Entry  Tuesday, December 13, 2022, 16:12, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 2 Re-routed_Anode_FEBIAD_12-2022_Test_2.docx
Thermocouples installed (X):
O - O
O - Anode
Entry  Monday, May 28, 2018, 08:46, Aaron Schmidt, , LP-FEBIAD, , TM2, 41790-9, 42752-5, In progress, New TM source tray swap out.  New_TM_Source_Tray_2018.docxTS-2018-05-30-06-30.rgaER-580-310-30kV-m28.txtER-580-320-30kV-M39.txt2018_TM2_Source_Tray_in_Test_Stand_-_Test_Results.docx
Monday, May 28, 2018, 08:45: Venting. Prep For removal.
Close FS#8. Clean up water
Adjust
Entry  Friday, August 10, 2018, 10:56, Aaron Schmidt, , , , , , , Problems/Solutions, New PS installation and Cathode BIAS set 
Friday, August 10, 2018, 10:25: Remove TBHT 500 PS and replace with TBHT 600 PS.
Friday, August 10, 2018, 10:50: Switch wiring in the high voltage cage from and Anode BIAS to Cathode BIAS setting.
Friday, August 10, 2018, 11:32: TBHT limit increased from 500A to 600A by Controls group.
Entry  Wednesday, November 27, 2019, 16:01, Fernando Maldonado, , , , , , , Problems/Solutions, New Controller for TP6 
Wednesday, November 27, 2019, 15:31: During HV tests, bias was around 55kV when a spark occur and almost immediately the controller for TP6 made a noticeable
noise and smoke started to come out of it.
Control room notified about the smoke.
Entry  Friday, February 23, 2018, 08:50, Aaron Schmidt, , , , , , , , New Al Corona  
Friday, February 23, 2018, 08:50 
Entry  Tuesday, January 20, 2015, 14:31, Anders Mjos, , , , , , , Problems/Solutions, Ne leak disconnected for recallibration 
SN 11-231 from VIC
Entry  Tuesday, October 27, 2020, 08:54, Aaron Schmidt, Nb#9 , LP-SIS, ITW, TM2, 44508-2, 43515-4, In progress, Nb#9 Conditioning Nb#9_Conditioning.docxER-580-230-30kV-M133.txtER-580-230-30kV-M23.txt
Tuesday, October 27, 2020, 08:40: Roughing.
Tuesday, October 27, 2020, 09:13: TP1B on.
Tuesday, October 27, 2020, 10:13: TP1A on.
Entry  Friday, August 31, 2012, 13:59, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Nb#7 installed 
Friday, August 31, 2012, 15:19: roughing
Friday, August 31, 2012, 15:39 : starting turbos
Friday, August 31, 2012, 15:44 : TP1B at speed
    Reply  Tuesday, September 04, 2012, 08:11, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , Done, Nb#7 installed 


    
        
            Anders Mjos wrote:
        
        
            
            Friday, August 31, 2012, 15:19: roughing
Entry  Wednesday, January 05, 2022, 15:12, Carla Babcock, , , , , , , , Modifications to test stand for mass marker tests 
Connection of TBHT negative to HV common removed (R4 in circuit diagram). Labelled and put in MRO bucket.
Anode connection moved to feedthrough J.
Rewired multipin patch panel. Left some grounded (HVC) wires hanging, should probably make this nice later.
Entry  Tuesday, December 01, 2020, 11:56, Carla Babcock, , , , , , , In progress, Modifications to test stand for TM3 tests 
Tuesday, December 01, 2020, 11:56 :
TSG:BIAS unplugged and controls pigtail (made by Ray) added in order to connect controls cable to TCS:BIAS, which is now installed in the same
rack.
Entry  Wednesday, December 02, 2020, 08:32, Carla Babcock, , , , , , , , Modifications to test stand for TM3 tests 
Wednesday, December 02, 2020, 08:31 :
Added copper wire connection to multipin screw terminals in HV cage to make sure they are grounded.
Attached grounding rod to back of HV cage. Not ideal, but couldn't find a better place without making a extension to the cable. Will see what John
Entry  Friday, December 04, 2020, 08:53, Carla Babcock, , , , , , , , Modifications to test stand for TM3 tests 
Friday, December 04, 2020, 08:52 :
Test stand roughed down to 29mT overnight. Started turbos for testing later.
Entry  Tuesday, December 08, 2020, 11:54, Carla Babcock, , , , , , , , Modifications to test stand for TM3 tests 20201207_135011.jpg20201207_134951.jpgScreenshot_from_2020-12-09_19-41-36.png
The copper tubes to be used in the TM3 test piece may have flux inside them from soldering the end caps on. There are holes along the length for outgassing,
and we will try to bake them out in the test stand before installing them. There is still a dummy bake out target installed there, see the photo for how
the tubes are loaded in. TGHT ramping started around 3pm.
Entry  Friday, December 11, 2020, 15:02, Carla Babcock, Sam McEwen, Aaron Schmidt, , , , , , , , Modifications to test stand for TM3 tests 20201211_140703.jpg20201211_140639.jpg20201211_140605.jpg
Test piece installed with Sam, Aaron and Alexander. Ended up shimming the support stand (middle foot) since it seemed to be bowing a bit and distorting
the gap between the containment box stand-in piece and the service tray piece. We should measure the gaps when testing is done with the same configuration.
Installation was not too hard, installed the whole thing as one piece. Had to remove the middle foot on the long side to get it through the door but otherwise
Entry  Thursday, December 03, 2020, 15:55, Carla Babcock, Alexander Shkuratoff, , , , , , , , Modifications to ISAC test stand for TM3 tests 20201203_150458.jpg20201203_173725.jpg
Thursday, December 03, 2020, 15:54 :
Got sign off from John Chow to run the system, though the nylon insulator was not ready when he came by. But we went over everything together.
Installed blue nylon insulator with all vacuum surfaces cleaned at least with methanol. No NPT fitting or tube installed, just testing service
Entry  Thursday, June 27, 2019, 09:51, Fernando Maldonado, , , , , , , Problems/Solutions, Melted cables changed 
See elog 737 

    
        
            Fernando
Entry  Friday, November 02, 2012, 14:20, Aurelia Laxdal, , LP-SIS, ITW, TM1, , , , Mass scan done 


Normal
0




false
false
false

EN-US
X-NONE
X-NONE

Entry  Thursday, April 04, 2024, 10:38, Dave Neilson, , LP-SIS, , , 44691-8, 45235-26, Done, Mass marker testing 
 Thursday, April 04, 2024, 09:49: Target inserted yesterday, April 3. mass marker tube connections carefully confirmed. Vacuum roughed, turbo pumps
switched on at end of day. Water cooling turned on this morning. 
Thursday, April 04, 2024, 09:52 : Vacuum at 6.4e-6.  Not low enough to bypass lockout for TGHT TBHT ramp.
Entry  Thursday, May 02, 2024, 13:45, Dave Neilson, -, LP-SIS, , , 44691-8, 45235-26, In progress, Mass marker testing 
 Wednesday, May 01, 2024, 12:44:  pumped down to rough vacuum, TP1B now on.
Wednesday, May 01, 2024, 12:49:  TP1A on.
Thursday, May 02, 2024, 9:10:  water cooling on. no effect on vacuum