Message ID: 877     Entry time: Monday, March 30, 2015, 07:38
Author: David Wang 
Category: ITE 
Type: Standard Operation 
Module: TM4 
Target/Number:  
Subject: TH Shut Down Activities Schedule Feb 23th- Apr 15th update 

Updated schedule this morning after last Fridays ISAC facility support group meeting.

Updated schedule on 2015-April -02. See attachments 3,4. The scheduled all shut down jobs are done on time.The TM2 move to SHC will be delayed to May.There will be a new beam running time TH activities schedule (start from April 15) replacing this shut down schedule on next time  weekly update.

Attachment 1: Target_Hall_shut_down_activities.pdf  344 kB  | Show | Hide all
Attachment 2: Target_Hall_shut_down_activities.mpp  664 kB
Attachment 3: Target_Hall_shut_down_activities.pdf  342 kB  Uploaded Thursday, April 02, 2015, 10:32  | Show | Hide all
Attachment 4: Target_Hall_shut_down_activities.mpp  667 kB  Uploaded Thursday, April 02, 2015, 10:32