444
|
Thursday, May 21, 2015, 17:26 |
Anders Mjos | | LP-FEBIAD | | TM2 | | | In progress | Re-testing new TM2 Source Tray | Thursday, May 21, 2015, 17:26: Roughing
Thursday, May 21, 2015, 18:02: Turbos
started |
|
443
|
Thursday, May 21, 2015, 16:40 |
Anders Mjos | | | | | | | Problems/Solutions | Reconfigured service cap coil connections | The service cap has been reconfigured
(colling and electric) to be compatible with
the TM2 Source tray. Coil- is E & F , |
|
442
|
Tuesday, May 19, 2015, 19:10 |
Anders Mjos | | | | | | | Problems/Solutions | EPICS white out | Likely caused by the PLC. e-fault
8139
Wednesday, May 20, 2015 |
|
441
|
Wednesday, May 13, 2015, 13:27 |
Anders Mjos | | LP-FEBIAD | | TM2 | | 39230-1 | In progress | Re-testing new TM2 Source Tray | NOTE:
COIL PS is a 100 A supply, thus actual COIL
current is 0.5x COIL set point. |
|
440
|
Friday, May 08, 2015, 09:07 |
Anders Mjos | | | | | | | Problems/Solutions | EPICS lost contact with the PLC | Everything shut down, while EPICS showed
everyhing to be on.
Controls group (Dave Morris) has |
|
439
|
Monday, May 04, 2015, 09:51 |
Anders Mjos | | | | | | | Problems/Solutions | FEBIAD Coil power supply replaced | Power supply did not work after high
voltage conditioning. On Friday May 1st John
Chow replaced the power supply with a |
|
438
|
Friday, April 24, 2015, 12:26 |
Anders Mjos | | LP-FEBIAD | | TM2 | | 39230-1 | In progress | Testing new TM2 Source Tray | Photos on DocuShare
Friday, April 24, 2015 |
|
437
|
Friday, April 24, 2015, 12:25 |
Anders Mjos | | | | | | | Problems/Solutions | Backing line pressure high | TSG:RP1 backing line pressure is >200
mT. An e-fault has been submitted to have
the roughing pump replaced. |
|
436
|
Wednesday, April 22, 2015, 13:17 |
Anders Mjos | | | | | | | | Source Tray Removed | by Mico, Dan and Anders |
|
435
|
Monday, April 13, 2015, 13:07 |
Anders Mjos | | | | | | | Problems/Solutions | ISAC Test Stand Optical elements power supply drop out | See e-fault 8027
Monday, April 13, 2015
Kevin and Graham are working on it |
|
434
|
Thursday, April 09, 2015, 11:21 |
Anders Mjos | | | | | | | Problems/Solutions | No RGA communcations | RGA stopped working. Likely after a spark
yesterday. |
|
433
|
Thursday, April 02, 2015, 15:42 |
Anders Mjos | TM2 Test Target | LP-FEBIAD | | TM2 | | 39230-1 | Done | TM2 Test Target Conditioning | Thursday, April 02, 2015, 15:42: Roughing
Thursday, April 02, 2015, 16:12:
Turbos started |
|
432
|
Tuesday, March 24, 2015, 09:50 |
Anders Mjos | | | | | | | In progress | Empty chamber | Roughed down on Friday 20th
Tuesday, March 24, 2015, 09:49: Turbos
started |
|
431
|
Monday, March 16, 2015, 18:53 |
Anders Mjos | Ta#45 | HP-SIS | ITE | TM4 | 38817-5 | | In progress | Conditioning Ta#45 | Monday, March 16, 2015, 18:53: Started
turbos
Monday, March 16, 2015, 19:00: Turbos |
|
430
|
Thursday, February 26, 2015, 10:11 |
Anders Mjos | | | | | | | In progress | Installing FEBIAD test target for emittance rig tests | Thursday, February 26, 2015, 10:11: Stopped
turbos
Thursday, February 26, 2015, 11:23: |
|
429
|
Wednesday, February 18, 2015, 13:32 |
Anders Mjos | | | | | | | Problems/Solutions | Switched off system in preparation for power outage | Thursday, February 19, 2015, 12:14: Starting
system again after the power outage
Thursday, February 19, 2015, 13:27: |
|
428
|
Tuesday, February 17, 2015, 14:41 |
Anders Mjos | | | | | | | In progress | Pumping down empty chamber | Tuesday, February 17, 2015, 14:35: Roughing.
Doors were difficult to get to seal.
Tuesday, February 17, 2015, 15:11: |
|
427
|
Friday, February 13, 2015, 13:59 |
Anders Mjos | | | | | | | Problems/Solutions | PLC failure | The PLC CPU came out of the socket around
11:50am today (Dave Morris). The CPU had
not been properly attached. This resulted |
|
426
|
Tuesday, February 03, 2015, 16:10 |
Anders Mjos | | | | | | | Problems/Solutions | Current read back on TBHT has been corrected to 600 A | By controls group |
|
425
|
Tuesday, February 03, 2015, 14:33 |
Anders Mjos | Empty | LP-SIS | | | | | In progress | Target with new center block and new EE insulator | Also with newly installed RGA
Tuesday, February 03, 2015, 14:33:
Roughing |
|