ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  854   Thursday, March 05, 2015, 14:30 chad fisherSouth Hot-CellDevelopment  Dissection BoxBox for dissecting targets almost complete.
Should be done tomorrow.
 20150305_142144.jpg 
  855   Monday, March 09, 2015, 09:42 chad fisherSouth Hot-CellDevelopment  Hot Cell Table Swiping3 swipes of the south hot cell table were
taken from the target hall through the roof
hatch (2 standard, 1 alpha).
  
  859   Thursday, March 12, 2015, 13:04 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITE to ITW.5 shielding blocks have been transferred
from ITE to ITW for next week TM4 move.
  
  865   Friday, March 20, 2015, 13:37 chad fisherSouth Hot-CellDevelopment  TM2 Optics TrayFinal assembly and alignment of TM2 optics
tray continued today. Front section is "aligned".
 20150320_113132[2].jpg20150320_113018_1[1].jpg 
  866   Monday, March 23, 2015, 07:56 David WangITEStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th updateThis schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule.
 Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp 
  871   Wednesday, March 25, 2015, 10:37 chad fisherSouth Hot-CellDevelopment  TM2 optics tray buildTM2 optics tray build is continuing. Going
well. Hope to have assembly and alignment
finished by Friday.
 20150325_101718.jpg20150325_101735.jpg20150325_102024.jpg 
  877   Monday, March 30, 2015, 07:38 David WangITEStandard OperationTM4 TH Shut Down Activities Schedule Feb 23th- Apr 15th updateUpdated schedule this morning after last
Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02.
 Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp 
  879   Tuesday, March 31, 2015, 11:36 chad fisherSouth Hot-CellDevelopmentTM2 TM2 Optics Tray CompleteTM2 optics tray is complete.
Master alignment tray: 0 up/down,
0 left/right
 20150331_OPTICS_FRONT.jpg20150331_OPTICS_MIDDLE.jpg20150331_OPTICS_BACK.jpg 
  882   Wednesday, April 01, 2015, 13:08 David WangITEStandard OperationTM4 Replaced ITE tank to module 42X0.275 o-ringI replaced ITE tank to module 42 ID X 0.275
o-ring. The o-ring is changed once a year
before the first beam time. The flanges was
 001.JPG002.JPG004.JPG005.JPG006.JPG 
  884   Friday, April 10, 2015, 15:40 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.5 shielding  blocks have been transferred
to ITE. The ITE is configured to take proton
beam.
  
  885   Monday, April 13, 2015, 08:59 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - June 26 2015See attachments 1, 2 for target hall schedule
from 07 April to 26 June 2015. The first
TM1 move which is scheduled on 16 April 2015
 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp 
  886   Wednesday, April 15, 2015, 09:01 Anders MjosConditioning StationDevelopment  Archiver variables added by Controls 
 
 
  
  890   Monday, April 20, 2015, 07:27 David WangITEStandard OperationTM4 Target Hall Scheduled Activities April 07 - June 26 2015Weekly target hall schedule update.2015-04-20
weekly target hall schedule update
2015-04-27 attachments 3,4.
 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp 
  893   Tuesday, April 21, 2015, 13:01 Grant MinorITWDevelopmentTM2 TM2 MK4 Optics Tray - banana plug bore modification (on bench)The MK4 optics tray prepared for TM2 (as
per ITA6082) had an undersized bore for the
banana plug, making insertion of the plug
 ita6092_redlines_gminor_21apr2015.pdfTM2_Optics_Tray_Bore_Mod_21Apr2015_1.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_2.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_3.JPG 
  895   Wednesday, April 22, 2015, 11:05 David WangConditioning StationStandard OperationTM1 electrical check on TM1 at CS under vacuumI did an electrical check on TM1 at CS.
The resistance check:A-B 3.918m ohm, A-C
5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m
  
  897   Thursday, April 23, 2015, 12:56 Anders MjosConditioning StationMaintenanceTM1 IG1 Good Vacuum limit changedChanged by Dave Morris. 
New value is 1E-5 T (old value was
7.09E-5 T)
 IG1GoodVacuum.png 
  899   Monday, April 27, 2015, 16:12 Keith C NgSouth Hot-CellDevelopmentTM2 Ceramic Standoffs in TM2 source tray steerer assemblyOn drawing ITA6008 for the Encole 0.5"
ceramic standoffs there is a note to match
pairs of ceramics to within +/-0.001".
 IMG_3106.JPG 
  900   Monday, April 27, 2015, 17:09 Grant MinorITEDevelopmentTM2 TM2 - New Source Tray - Water Block Seal Groove Inspection ReportThe water blocks soldered to the TM2 cooling
lines (see Ref. Assy. ITA6144) were inspected.
See attached inspection reports and
 IMG_1859.JPGTM2_New_Source_Tray_Water_Block_Inspection_Results_24_April_2015.pdfTM2_water_block_inspect_24Apr2015.pdfTM2_New_Source_Tray_Water_Block_Inspection_Results_April_2015.xlsx 
  903   Tuesday, April 28, 2015, 11:09 Anders MjosITWMaintenance  Resistance measured of TGHT and TBHT lines to ITWThe new TBHT and TGHT power supplies were
brough up to high current; 350 A and 420
A respectively. The TGHT power supply was
 Resistance_from_Electrical_Room_to_Target_Station.xlsx 
  907   Friday, May 01, 2015, 08:27 chad fisherSouth Hot-CellRepairTM2 Containment Box RemovalContainment box has been removed in preparation
for wire replacement.
  