ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  444   Thursday, May 21, 2015, 17:26 Anders Mjos LP-FEBIAD TM2  In progressRe-testing new TM2 Source Tray Thursday, May 21, 2015, 17:26: Roughing
Thursday, May 21, 2015, 18:02: Turbos
started
 TM2_Source_Tray_Test_FEBIAD_Target_Test_3.docx2015-05-22_Flow.xlsx 
  443   Thursday, May 21, 2015, 16:40 Anders Mjos      Problems/SolutionsReconfigured service cap coil connections The service cap has been reconfigured
(colling and electric) to be compatible with
the TM2 Source tray. Coil- is E & F ,
 TestStandSourceTray.jpgTM2SourceTray.jpg 
  442   Tuesday, May 19, 2015, 19:10 Anders Mjos      Problems/SolutionsEPICS white out Likely caused by the PLC. e-fault
 8139

Wednesday, May 20, 2015
  
  441   Wednesday, May 13, 2015, 13:27 Anders Mjos LP-FEBIAD TM2 39230-1In progressRe-testing new TM2 Source TrayNOTE:
COIL PS is a 100 A supply, thus actual COIL
current is 0.5x COIL set point.
  
  440   Friday, May 08, 2015, 09:07 Anders Mjos      Problems/SolutionsEPICS lost contact with the PLCEverything shut down, while EPICS showed
everyhing to be on.
Controls group (Dave Morris) has
  
  439   Monday, May 04, 2015, 09:51 Anders Mjos      Problems/SolutionsFEBIAD Coil power supply replaced Power supply did not work after high
voltage conditioning. On Friday May 1st John
Chow replaced the power supply with a 
  
  438   Friday, April 24, 2015, 12:26 Anders Mjos LP-FEBIAD TM2 39230-1In progressTesting new TM2 Source TrayPhotos on DocuShare

 
Friday, April 24, 2015
 TM2_Source_Tray_in_Test_Stand_-_Electrical_Check.pdfTM2_Source_Tray_in_Test_Stand_FEBIAD_Coil_Water_Leak.pdfTM2_Source_Tray_Test_FEBIAD_Target.docxTM2_Source_Tray_Coil_Leak_2015-04-30.png 
  437   Friday, April 24, 2015, 12:25 Anders Mjos      Problems/SolutionsBacking line pressure highTSG:RP1 backing line pressure is >200
mT. An e-fault has been submitted to have
the roughing pump replaced.
  
  436   Wednesday, April 22, 2015, 13:17 Anders Mjos       Source Tray Removed by Mico, Dan and Anders   
  435   Monday, April 13, 2015, 13:07 Anders Mjos      Problems/SolutionsISAC Test Stand Optical elements power supply drop out See e-fault 8027 
Monday, April 13, 2015
Kevin and Graham are working on it
  
  434   Thursday, April 09, 2015, 11:21 Anders Mjos      Problems/SolutionsNo RGA communcationsRGA stopped working. Likely after a spark
yesterday.
  
  433   Thursday, April 02, 2015, 15:42 Anders MjosTM2 Test TargetLP-FEBIAD TM2 39230-1DoneTM2 Test Target ConditioningThursday, April 02, 2015, 15:42: Roughing
Thursday, April 02, 2015, 16:12:
Turbos started
 TM2_FEBIAD_Test_Target.docxER_Scans.zip 
  432   Tuesday, March 24, 2015, 09:50 Anders Mjos      In progressEmpty chamberRoughed down on Friday 20th
Tuesday, March 24, 2015, 09:49: Turbos
started
  
  431   Monday, March 16, 2015, 18:53 Anders MjosTa#45HP-SISITETM438817-5 In progressConditioning Ta#45 Monday, March 16, 2015, 18:53: Started
turbos
Monday, March 16, 2015, 19:00: Turbos
 Ta#45_Test_Stand.docxTa#45_2015-03-17_Mar_17_2015_09-05-31_AM.ana 
  430   Thursday, February 26, 2015, 10:11 Anders Mjos      In progressInstalling FEBIAD test target for emittance rig testsThursday, February 26, 2015, 10:11: Stopped
turbos
Thursday, February 26, 2015, 11:23:
 ER_Test_w_FEBIAD.docxFebiadTS.xls 
  429   Wednesday, February 18, 2015, 13:32 Anders Mjos      Problems/SolutionsSwitched off system in preparation for power outageThursday, February 19, 2015, 12:14: Starting
system again after the power outage
Thursday, February 19, 2015, 13:27:
  
  428   Tuesday, February 17, 2015, 14:41 Anders Mjos      In progressPumping down empty chamberTuesday, February 17, 2015, 14:35: Roughing.
Doors were difficult to get to seal.
Tuesday, February 17, 2015, 15:11:
  
  427   Friday, February 13, 2015, 13:59 Anders Mjos      Problems/SolutionsPLC failureThe PLC CPU came out of the socket around
11:50am today (Dave Morris). The CPU had
not been properly attached. This resulted
  
  426   Tuesday, February 03, 2015, 16:10 Anders Mjos      Problems/SolutionsCurrent read back on TBHT has been corrected to 600 A By controls group   
  425   Tuesday, February 03, 2015, 14:33 Anders MjosEmptyLP-SIS    In progressTarget with new center block and new EE insulatorAlso with newly installed RGA
Tuesday, February 03, 2015, 14:33:
Roughing
 2015-02-04-1530trace.pngLP-SIS-newCenterBlock_Feb_05_2015.zip 