Monday, May 26, 2014, 14:15, Aurelia Laxdal, SiC#30, HP-FEBIAD, ITE, TM3, , , Done, SiC#30 HV and Heaters Conditioning
|
Friday, June 13, 2014, 08:43, Anders Mjos, SiC#30, HP-FEBIAD, ITE, TM3, 38481-8, 39956-5, Done, SiC#30 HV and Heaters Conditioning
|
Tuesday, June 17, 2014, 15:22, Anders Mjos, SiC#30, HP-FEBIAD, ITE, TM3, 38481-8, 39956-5, In progress, SiC#30 HV and Heaters Conditioning
|
|
Message ID: 382
Entry time: Monday, May 26, 2014, 14:15
Reply to this: 384
|
Author: |
Aurelia Laxdal |
Target/No.#: |
SiC#30 |
Source: |
HP-FEBIAD |
Station: |
ITE |
Module: |
TM3 |
Target Oven W.O#: |
|
Heat Shield W.O#: |
|
Status: |
Done |
Subject: |
SiC#30 HV and Heaters Conditioning |
|
|
HV and Heaters Conditioning for SiC#30 was completed Friday, May 23, 2014. The target was cooled down and it's ready for the on-line installation. |
|