heat Shield W.O# 41751-6: Includes insulators, new Al grounded 9-pin, bracket, & gripper arms. Blank/Plate. No source cup/EE.


HP-SIS Target # 42218-6: Full Clean. Crystal Clear, Acetone, & Methanol used.


Wednesday, February 01, 2017, 09:47: HS removed from test stand. Exchange target.

Wednesday, February 01, 2017, 10:04: Target # 42218-6 placed into test stand. Door open for 17 minutes.

Wednesday, February 01, 2017, 10:10: Roughing.

Wednesday, February 01, 2017, 10:10: Doors sealed for roughing.

Wednesday, February 01, 2017, 10:11 BV1B OPEN. Opened @ 431T.

Wednesday, February 01, 2017, 10:29: Both Turbo pumps started.

Wednesday, February 01, 2017, 10:34: Ion gauge on. TP1B @ speed 42 KRPM.

Wednesday, February 01, 2017, 10:37: TP1A @ speed 38 KRPM.

Wednesday, February 01, 2017, 10:40: RGA on. Vacuum @ 6.79E-05T.

Wednesday, February 01, 2017, 15:30: Check. Vacuum @ 3.18E-7T.


Thursday, February 02, 2017, 08:15: Water lines opened. No response on RGA. Vacuum stable @ 1.29E-07T.

Thursday, February 02, 2017, 08:18: Power/Sources on.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 22.7 3.92
 TBHT 22.5 3.08
 COIL + EE 22.5 5.10
 TGHT  22.7 5.66

Thursday, February 02, 2017, 08:30: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.

Thursday, February 02, 2017, 10:00: Check. Vacuum @ 6.76E-07T.

Thursday, February 02, 2017, 11:41: Check. Vacuum @ 3.26E-07T.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP  29.1 3.99
 TBHT  23.9  3.16
 COIL + EE  23.8 5.19
 TGHT  25.5  5.80

Thursday, February 02, 2017, 13:30: Check. Vacuum @ 1.97E-07T.

Thursday, February 02, 2017, 15:30: Check. Vacuum @ 1.88E-07T.


Friday, February 03, 2017, 08:45: Check. Vacuum @ 1.62E-07T

Friday, February 03, 2017, 08:50: RGA restarted.

Friday, February 03, 2017, 10:50: Auto-cooling started @ 2A per min.


Monday, February 06, 2017, 08:18: Multiple attempts made to restart epics. Strip tools are not available. Vacuum data not available (White out screen). (see power outage eLog)

Monday, February 06, 2017, 08:20: RGA confirmed shut down.

Monday, February 06, 2017, 08:23: Sources/power off.

Monday, February 06, 2017, 08:25: Water lines purged.

Monday, February 06, 2017, 10:14: Turbo pumps restarted.

Monday, February 06, 2017, 10:19: Ion gauge on. TP1B @ speed 42 KRPM.

Monday, February 06, 2017, 10:22: TP1A @ speed 38 KRPM.


Tuesday, February 07, 2017, 08:13: Turbos off.

Tuesday, February 07, 2017, 09:10: Venting.

Entry  Wednesday, January 25, 2017, 14:56, Aaron Schmidt, , , , , 42218-14, 41751-6, Done, Target cleaning test LP-SIS CC Clean LP-SIS_CC_Clean.docxTS-2017-02-07-10-40.rgaOMEGA_OM-DAQPRO-5300_09-Feb-17_10.49.31.dlp

Target Test (Fully Cleaned vs Crystal Clean only).

For all tests:

-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.

- Ensure previous test turbos are off by 8:15 and started venting by 9:15am to meet timeline.

-Start Roughing by 10:10am +/- 1 minute.

-TGHT / TBHT ramping starts @ 8:30am. 2A per min to 580A / 200A

ALL START TIMES MUST BE CONSISTENT.


***Pre-outgassed*** Heat Shield W.O# 41751-6: Includes insulators, new Al grounded 9-pin, bracket, & gripper arms. Blank/Plate. No source cup/EE.


LP-SIS Target # 42218-14: Crystal Clean only.


Tuesday, February 07, 2017, 09:48: HS removed from test stand. Exchange target.

Tuesday, February 07, 2017, 10:07: Target # 42218-14 placed into test stand. Door open for 19 minutes.

