  724   Saturday, May 25, 2019, 12:43 Aaron SchmidtTest FEBIAD / TM4LP-FEBIAD TM4395530-342752-5In progressInstalled TM4 Source TraySilver bolts on TGHT & Coil Lines.
Oxide steel bolts on TBHT. Filed target to
suit / fit (Previously heated). Rubber O-rings
 TM4_Source_Tray_-_2019_-_Leak_Check.docxTM4_Source_Tray_-_2019.docxTS-2019-05-27-07-08.rga 
  723   Wednesday, May 22, 2019, 13:47 Aaron Schmidt       Calibrated MasscorrWednesday, May 22, 2019, 13:44: Calibration
Confirmed.
New Masscorr setup:
  
  722   Tuesday, May 14, 2019, 10:22 Aaron SchmidtZrC#8LP-SISITETM243044-542972-3In progressConditioning ZrC#8 HSTuesday, May 14, 2019, 10:21: Roughing
Tuesday, May 14, 2019, 10:51: Turbo
pumps on.
 ZrC#8.docxTS-2019-05-14-11-05.rgaTS-2019-05-16-07-30.rgaTS-2019-05-21-07-10.rgaITE-TM2-ZrC#8-LP-SIS_Test_Stand.docx 
  721   Tuesday, May 07, 2019, 13:16 Aaron SchmidtTa#58LP-SISITETM243044-4 In progress9-pin connection configuration (Using Ta#58)Ref:
https://elog.triumf.ca/TIS/Test-Stand/679
Pin configuration between top 9-pin
 HV_Tests_2019_-_AL_-_1.docxTS-2019-05-08-08-12.rgaTS-2019-05-08-14-20.rga 
  720   Friday, May 03, 2019, 08:30 Anders Mjos      In progressTrainingTraining: Venting and pump down
Friday, May 03, 2019, 08:30: Turbo
pumps stopped.
  
  719   Friday, April 26, 2019, 13:45 Aaron SchmidtTa#58LP-SISITETM243044-442972-7In progressConditioning Ta#58 HSFriday, April 26, 2019, 13:43: Roughing.
Friday, April 26, 2019, 14:12: Turbo
pumps on.
 7x 
  718   Tuesday, April 23, 2019, 14:39 Aaron Schmidt LP-SIS   42752-8DoneConditioning UC#28 HS Tuesday, April 23, 2019, 14:39: Roughing.
Tuesday, April 23, 2019, 15:09: Turbo
pumps started.
 TS-2019-04-24-07-30.rgaUC#28_HS.docx 
  717   Monday, April 15, 2019, 14:42 Aaron Schmidt LP-SIS   42972-1DoneConditioning UC#27 HS & test FS#3New coil lines installed for P2N testing
later.
Monday, April 15, 2019, 14:15: Roughing.
 UC#27_&_FS#3_check.docxTS-2019-04-16-08-20.rga 
  716   Friday, April 05, 2019, 07:02 Aaron Schmidt LP-FEBIAD  395530-342752-5In progressTS operation test - LP FEBIADDue to previous issues, a full run / test
should be performed on the ISAC Test Stand.
Friday, April 05, 2019, 07:00: RGA
 TS_-_New_BIAS__EZL_Testing_-_2019.docxTS-2019-04-05-07-00.rga 
  715   Wednesday, March 27, 2019, 11:01 Aaron Schmidt      Problems/SolutionsBIAS PS replaced. TestWednesday, March 27, 2019, 10:25: BIAS
@ 1 kV
952V - 548uA on controls readback
 NEW_BIAS_PS_testing_-_2019.docx 
  714   Tuesday, March 26, 2019, 10:44 Aaron Schmidt      Problems/SolutionsEZL PS replaced. TestEZL checked. OK @ 5kV
BIAS PS issues.
2.3kV on screen. Read back on PS
 New_EZL_PS_testing_-_2019.docx 
  713   Thursday, March 21, 2019, 08:33 Aaron Schmidt       Pump down TSThursday, March 21, 2019, 08:32: Roughing.   
  712   Monday, March 11, 2019, 13:56 Aaron Schmidt      DoneTGHT PS replacedMonday, March 11, 2019, 13:55: The TGHT
PS was replaced.
Brought up to 20 A. Operation. ok.
  
  711   Thursday, March 07, 2019, 07:55 Aaron Schmidt LP-FEBIAD    Problems/SolutionsTS restart - Troubleshoot BIAS sparkThursday, March 07, 2019, 07:48: IV4 reset,
BV6 & TMS TP6 reset.
Turbo pump restarted.
 BIAS_spark_out_issue_-_2019.docxTS-2019-03-07-07-51.rga 
  710   Friday, March 01, 2019, 14:51 Aaron Schmidt LP-FEBIAD     Gas lines test & Emissions measurement prepFriday, March 01, 2019, 14:50:
SV5 replaced with a new valve.
SV1 disconnected from the He line
 gas-lines-changes.jpgGas_line_backing_pump_test_2019.docxTS-2019-03-05-09-45.rgaTS-2019-03-06-08-00.rga 
  709   Friday, February 22, 2019, 11:11 Aaron Schmidt LP-FEBIAD     Gas line backing pump testsBacking "mini pump" testing.
-Open gas lines & auto ramp (If
using HV, close up the back)
  
  708   Thursday, January 24, 2019, 08:42 Aaron Schmidt       IG6 fix (w/ instruction)TMS:IG6 had continued communication errors
post power outage & would not switch
on. After a power loss, IG6 switches automatically
  
  707   Monday, January 21, 2019, 10:55 Aaron Schmidt       2019 Anode tests FM-1Monday, January 21, 2019, 10:50: RGA on.
Monday, January 21, 2019, 10:54:
Waterlines opened. No response on RGA. Vacuum
  
  706   Monday, January 14, 2019, 09:47 Aaron Schmidt       TS restart after power outageMonday, January 14, 2019, 09:00: Epics
white out
Ref: Fault report  11993 (11981
  
  705   Thursday, January 10, 2019, 11:38 Aaron Schmidt       Power outtage prepThursday, January 10, 2019, 11:32: Power
down TS. Lock out.
Thursday, January 10, 2019, 11:36:
  