915
|
Monday, April 04, 2022, 20:56 |
Carla Babcock | | | | | | | | wiring reverted for cathode-bias FEBIAD | Wiring which was changed to run the mass
marker tests has been reverted:
anode bias cable connected |
|
|
952
|
Monday, December 19, 2022, 12:49 |
Carla Babcock | | HP-FEBIAD | | | | | | HP-FEBIAD tests | Monday, December 19, 2022, 12:06 : Tomislav
changed the polarity of the anode power supply
last week and everything has been closed |
|
|
953
|
Wednesday, December 21, 2022, 17:06 |
Carla Babcock | | | | | | | | Prep for power outage | Source and beamline power supplies turned
off in EPICS
HV cage power off |
|
|
954
|
Tuesday, January 03, 2023, 10:03 |
Carla Babcock | | | | | | | | Recovery from power outage | Easy recovery after power outage, just
had to power cycle the ground PLC IOC and
the BiRa IOC. |
|
|
40
|
Tuesday, February 28, 2012, 16:32 |
Brandon Humphries | | | | | | | | Initial settings for FEBIAD on Test Stand | ISAC Test Stand FEBIAD Ion Source and ISACT
optics screen grabs before practicing tuning.
Tune saved as: data/febiaddata/tune/120228-1620_0.snap |
|
|
1009
|
Friday, May 17, 2024, 17:24 |
Brady Borrmann | UC# | LP-FEBIAD | ITE | | 44692-4 | 45235-18 | In progress | Conditioning Spare Development Target | Friday, May 17, 2024, Spare FEBIAD Development
target installed
Friday, May 17, 2024, 17:00: Roughing |
|
|
1011
|
Wednesday, June 19, 2024, 15:50 |
Brady Borrmann | TiC#9 | HP-SIS | | | 45447-29 | 45235-19 | In progress | Conditioning TiC#9 | Wednesday, June19, 2024, Spare TiC HP-SIS
target installed. TiC#24C
Wednesday, June19, 2024, 15:00: Roughing |
|
|
1028
|
Tuesday, November 05, 2024, 16:40 |
Brady Borrmann | UC #24D (Assembly only) | LP-IG-LIS | | | | 44972-5 / 42972-9 | In progress | Conditioning UC#24D Assembly | 42972-5 Base / 42972-9 Lid
|
|
|
6
|
Friday, September 16, 2011, 12:39 |
Aurelia Laxdal | TaC#1 | LP-SIS | ITE | TM1 | 38634-6 | 36833-6 | In progress | HV conditioning | Started the HV conditioning: TSG:BIAS=30kV
and TSH:EE=-700V. |
|
|
7
|
Monday, September 19, 2011, 09:11 |
Aurelia Laxdal | TaC#1 | LP-SIS | ITE | TM1 | 38634-6 | 36833-6 | In progress | Started target and tube heaters. | Heaters conditioning went fine: 580A and
230A.
Did a mass scan: |
|
|
8
|
Tuesday, September 20, 2011, 19:00 |
Aurelia Laxdal | TaC#1 | LP-SIS | ITE | TM1 | 38634-6 | 36833-6 | Done | Finished testing TaC#1 | Tuesday, September 20, 2011:
Did another mass scan today at 5:40.
Saved as: plotdump-local-clean.txt Sept 20 |
|
|
15
|
Wednesday, September 28, 2011, 16:33 |
Aurelia Laxdal | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | In progress | HV conditioning | Started the HV conditioning: TSG:BIAS=30kV |
|
|
16
|
Thursday, September 29, 2011, 09:27 |
Aurelia Laxdal | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | In progress | Heaters conditioning | Started the heaters conditioning: TGHT
up to 580A and TBHT up to 230A. |
|
|
17
|
Friday, September 30, 2011, 18:03 |
Aurelia Laxdal | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | Done | Finished testing SiC#26 at the Test Stand | Today, did a did a mass scan: plotdump-local-clean.txt
Sep30 11 12-20-08.txt
Optimized a bit the tune with Friedhelm, |
|
|
18
|
Monday, October 03, 2011, 10:53 |
Aurelia Laxdal | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | Done | Target is ready to be removed. | Turned off the HV and locked up the transformer.
Isolated the ion source box. The target is
under vacuum and the water is still on. |
|
|
26
|
Tuesday, December 13, 2011, 14:10 |
Aurelia Laxdal | | | | | | | | Test Stand IOC reboot | Evgeniy rebooted the ISAC Test Stand IOC.
Re-started EPICS at the Test Stand.
Found all 4 turbo pumps off and their |
|
|
27
|
Monday, December 19, 2011, 13:09 |
Aurelia Laxdal | | | | | | | | Test Stand updates | In January Controls will install a new
firewall for ISAC Test Stand. Until then
ISAC Test Stand can be used, but it may require |
|
|
34
|
Friday, February 17, 2012, 10:27 |
Aurelia Laxdal | | | | | | | Done | Started the Archivers | Started both ISACT and SOURCES Archivers. |
|
|
83
|
Monday, May 14, 2012, 15:36 |
Aurelia Laxdal | | | | | | | | Test Stand - IOC reboot | Did a local IOC reboot to cure to white-out.
The test stand is now operational. |
|
|
84
|
Monday, May 14, 2012, 16:57 |
Aurelia Laxdal | | | ITE | TM4 | | | | SiC#27-HP-SIS installed in the Test Stand | Rick and John installed the ITE-TM4-SiC#27-HP-SIS-May2012
in the Test Stand. Pumping down. |
|