19
|
Tuesday, March 06, 2012, 15:27 |
Isaac Earle | Repair | Target 1 | Target | Quick Connect Fittings on T1 Target | The air hoses for the profile monitor
supply line were inspected and no cracking
was found (was found on T2). The quick |
|
190
|
Wednesday, March 16, 2016, 16:50 |
Isaac Earle | Development | Target 2 | Controls | Preliminary Testing of T2 Control System Complete | Preliminary testing of the new
PLC control system and EPICS interface was |
|
189
|
Monday, March 07, 2016, 18:22 |
Isaac Earle | Development | Target 1 | Controls | Preliminary Testing of T1 Control System Complete | Preliminary testing of the new PLC
control system and EPICS interface was completed
today for the T1 target, T1 cooling package, |
|
83
|
Friday, May 31, 2013, 16:07 |
Isaac Earle | Repair | Target 1 | Target | Power Supply Fan Failure | Today (May 31, 2013) I was contacted
regarding a burning smell and high temperatures
around the T1/T2 controls racks. Erwin |
  |
297
|
Wednesday, July 06, 2022, 12:52 |
Adam Newsome | Other | Other | Hot Cell | Potential hot cell window oil leak | Some oil was noticed around the hot cell
window, on the control panel, and on the
ground below the control panel. A leak is |
|
163
|
Friday, June 19, 2015, 17:11 |
Isaac Earle | Development | Other | Controls | PLC Test of Ultrasonic Level Sensor | The new T1/T2 level sensors
(Omega LVCN414) were hooked up to the PLC |
|
177
|
Monday, October 05, 2015, 15:25 |
Isaac Earle | Standard Operation | Other | Other | Old T2 Protect Monitor Cassette Update | The T2 protect monitor cassette removed
in April 2015 (see E-log #154) was surveyed
today. It was approximately 3mSv/hr |
|
280
|
Friday, March 11, 2022, 15:06 |
Adam Newsome | Maintenance | Target 2 | Cooling | O-rings on T2 cooling package water reservoir changed | The four o-rings on top of the T2 cooling
package water reservoir were changed as
per the recommended 5 year replacement schedule. |
|
279
|
Friday, March 11, 2022, 15:05 |
Adam Newsome | Maintenance | Target 1 | Cooling | O-rings on T1 cooling package water reservoir changed | The four o-rings on top of the T1 cooling
package water reservoir were changed as per
the recommended 5 year replacement schedule. |
|
301
|
Tuesday, August 30, 2022, 14:24 |
Adam Newsome | Maintenance | Other | Hot Cell | Nuclear Ventilation - Filter Change | Mechanical Services Group changed the pre-filter
in the ventilation system on Aug. 29, 2022
as per work permit C2022-08-29-2. |
|
166
|
Thursday, July 09, 2015, 13:51 |
Isaac Earle | Development | Other | Target | New T1 and T2 Beryllium Targets Ordered | An order for new T1 and T2 beryllium
targets was submitted to the TRIUMF machine
shop today. A total of seven T2 targets |
|
207
|
Thursday, September 08, 2016, 17:26 |
Isaac Earle | Development | Other | Active Sump | New Active Sump High Level Switch and Electronics Installed | To address the deficiencies identified
in E-Logs #204 and #205 the old active sump
high level switch was replaced with Omega |
  |
215
|
Wednesday, March 15, 2017, 16:13 |
Isaac Earle | Standard Operation | Other | Active Sump | Meson Hall Hot Cell Lab Active Sump Water Released | On March 13th in the morning the
Meson Hall Hot Cell Lab active sump reached
the high level sensor. The system responded |
|
298
|
Thursday, July 28, 2022, 12:51 |
Adam Newsome | Repair | Other | Hot Cell | Meson Hall Hot Cell - Nuclear Ventilation Issue | It was reported today by Peter Bratt that
the nuclear ventilation system for the hot
cell is not functioning. At this time, the |
|
328
|
Wednesday, May 03, 2023, 10:06 |
Adam Newsome | Maintenance | Other | Hot Cell | Meson Hall Hot Cell - Nuclear Ventilation HEPA Filter Changed, Operational | The HEPA filter in the nuclear ventilation
system for the Meson Hall Hot Cell was changed
and tested by mechanical services under work |
|
36
|
Wednesday, June 06, 2012, 08:48 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the hot cell. No |
|
46
|
Friday, June 29, 2012, 14:18 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the cell. The |
|
62
|
Tuesday, November 13, 2012, 16:26 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side manipulator
in the west hot cell was completed today.
Part of the repair was done by entering |
|
91
|
Tuesday, November 12, 2013, 11:49 |
Isaac Earle | Repair | Target 1 | Target | MH Hot Cell Lab Manipulator Overhaul | Complete overhaul of all manipulators
in the Remote Handling Hot Cell Lab in the
Meson Hall was performed by Peter Dudley |
|
14
|
Wednesday, January 25, 2012, 13:26 |
Isaac Earle | Maintenance | Target 2 | Target | M9BB Returned to Beam Line | M9 beam blocker returned to beam line.
T2 target disconnected, picked up
using flask, and returned to beam line as |
|