1170
|
Friday, March 18, 2016, 09:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall schedule for beam schedule 130 (Apr- Sep) | I would like to post the spreadsheet of
target hall schedule for beam schedule 130(Apr
to Sep) first. The MS project of TH schedule |
|
|
1171
|
Friday, March 18, 2016, 09:42 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 vacuum sysytem has been connected at TCS | TM2 vacuum system has been connected at
TCS. Started roughing pump. Everything is
good so far. |
|
|
1172
|
Friday, March 18, 2016, 11:43 |
chad fisher | South Hot-Cell | Standard Operation | | | SiC#32 dissection | SiC#32 has been open for inspection. |
|
|
1174
|
Monday, March 21, 2016, 10:25 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 Helium pressure Test Result in TCS and ITW | TM2 has been helium pressure tested in
ITW and TCS. They are both tested with 70psi
helium, each circuit for 3minutes. |
|
|
1175
|
Monday, March 21, 2016, 11:30 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 and TCS vacuum pumps are stopped | I stopped TM2 and TCS vacuum pumps. It
will be vented and disconnected this afternoon
for tomorrow moving. |
|
|
1176
|
Monday, March 21, 2016, 15:27 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 has been disconnected at TCS | TM2 vacuum system has been disconnected
at TCS. Venting is in process now. |
|
|
1179
|
Wednesday, March 23, 2016, 11:32 |
David Wang | South Hot-Cell | Repair | TM2 | | TM2 Helium spray leak check on GE and MSP lines at SHC | Chad and I did the helium spray
leak check on TM2 GE and MSP water lines
at SHC this morning. We confirmed the GE |
|
|
1180
|
Thursday, March 24, 2016, 13:15 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 and TCS vacuum system has been connected | TM1 and TCS vacuum system have been connected.
All turbo-pumps are started. The pumping
down is fine. |
|
|
1182
|
Tuesday, March 29, 2016, 08:38 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 water lines helium pressure check at TCS | TM1 water lines helium pressure check at
TCS is done. 70 psi helium was applied to
water circuits. Leak detector base leak rate |
|
|
1183
|
Wednesday, March 30, 2016, 08:40 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | update the schedule according to changes.See
attachment1, 2. |
|
|
1185
|
Wednesday, March 30, 2016, 15:49 |
David Wang | Assembly/Bench Test | Repair | TM2 | | TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo. | On each water circuit in side the service
cap, there are 4 soldering stems which two
of them are inside blue nylon insulator and |
7x |
|
1188
|
Friday, April 01, 2016, 14:41 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 and TCS vacuum system has been connected. TCS control page white out. | I can not start the TCS pumps due to control
page white out. Control group is working
on this issue. |
|
|
1189
|
Monday, April 04, 2016, 11:14 |
David Wang | Conditioning Station | Standard Operation | TM1 | | Helium pressure test on TM1 HS line at CS | New UCx target is installed on the module.
70psi helium,3 minutes. NO response on LD.
LD is pumped to bottom LR and LP during test. |
|
|
1192
|
Tuesday, April 05, 2016, 12:36 |
David Wang | ITW | Standard Operation | TM1 | | TM1 vacuum system has been connected in ITW. | All turbo -pumps are started. |
|
|
1193
|
Tuesday, April 05, 2016, 12:40 |
David Wang | ITE | Standard Operation | TM4 | | I stopped ITE turbo pumps this morning | The ITE and TM4 have been vented with Argon
. TM4 vacuum system is disconnected in ITE. |
|
|
1198
|
Friday, April 08, 2016, 07:10 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 vacuum has been connected in ITE. | All turbo pumps are started yesterday.
The pumping down is good over night. |
|
|
1200
|
Friday, April 08, 2016, 08:13 |
Anders Mjos | ITE/ITW Cooling | Maintenance | | | High Active Water Resistivity | The high active water resistivity took
a long time to recover after the upgrade
to the water cooling circuit. The system |
|
|
1201
|
Friday, April 08, 2016, 08:48 |
David Wang | ITW | Standard Operation | | | ITW water signal interlock check. | I did a ITW water signals interlock check
with ISAC opp. They are checked once a year
before first beam on. |
|
|
1202
|
Friday, April 08, 2016, 13:16 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | Update schedule weekly .see attachment
1,2 |
|
|
1203
|
Monday, April 11, 2016, 09:42 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Helium pressure test on TM4 HS line at CS with new Lp Ta target | 70 psi helium , 2 minutes. Base leak rate
0.0x E-9 atm.cc/sec. base pressure 0.0XE-4
torr. no response on LD.The line is good. |
|