Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 25 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
  ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Statusdown Subject Text Attachments
  695   Thursday, November 08, 2018, 10:54 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressTest FEBIAD w/ Silver bolts & sealed end capsSilver bolts used on Coil, TGHT, &
TBHT. Back panel opened for new gas bottles.
Thursday, November 08, 2018, 10:52:
  
  700   Wednesday, December 12, 2018, 13:22 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressAnode leak current check.Wednesday, December 12, 2018, 13:15: Power
/ Sources on.
Wednesday, December 12, 2018, 13:20:
  
  703   Tuesday, January 08, 2019, 08:11 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressTS restart Tuesday, January 08, 2019, 08:00: Epics
white out fixed. Ref: Fault report 11981.
Tuesday, January 08, 2019, 08:10:
  
  716   Friday, April 05, 2019, 07:02 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressTS operation test - LP FEBIADDue to previous issues, a full run / test
should be performed on the ISAC Test Stand.
Friday, April 05, 2019, 07:00: RGA
 TS_-_New_BIAS__EZL_Testing_-_2019.docxTS-2019-04-05-07-00.rga 
  719   Friday, April 26, 2019, 13:45 Aaron SchmidtTa#58LP-SISITETM243044-442972-7In progressConditioning Ta#58 HSFriday, April 26, 2019, 13:43: Roughing.
Friday, April 26, 2019, 14:12: Turbo
pumps on.
 7x 
  720   Friday, May 03, 2019, 08:30 Anders Mjos      In progressTrainingTraining: Venting and pump down
Friday, May 03, 2019, 08:30: Turbo
pumps stopped.
  
  721   Tuesday, May 07, 2019, 13:16 Aaron SchmidtTa#58LP-SISITETM243044-4 In progress9-pin connection configuration (Using Ta#58)Ref:
https://elog.triumf.ca/TIS/Test-Stand/679
Pin configuration between top 9-pin
 HV_Tests_2019_-_AL_-_1.docxTS-2019-05-08-08-12.rgaTS-2019-05-08-14-20.rga 
  722   Tuesday, May 14, 2019, 10:22 Aaron SchmidtZrC#8LP-SISITETM243044-542972-3In progressConditioning ZrC#8 HSTuesday, May 14, 2019, 10:21: Roughing
Tuesday, May 14, 2019, 10:51: Turbo
pumps on.
 ZrC#8.docxTS-2019-05-14-11-05.rgaTS-2019-05-16-07-30.rgaTS-2019-05-21-07-10.rgaITE-TM2-ZrC#8-LP-SIS_Test_Stand.docx 
  724   Saturday, May 25, 2019, 12:43 Aaron SchmidtTest FEBIAD / TM4LP-FEBIAD TM4395530-342752-5In progressInstalled TM4 Source TraySilver bolts on TGHT & Coil Lines.
Oxide steel bolts on TBHT. Filed target to
suit / fit (Previously heated). Rubber O-rings
 TM4_Source_Tray_-_2019_-_Leak_Check.docxTM4_Source_Tray_-_2019.docxTS-2019-05-27-07-08.rga 
  725   Tuesday, May 28, 2019, 15:05 Aaron SchmidtTest FEBIAD / TM4LP-FEBIAD TM4395530-342752-5In progressTM4 Source Tray - Episode IISEE ELOG 724
Tuesday, May 28, 2019, 15:02: Roughing
Tuesday, May 28, 2019, 15:32: Turbos
 TM4_Source_Tray_-_2019_-_2.docxTS-2019-05-29-07-08.rgaTM4_Source_Tray_-_2019_-_3_-_HV_-_1.docxTM4_Source_Tray_-_2019_-_4_-_HV_-_2_-_Heat_on.docxTM4_Source_Tray_-_2019_-_5_-_HV_over_50_-Heat_on.docx 
  731   Tuesday, June 11, 2019, 14:33 Aaron SchmidtTest FEBIADLP-FEBIAD  395530-342752-5In progressISAC Source tray re-installed w/ optics tray.Tuesday, June 11, 2019, 14:33: Roughing.

Wednesday, June 12, 2019,
08:18: Venting to install FEBIAD.
  
  738   Wednesday, June 26, 2019, 11:34 Aaron SchmidtTest TaHP-SIS TM4No Target oven #42972-4In progressTest target for TM4 checksThe HP-SIS uses the older center block.
No serial number found. 
Loaded with Tantalum. Rough Target
  
  744   Monday, July 08, 2019, 09:20 Luca Egoritip2n1 ITE   In progressp2n heating test(see entry 742)
 
p2n target heated over the weekend
 Capture.PNGCapture1.PNG 
  750   Friday, August 02, 2019, 13:16 Aaron SchmidtP2N - 1     In progressp2n heating test 4Friday, August 02, 2019: p2n target installed
in the test stand, the ion source was fully
removed to avoid any risk of shorting. The
  
  753   Thursday, August 08, 2019, 09:12 Aaron Schmidt LP-FEBIAD   42752-7In progressP2N Setup - LP-FEBIAD targetInserted a used (heating) LP-FEBIAD target
with a basic heat shield assembly with no
end plate foil on the window side to observe
 8x 
  758   Monday, September 23, 2019, 13:30 Aaron SchmidtTa#59LP-SISITETM244062-542752-10In progressConditioning Ta#59 AssyMonday, September 23, 2019, 13:28: Roughing.
Monday, September 23, 2019, 13:38:
Closed BV1A / Opened BV1 A & B to open
 9x 
  761   Wednesday, October 02, 2019, 13:42 Aaron Schmidt LP-SIS  41790-943515-9In progressConditioning UC#(30) HSWednesday, October 02, 2019, 13:42: Roughing.
Wednesday, October 02, 2019, 14:13:
Turbo Pumps started.
 UC#30.docx 
  762   Friday, October 18, 2019, 15:01 Aaron SchmidtSiC#38HP-FEBIADITETM242464-442752-1In progressConditioning SiC#38 HP-FEBIADFriday, October 18, 2019, 14:58: Roughing.
Friday, October 18, 2019, 15:30:
Turbo pumps on.
 12x 
  769   Friday, November 01, 2019, 16:01 Fernando Maldonado LP-SIS  41790-9 43515-9 In progressPeek seal tests on UCx#30 HSFriday, November 01, 2019, 15:47: A symbiotic 
peek seal assembly  was installed on
the manipulator grip to verify the temperature
 UC#30-plus-peak-seal.docxTS-2019-11-01-16-22.rgaTS-2019-11-04-16-12.rgaTS-2019-11-05-08-30.rga 
  770   Friday, November 08, 2019, 14:21 Aaron Schmidt LP-SIS  41790-943515-9In progressNitrogen Bottle leak testFriday, November 01, 2019, 14:00: Nitrogen
bottle installed. Purged waterlines HS /
FS#5. Purge done in conjunction with SiC#38
  
ELOG V2.9.2-2455