864
|
Monday, March 15, 2021, 16:10 |
Carla Babcock | | | | | | | | TISA emittance meter testing with new FEBIAD source | Monday, March 15, 2021, 16:09 Target and
ion source ramped to 400A/330A this afternoon
Monday, March 15, 2021, 18:53 : Tune |
|
863
|
Wednesday, March 10, 2021, 14:57 |
Aaron Schmidt | | HP-FEBIAD | | | | 42752-5 | In progress | Emittance meter test with FEBIAD | Wednesday, March 10, 2021, 14:54: Roughing.
Wednesday, March 10, 2021, 14:57:
BV1A open. |
|
862
|
Wednesday, March 10, 2021, 14:28 |
Aaron Schmidt | | | | | | | In progress | RP2 swap. | Swapped RP2 out from a Varian SH-110 to
a Varian PTS06001.
Wednesday, March 10, 2021, 14:20: |
|
861
|
Wednesday, March 10, 2021, 11:10 |
Carla Babcock | | | | | | | | Venting for installation of emittance meters | Wednesday, March 10, 2021, 10:48
: Venting beamline section only for installation
of emittance meters. |
|
860
|
Tuesday, March 02, 2021, 11:42 |
Aaron Schmidt | | | | | | | | TS Tripped. | |
|
859
|
Monday, March 01, 2021, 16:13 |
Fernando Maldonado | | | | | | | Done | Temporary RGA installation | Monday, March 01, 2021, 16:03: An
ExTorr RGA has been installed in the ISAC
test stand. |
|
858
|
Monday, March 01, 2021, 12:58 |
Fernando Maldonado | | LP-FEBIAD | | | | | Done | FEBIAD parameter scans v2 | Monday, March 01, 2021, 12:57: Roughing
Monday, March 01, 2021, 13:30: Turbos
on. Started a bit late as I was distracted. |
|
857
|
Monday, February 22, 2021, 18:25 |
Fernando Maldonado | | HP-FEBIAD | | | | | Done | FEBIAD parameter scans | Monday, February 22, 2021, 17:48 Roughing
Monday, February 22, 2021, 18:17:
Turbos on. |
|
856
|
Friday, February 19, 2021, 13:44 |
Fernando Maldonado | | | | | | | Failed | FEBIAD parameter scans | Friday, February 19, 2021, 13:28: Roughing
Friday, February 19, 2021, 13:43:
Power on |
|
855
|
Thursday, February 18, 2021, 16:48 |
Fernando Maldonado | | | | | | | Failed | FEBIAD parameter scans | Thursday, February 18, 2021, 15:19: Gas
lines roughed and refilled. Gauge reads -50
kPa. Absolute pressure is 50 kPa. |
|
854
|
Thursday, February 18, 2021, 15:15 |
Fernando Maldonado | | | | | | | Done | HLA tests | Thursday, February 18, 2021, 15:01: With
the help of Spencer Kiy, we tested the proper
communication from python to epics. |
|
853
|
Thursday, February 18, 2021, 11:03 |
Aaron Schmidt | | | | | | | Problems/Solutions | DI water pump configuration | https://elog.triumf.ca/TIS/Test-Stand/847
There was a previous DI CU-LCW
pump trip as per the above elog. The CU-LCW |
|
852
|
Thursday, February 18, 2021, 10:47 |
Aaron Schmidt | | | | | | | | Optics loss / CANBUS failure. | Thursday, February 18, 2021, 10:45: TPS:Q3
& the TSB CBC CANBUS controllers had
failed yesterday, as well as a cable was |
|
851
|
Tuesday, February 16, 2021, 14:52 |
Fernando Maldonado | | | | | | | Problems/Solutions | Leak checking gas lines. | Vacuum side
Tuesday, February 16, 2021, 13:42:
The gas lines inside have been check. The |
|
850
|
Friday, February 12, 2021, 16:38 |
Fernando Maldonado | | | | | | | Failed | FEBIAD parameter scan - efficiency measurements - energy spread. | Friday, February 12, 2021, 16:37: FEBIAD
installed with mechanical calibrated leak
Friday, February 12, 2021, 16:38: |
|
849
|
Friday, February 12, 2021, 12:16 |
Fernando Maldonado | | | | | | | Problems/Solutions | Grounding collimator cable from outside | Friday, February 12, 2021, 12:13:
Since the collimator is not used, Carla and
I installed a BNC short outside the cage. |
|
848
|
Wednesday, February 10, 2021, 09:49 |
Aaron Schmidt | | LP-SIS | | | 44691-8 | 44378-2 / 44378-3 | Failed | Energy spread calibration with SIS | Note* target has a ring on the TGHT - Right
leg. EE & PE placed. Target to HS OL
- OK. |
|
847
|
Tuesday, February 09, 2021, 14:02 |
Aaron Schmidt | | | | | | | Problems/Solutions | DI water loss | Tuesday, February 09, 2021, 13:43: DI water
flow completely stopped.
Control room contacted. DI water |
|
846
|
Monday, February 08, 2021, 09:20 |
Aaron Schmidt | | LP-SIS | | | 44139-10 | 44378-2 | Failed | Energy spread calibration with SIS. No PE | Re-salted. PE removed. EE Cleaned
Monday, February 08, 2021, 09:17:
Roughing. |
|
845
|
Thursday, February 04, 2021, 19:22 |
Fernando Maldonado | | LP-SIS | | | 44139-10 | 44378-2 | Done | Energy spread calibration with SIS | See e-log entry: 884:
Thursday, February 04, 2021, 18:45:
Roughing |
|
|