258
|
Friday, February 28, 2020, 09:06 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand floor plate installed | The M9 service stand floor plate
(TB23351) was installed in the M9 pit yesterday.
Prior to installation all 5 threaded inserts |
|
267
|
Tuesday, July 07, 2020, 15:13 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand Lemo connector wiring | The diagram below shows the wiring for
the two connectors on the service stand (the
wires running from the stand to the power |
|
266
|
Tuesday, July 07, 2020, 13:22 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 | The M9 Q1Q2 magnet assembly lift
beam has been installed according to drawing
TB23401. The side-to-side as well as |
|
13
|
Monday, January 23, 2012, 15:27 |
Isaac Earle | Repair | Target 2 | Target | M20BB returned to beam line. M9BB moved to hot cell. | M20 beam blocker was transferred from the
hot cell to the beam line.
M9 beam blocker was transferred from |
|
237
|
Friday, April 13, 2018, 14:21 |
Isaac Earle | Maintenance | Other | Other | M20 beam blocker MRO and T1/T2 final checks | The M20 beam blocker main shaft seals were
replaced as per the T1/T2 target device maintenance
schedule. Both air cylinders were found |
|
323
|
Friday, March 03, 2023, 16:00 |
Albert Kong | Maintenance | Target 2 | Other | M20 Return to T2 Monolith + Vaccum Leak / T1-T2 Valve Re-inspection | We moved M20 back to the T2 monolith
and re did the connections for air + limit
switches + T2 profile monitor air. |
|
324
|
Monday, March 06, 2023, 16:58 |
Albert Kong | Repair | Target 2 | Cooling | M20 O-Ring Replacement and Valve Replacement Leak Check | We replaced tha O-ring on M20 at
T2 and brought the target station down to
vacuum, which allowed the target water pump |
|
319
|
Tuesday, February 21, 2023, 16:56 |
Albert Kong | Maintenance | Target 2 | Other | M20 BB moved to meson hall hot cell roof | The M20 beam blocker was moved from the
T2 monolith to the meson hall hot cell with
the remote handling flask (completed ~4pm). |
|
12
|
Friday, January 20, 2012, 10:23 |
Isaac Earle | Repair | Target 2 | Target | M20 BB Shaft Bearing Replaced | The replacement shaft bearing was machined
by Maico Dalla Valle and installed in the
beam blocker. Smooth operation of the |
|
162
|
Thursday, June 11, 2015, 16:59 |
Isaac Earle | Development | Other | Controls | Lab Test of New T1/T2 Level Sensors | The new T1/T2 level sensors (Omega LVCN414)
were tested in the RH HC lab today using
the Omega software on a laptop and positioning |
|
3
|
Friday, November 04, 2011, 13:36 |
Isaac Earle | Maintenance | Target 2 | Target | Kaon Target (Training) | Moved Kaon Target from storage
pit to remote handling hot cell using flask
as training exercise. Safety surveyor |
|
288
|
Thursday, April 14, 2022, 14:38 |
Adam Newsome | Other | Target 2 | Diagnostics | Issue with Protect Monitor SHV Cable | Diagnostics group (Shengli Liu) noted a
lack of connectivity between control panel
and T2 Protect Monitor via the high voltage |
|
178
|
Tuesday, October 06, 2015, 14:04 |
Isaac Earle | Other | Other | Controls | Instructions for loading display screen for T1/T2 | The following instructions were provided
by Graham Waters:
|
|
349
|
Friday, June 28, 2024, 15:44 |
Albert Kong | Other | Other | Transfer Flask | Inspection of Primary Target Transfer Flask |
Normal
0
|
|
344
|
Thursday, February 15, 2024, 12:38 |
Riley Sykes | Repair | Other | Hot Cell | Indium Extruder Hand Pump | Feb 1 2024
Hand Pump observed to be losing pressure
at full extension of cylinder, seals likely |
|
357
|
Friday, November 29, 2024, 11:57 |
Adam Newsome | Maintenance | Other | Hot Cell | Hot cell and warm cell maintenance tasks | The following maintenance tasks were completed
on 2024-11-29 by A. Newsome, A. Kong, A.
Tam, M. Dalla Valle: |
|
38
|
Thursday, June 07, 2012, 18:08 |
Isaac Earle | Repair | Target 1 | Target | Hot Cell Manipulator Broken Tape | A tape snapped on the west side manipulator
today while working on the T1-MK2 target
repair. The tape travels through to |
|
32
|
Monday, April 23, 2012, 09:55 |
Isaac Earle | Repair | Target 1 | Target | Hot Cell Manipulator Broken Cable | While working on the leak repair
of the T1-MK2 target in the hot cell on Friday
April 20th, a cable snapped on the slave |
|
296
|
Wednesday, July 06, 2022, 12:49 |
Adam Newsome | Repair | Other | Hot Cell | Hot Cell - Helium wand tubing broken | The tubing for the helium wand inside the
hot cell is broken and needs to be replaced.
More tubing has been ordered and the job |
|
295
|
Wednesday, July 06, 2022, 12:49 |
Matthew Gareau | Repair | Other | Other | Helium line damage, and hotcell window oil leaking | Today myself and Adam Newsome started the
leak detection steps for a target exchange
and notice that the Helium line was not connected/broken |
|