Tuesday, February 07, 2017, 10:10: Roughing.

Tuesday, February 07, 2017, 10:10: Doors sealed for roughing.

Tuesday, February 07, 2017, 10:11: BV1B OPEN. Opened @ 430T.

Tuesday, February 07, 2017, 10:29: Both Turbo pumps started.

Tuesday, February 07, 2017, 10:34: Ion gauge on. TP1B @ speed 42 KRPM.

Tuesday, February 07, 2017, 10:37: TP1A @ speed 38 KRPM.

Tuesday, February 07, 2017, 10:39: RGA on. Vacuum @ 1.49E-05T.

Tuesday, February 07, 2017, 15:30: Check. Vacuum @ 3.26E-07T.


Wednesday, February 08, 2017, 08:12: Water lines opened. No response on RGA. Vacuum stable @ 1.29E-07T.

Wednesday, February 08, 2017, 08:14 : Power/Sources on.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 20.8 4.06
 TBHT 20.5 3.17
 COIL + EE 20.6 5.27
 TGHT  20.7 5.88

Wednesday, February 08, 2017, 08:30: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.

Wednesday, February 08, 2017, 10:00: Check. Vacuum @ 3.33E-07T.

Wednesday, February 08, 2017, 11:40: Check. Vacuum @ 1.70E-07T.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 30.2 4.06
 TBHT 21.0  3.17
 COIL + EE  21.1 5.22
 TGHT

 21.3

 5.82

Wednesday, February 08, 2017, 13:30: Check. Vacuum @ 3.53E-07T.

Wednesday, February 08, 2017, 15:30: Auto-cooling started @ 2A per min. Vacuum @ 3.88E-07T.

***NOTE: Small water anomaly on RGA affecting Vacuum***


***NOTE: Small water anomaly on RGA affecting Vacuum continues***

Thursday, February 09, 2017, 08:08: Sources/power off.

Thursday, February 09, 2017, 08:10: Water lines purged.

Thursday, February 09, 2017, 08:11: RGA off.

Thursday, February 09, 2017, 09:00: Venting

Entry  Wednesday, January 25, 2017, 14:57, Aaron Schmidt, , , , , 42218-11, 41751-6, Done, Target cleaning test LP-SIS Full Clean LP-SIS_Full_Clean.docxOMEGA_OM-DAQPRO-5300_15-Feb-17_13.30.42.dlpTS-2017-02-09-10-40.rga

Target Test (Fully Cleaned vs Crystal Clean only).

For all tests:

-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.

- Ensure previous test turbos are off by 8:15 and started venting by 9:15am to meet timeline.

-Start Roughing by 10:10am +/- 1 minute.

-TGHT / TBHT ramping starts @ 8:30am. 2A per min to 580A / 200A

ALL START TIMES MUST BE CONSISTENT.


***Pre-outgassed*** Heat Shield W.O# 41751-6: Includes insulators, new Al grounded 9-pin, bracket, & gripper arms. Blank/Plate. No source cup/EE.


HP-SIS Target # 42218-11: Full Clean. Crystal Clear, Acetone, & Methanol used.


Thursday, February 09, 2017, 09:44: HS removed from test stand. Exchange target.

Thursday, February 09, 2017, 10:04: Target # 42218-11 placed into test stand. Door open for 20 minutes.

Thursday, February 09, 2017, 10:10: Roughing.

 Thursday, February 09, 2017, 10:10: Doors sealed for roughing.

Thursday, February 09, 2017, 10:11: BV1B OPEN. Opened @ 428T.

Thursday, February 09, 2017, 10:29: Both Turbo pumps started.

Thursday, February 09, 2017, 10:34: Ion gauge on. TP1B @ speed 42 KRPM.

Thursday, February 09, 2017, 10:37: TP1A @ speed 38 KRPM.

Thursday, February 09, 2017, 10:40: RGA on. Vacuum @ 1.45E-05T.

Thursday, February 09, 2017, 10:47: Strip tool Vacuum.Current restarted.

Thursday, February 09, 2017, 15:34: Check. Vacuum @ 3.97E-07T.

