  RH-Meson Hall, Page 2 of 18  Not logged in ELOG logo
  ID Date Author Categorydown Type Specific Subject Text Attachments
  111   Thursday, April 03, 2014, 13:43 Isaac EarleStandard OperationTarget 2TargetT2 Profile Monitor OKT2 Profile Monitor actuation was tested
today from the control room and all is working
properly.  The position (IN / OUT) also
  
  112   Thursday, April 03, 2014, 16:35 Isaac EarleStandard OperationTarget 1CoolingT1 Cooling Package Started The T1 cooling package was started
around 2pm today.  There was no change
to the T1 volume vacuum during startup.
  
  113   Monday, April 14, 2014, 15:30 Isaac EarleStandard OperationTarget 2TargetT2 Target Moved to Position 4The T2-MK2 target (currently installed
in the beamline) was moved from position
0 to position 4 (10cm Be) using the portable
  
  117   Tuesday, June 03, 2014, 22:56 Isaac EarleStandard OperationTarget 2TargetT2 Target Position Moves (Development Shift)The T2 target was moved from Position 4
to Position 0 at 11:15am so the profile monitor
could be used during the development shift.
  
  128   Tuesday, November 18, 2014, 10:52 Isaac EarleStandard OperationTarget 1Active SumpRH Hot Cell Lab Active Sump ReleasedRelease of the Remote Handling Hot
Cell Lab active sump water was completed
  
  130   Friday, December 19, 2014, 14:35 Isaac EarleStandard OperationTarget 2OtherAmplified Air Shut OffThe BL1A amplified air system has been
shut off, and will remain off until required
for BL1A start-up in Spring 2015 (the lower
  
  132   Monday, January 05, 2015, 15:08 Isaac EarleStandard OperationTarget 2Water LeakCooling Packages Re-Started; Suspect External Water Leak at T2 PackagePumping was restored to 1A today by Vacuum
Group and the beam line returned to normal
vacuum levels.  Both cooling packages
  
  134   Monday, January 12, 2015, 16:35 Isaac EarleStandard OperationTarget 1CoolingT1 & T2 MRO StatusThe following tasks have been performed
at T1:
- T1 monolith painted using grey
  
  135   Wednesday, January 14, 2015, 13:32 Isaac EarleStandard OperationTarget 1TargetT1-MK2 Moved from B/L to Storage PitThe T1-MK2 target was transferred from
the beam line to the storage pit in hole
#5 using the transfer flask.  A maximum
  
  136   Wednesday, January 14, 2015, 15:06 Isaac EarleStandard OperationTarget 1OtherActive Item Stored in East Hot CellThe active item discovered on January 9,
2015 outside the BL1A bootbox has been moved
to the Meson Hall east hot cell for storage.
  
  142   Friday, February 20, 2015, 13:55 Isaac EarleStandard OperationTarget 2TargetT1 & T2 Target Moves- The T1-MK1 target was moved from the
hot cell to storage pit hole #3 (ready as
T1 spare)
  
  145   Thursday, March 12, 2015, 10:51 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Pos'n 4 Elevation MeasurementsElevation measurements of the T2-MK2 target
were taken in the hot cell to confirm previous
records in preparation for the T2 Protect
  
  148   Monday, April 20, 2015, 11:42 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target & T2 Protect Moved The T2-MK2 target was moved from
the hot cell to the beam line. The T2 Protect
Monitor was moved from the beam line to the
  
  149   Tuesday, April 21, 2015, 12:59 Isaac EarleStandard OperationTarget 1TargetT1-MK2 target moved from storage pit to beam line The T1-MK2 target was transported
from the storage pit to the beamline.  The
target measured approximately 10mSv/hr at
  
  150   Tuesday, April 21, 2015, 13:38 Isaac EarleStandard OperationTarget 1TargetAir Amplifier Started. T1 & T2 Profile Monitor Actuation Checked The lower air amplifier has been
started, and air supplied to the T1 and T2
areas by opening the appropriate ball valves
  
  152   Wednesday, April 22, 2015, 15:15 Isaac EarleStandard OperationTarget 1CoolingT1 and T2 Cooling Packages ReadyBoth cooling packages are running steadily
with the targets in Position 0.  
The demin flow (Q2) for both was
  
  155   Thursday, April 23, 2015, 16:29 Isaac EarleStandard OperationTarget 1TargetT1 & T2 Profile and Protect Monitors Electrical Check CompletedAn electrical check has been completed
for the T1 & T2 Profile and Protect Monitors
by Dave Cameron and Mike Russell.  They
  
  156   Friday, April 24, 2015, 11:53 Isaac EarleStandard OperationTarget 2TargetT2-MK2 Target Info Sheet & ElevationsT2-MK2 target information sheet, beam spot
measurements, and elevations were updated
and delivered to Operations. PDF copy attached.
 T2-MK2_-_2015_Elevations.pdf 
  159   Friday, May 08, 2015, 09:48 Isaac EarleStandard OperationOtherOtherBL1A Blocks RestoredReplacement of the BL1A blocks was completed
yesterday (May 8, 2015) in preparation for
first beam down 1A on May 12th.  The
 1A_Shield_Blocks_Restored_for_1A_beam_2015_&_2014.pdf 
  160   Tuesday, May 12, 2015, 21:20 Grant MinorStandard OperationTarget 1TargetT1 & T2 Targets moved from pos. 0 to pos. 4Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm.
  