Entry  Monday, May 26, 2014, 14:15, Aurelia Laxdal, SiC#30, HP-FEBIAD, ITE, TM3, , , Done, SiC#30 HV and Heaters Conditioning  SiC#30_Conditioning_2nd_time.docx
    Reply  Friday, June 13, 2014, 08:43, Anders Mjos, SiC#30, HP-FEBIAD, ITE, TM3, 38481-8, 39956-5, Done, SiC#30 HV and Heaters Conditioning  
       Reply  Tuesday, June 17, 2014, 15:22, Anders Mjos, SiC#30, HP-FEBIAD, ITE, TM3, 38481-8, 39956-5, In progress, SiC#30 HV and Heaters Conditioning  SiC#30_Conditioning_3rd_time.docx
Message ID: 384     Entry time: Friday, June 13, 2014, 08:43     In reply to: 382     Reply to this: 386
Author: Anders Mjos 
Target/No.#: SiC#30 
Source: HP-FEBIAD 
Station: ITE 
Module: TM3 
Target Oven W.O#: 38481-8 
Heat Shield W.O#: 39956-5 
Status: Done 
Subject: SiC#30 HV and Heaters Conditioning  

Aurelia Laxdal wrote:

HV and Heaters Conditioning for SiC#30 was completed Friday, May 23, 2014. The target was cooled down and it's ready for the on-line installation.

 Friday, June 13, 2014, 08:43: Turbos stopped. Vacuum at 1.2E-7 T


Monday, June 16, 2014, 08:26: Venting. Water purged.

Monday, June 16, 2014, 09:00: Target removed