***NOTE: Small water anomaly on RGA affecting Vacuum***


***NOTE: Small water anomaly on RGA affecting Vacuum*** Continues. Monitor through heating.

Friday, February 10, 2017, 08:06: Water lines opened. No response on RGA. Vacuum stable @ 3.24E-07T.

Friday, February 10, 2017, 08:08: Power/Sources on.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 24.4 4.02
 TBHT 24.2 3.22
 COIL + EE 24.2 5.26
 TGHT  24.4 5.90

08:30: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.

10:00: Check. Vacuum @ 3.68-4.87E-07T. (Anomaly variant)

11:40: Check. Vacuum @ XE-07T.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 34.6 4.12
 TBHT 25.5  3.21
 COIL + EE  25.5 5.29
 TGHT

 27.3

 5.88

Check. Vacuum @ 4.41E-07T.

 Auto-cooling started @ 2A per min. Vacuum @ 4.25E-07T.


Tuesday, February 14, 2017, 08:22: Power/sources off.

Tuesday, February 14, 2017, 08:23: Water lines purged.

Tuesday, February 14, 2017, 08:26: RGA off. Ion Gauge off. Turbo pumps off.

Entry  Wednesday, July 19, 2017, 09:13, Aaron Schmidt, Ta Targets, , , , , , Done, Ion Peaks Magnet_peaks.xlsx

Attached is a recent list of Ta targets with their extracted ions peaks.

Entry  Tuesday, December 12, 2017, 08:32, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, Pump down w/ possible outgas Empty_Chamber_-_Silver_bolts_removed.docxTS-2017-12-12-09-00.rgaTS-2017-12-13-06-50.rga

Check achievable vacuum. Watch for spikes on RGA. Silver bolts removed from the chamber. Vented steel screws in.

Tuesday, December 12, 2017, 08:23: Doors open from previous test. (Open for 7 minutes)

Tuesday, December 12, 2017, 08:30: Doors closed. Roughing.

Tuesday, December 12, 2017, 08:50: Turbo pumps on.

Tuesday, December 12, 2017, 08:56: Ion gauge on.


Wednesday, December 13, 2017, 06:46: Check. Vacuum @ 5.44e-07T. RGA Error.

Wednesday, December 13, 2017, 06:49: RGA restarted.

Wednesday, December 13, 2017, 06:52: Water lines opened. Vacuum @ 5.44e-07T

Wednesday, December 13, 2017, 06:54: Power on.

Wednesday, December 13, 2017, 06:56: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.


Friday, December 15, 2017, 13:37: Auto-cooling @ 2A per min


Monday, December 18, 2017, 08:15: Power/source off.


Wednesday, December 20, 2017, 09:07: RGA off.

Wednesday, December 20, 2017, 09:08: Both Ion gauges and all 4 turbo pumps off.

Entry  Wednesday, December 20, 2017, 09:11, Aaron Schmidt, , LP-SIS, , , (Blank), 42752-3, Done, Holiday Shut Down 

Power/sources already off. The water cooling is currently left on.

Wednesday, December 20, 2017, 09:07: RGA off.

Wednesday, December 20, 2017, 09:08: Both Ion gauges and all 4 turbo pumps off.

Wednesday, December 20, 2017, 11:21: Valves closed. Roughing pumps off.

Wednesday, December 20, 2017, 11:22: RGA shut off completely.

Entry  Monday, January 22, 2018, 09:04, Aaron Schmidt, , , , , , , Done, Power outage & Controller replacement. 

Computer, TS, epics, restarted. Power checks

Monday, January 22, 2018, 09:00: ISAC PLC TLCIOC Restarted. 

Turbo pumps restarted.

Monday, January 22, 2018, 09:26: New controller for TSG:TP1B brought in.

(Connect) Global reset. Resart Turbo pumps.

Monday, January 22, 2018, 09:40: Both turbo pumps @ speed.

Vacuum controls ok

Sources ok

Optics -  Issues. Some restart, others do not.

 

Entry  Friday, January 26, 2018, 11:10, Aaron Schmidt, , , , , , , Done, Helium tank replacement 

Friday, January 26, 2018, 11:08: New Helium tank installed inside the Test Stand.

-The 'Full' tag remains. The He tank was not opened.

-The old tank was placed beside the Test Stand beneath/beside the power switch.