Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 10 of 49  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Monday, March 15, 2021, 16:10, Carla Babcock, , , , , , , , TISA emittance meter testing with new FEBIAD source Carla_tune_tracking.docx
Monday, March 15, 2021, 16:09 Target and ion source ramped to 400A/330A this afternoon
Monday, March 15, 2021, 18:53 : Tune through to final RPMs but not optimized. 5e-8 on FC0. Will turn down target and ion source values to TGHT/TBHT
350/250 until tomorrow. BIAS/EZL/COIL/ANODE all off.
Entry  Wednesday, March 10, 2021, 14:57, Aaron Schmidt, , HP-FEBIAD, , , , 42752-5, In progress, Emittance meter test with FEBIAD 
Wednesday, March 10, 2021, 14:54: Roughing.
Wednesday, March 10, 2021, 14:57: BV1A open.

Thursday, March 11, 2021, 09:41: TP1B on. 
Entry  Wednesday, March 10, 2021, 14:28, Aaron Schmidt, , , , , , , In progress, RP2 swap. 
Swapped RP2 out from a Varian SH-110 to a Varian PTS06001.
Wednesday, March 10, 2021, 14:20: RP2 on.
Wednesday, March 10, 2021, 14:27: Turbo pumps on
Entry  Wednesday, March 10, 2021, 11:10, Carla Babcock, , , , , , , , Venting for installation of emittance meters 
Wednesday, March 10, 2021, 10:48  : Venting beamline section only for installation of emittance meters.
Entry  Tuesday, March 02, 2021, 11:42, Aaron Schmidt, , , , , , , , TS Tripped. 
 
Entry  Monday, March 01, 2021, 16:13, Fernando Maldonado, , , , , , , Done, Temporary RGA installation EXTorr.PNG
 Monday, March 01, 2021, 16:03: An ExTorr RGA has been installed in the ISAC test stand.
The original SRS 100 is still broken ( e-log 778)
Entry  Monday, March 01, 2021, 12:58, Fernando Maldonado, , LP-FEBIAD, , , , , Done, FEBIAD parameter scans v2 
 Monday, March 01, 2021, 12:57: Roughing
Monday, March 01, 2021, 13:30: Turbos on. Started a bit late as I was distracted. They were ready at around 13:26
Monday, March 01, 2021, 13:41: IG1 on. 
Entry  Monday, February 22, 2021, 18:25, Fernando Maldonado, , HP-FEBIAD, , , , , Done, FEBIAD parameter scans ESC_-_Feb_23_FEBAID_parameter_initial_checks.docxER-580-290-30kV-m28_2021-2-23.txt
Monday, February 22, 2021, 17:48 Roughing
Monday, February 22, 2021, 18:17: Turbos on.
Monday, February 22, 2021, 18:25: IG1 on.
Entry  Friday, February 19, 2021, 13:44, Fernando Maldonado, , , , , , , Failed, FEBIAD parameter scans GND-COIL_spark.jpgGND-HS_spark.jpg
Friday, February 19, 2021, 13:28: Roughing
Friday, February 19, 2021, 13:43: Power on
Friday, February 19, 2021, 13:59: Turbos on
Entry  Thursday, February 18, 2021, 16:48, Fernando Maldonado, , , , , , , Failed, FEBIAD parameter scans 
Thursday, February 18, 2021, 15:19: Gas lines roughed and refilled. Gauge reads -50 kPa. Absolute pressure is 50 kPa.
IG1 @ 9.7 e-7 T.
Thursday, February 18, 2021, 15:27: BIAS/EZL/EE @ 30/13/1.5 kV. No sign of instabilities as before. Bias current=0.08 mA.
Entry  Thursday, February 18, 2021, 15:15, Fernando Maldonado, , , , , , , Done, HLA tests 
Thursday, February 18, 2021, 15:01: With the help of Spencer Kiy, we tested the proper communication from python to epics.
Getting TSP:Q1 PV: successful both from the web application and jupyter notebook.
Setting TSP:Q1 PV: successful from the web application, failed jupyter notebook.
Entry  Thursday, February 18, 2021, 11:03, Aaron Schmidt, , , , , , , Problems/Solutions, DI water pump configuration 
https://elog.triumf.ca/TIS/Test-Stand/847
There was a previous DI CU-LCW  pump trip as per the above elog. The CU-LCW pump was configured this morning. The water pressure is set to
80 PSI as per the MCR. Any further can overload & trip the pump. 
Entry  Thursday, February 18, 2021, 10:47, Aaron Schmidt, , , , , , , , Optics loss / CANBUS failure. 
Thursday, February 18, 2021, 10:45: TPS:Q3 & the TSB CBC CANBUS controllers had failed yesterday, as well as a cable was incorrectly seated. This
was fixed this morning.
Entry  Tuesday, February 16, 2021, 14:52, Fernando Maldonado, , , , , , , Problems/Solutions, Leak checking gas lines. 
Vacuum side
Tuesday, February 16, 2021, 13:42: The gas lines inside have been check. The inlet of the calibrated leak was not tighten properly and hence the
large leak observed.  FIXED.
Entry  Friday, February 12, 2021, 16:38, Fernando Maldonado, , , , , , , Failed, FEBIAD parameter scan - efficiency measurements - energy spread. 
Friday, February 12, 2021, 16:37: FEBIAD installed with mechanical calibrated leak
Friday, February 12, 2021, 16:38: Roughing.
Gas lines opened all the way to the sour. SV4 and SV5.
Entry  Friday, February 12, 2021, 12:16, Fernando Maldonado, , , , , , , Problems/Solutions, Grounding collimator cable from outside 20210212_121227.jpg
 Friday, February 12, 2021, 12:13: Since the collimator is not used, Carla and I installed a BNC short outside the cage. See picture.
Entry  Wednesday, February 10, 2021, 09:49, Aaron Schmidt, , LP-SIS, , , 44691-8, 44378-2 / 44378-3, Failed, Energy spread calibration with SIS spark_inside_chamber_roof.pngspark_inside_chamber_front_view.png
Note* target has a ring on the TGHT - Right leg. EE & PE placed. Target to HS OL - OK.
Wednesday, February 10, 2021, 09:37: Roughing.
Wednesday, February 10, 2021, 09:45: Bypass / Force applied on IG1 to test Anode.
Entry  Tuesday, February 09, 2021, 14:02, Aaron Schmidt, , , , , , , Problems/Solutions, DI water loss 
Tuesday, February 09, 2021, 13:43: DI water flow completely stopped.
Control room contacted. DI water loss confirmed.
Tuesday, February 09, 2021, 13:52: DI water flow returned.
Entry  Monday, February 08, 2021, 09:20, Aaron Schmidt, , LP-SIS, , , 44139-10, 44378-2, Failed, Energy spread calibration with SIS. No PE ESC_-_Feb_8_Start.docx
Re-salted. PE removed. EE Cleaned
Monday, February 08, 2021, 09:17: Roughing.
Monday, February 08, 2021, 09:46: TP1B on
Entry  Thursday, February 04, 2021, 19:22, Fernando Maldonado, , LP-SIS, , , 44139-10 , 44378-2, Done, Energy spread calibration with SIS ESC_-_Feb_5_Start.docx
See e-log entry: 884:
Thursday, February 04, 2021, 18:45: Roughing
Thursday, February 04, 2021, 19:13: Turbos on.
ELOG V2.9.2-2455