890
|
Monday, April 20, 2015, 07:27 |
David Wang | ITE | Standard Operation | TM4 | | Target Hall Scheduled Activities April 07 - June 26 2015 | Weekly target hall schedule update.2015-04-20
weekly target hall schedule update
2015-04-27 attachments 3,4. |
   |
893
|
Tuesday, April 21, 2015, 13:01 |
Grant Minor | ITW | Development | TM2 | | TM2 MK4 Optics Tray - banana plug bore modification (on bench) | The MK4 optics tray prepared for TM2 (as
per ITA6082) had an undersized bore for the
banana plug, making insertion of the plug |
   |
895
|
Wednesday, April 22, 2015, 11:05 |
David Wang | Conditioning Station | Standard Operation | TM1 | | electrical check on TM1 at CS under vacuum | I did an electrical check on TM1 at CS.
The resistance check:A-B 3.918m ohm, A-C
5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m |
|
897
|
Thursday, April 23, 2015, 12:56 |
Anders Mjos | Conditioning Station | Maintenance | TM1 | | IG1 Good Vacuum limit changed | Changed by Dave Morris.
New value is 1E-5 T (old value was
7.09E-5 T) |
|
899
|
Monday, April 27, 2015, 16:12 |
Keith C Ng | South Hot-Cell | Development | TM2 | | Ceramic Standoffs in TM2 source tray steerer assembly | On drawing ITA6008 for the Encole 0.5"
ceramic standoffs there is a note to match
pairs of ceramics to within +/-0.001". |
|
900
|
Monday, April 27, 2015, 17:09 |
Grant Minor | ITE | Development | TM2 | | TM2 - New Source Tray - Water Block Seal Groove Inspection Report | The water blocks soldered to the TM2 cooling
lines (see Ref. Assy. ITA6144) were inspected.
See attached inspection reports and |
   |
903
|
Tuesday, April 28, 2015, 11:09 |
Anders Mjos | ITW | Maintenance | | | Resistance measured of TGHT and TBHT lines to ITW | The new TBHT and TGHT power supplies were
brough up to high current; 350 A and 420
A respectively. The TGHT power supply was |
|
907
|
Friday, May 01, 2015, 08:27 |
chad fisher | South Hot-Cell | Repair | TM2 | | Containment Box Removal | Containment box has been removed in preparation
for wire replacement. |
|
908
|
Friday, May 01, 2015, 13:48 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - June 26 2015 update | Target Hall Scheduled Activities
April 07 - June 26 2015 update.
2015-05-01. All TH scheduled |
 |
909
|
Monday, May 04, 2015, 13:32 |
Anders Mjos | Conditioning Station | Maintenance | | | TK2 expansion tank topped up | Caled cyclotron ops to open P23 and confirmed
penthouse valve open.
Filled up TK2 to 21 in water leve. |
|
910
|
Tuesday, May 05, 2015, 10:57 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Wiring | Old wiring was removed yesterday, new wiring
run thru the vacuum chase. Old IMG gauge
removed today, new cable trays installed |
 |
913
|
Monday, May 11, 2015, 10:45 |
Anders Mjos | Conditioning Station | Maintenance | | | RGA electronics box installed | The communications chip has been
replaced. The electronics box has been grounded
(see attached pdf). |
|
914
|
Monday, May 11, 2015, 11:20 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - June 26 2015 | The schedule has some changes due to
new TM2 source tray coil cooling line leaking
at test stand. Now,It is re-scheduled in |
6x |
915
|
Wednesday, May 13, 2015, 13:55 |
chad fisher | South Hot-Cell | Repair | TM2 | | Shutter removal | TM2 has been successfully de-shuttered.
All went pretty much according to
plan except I had to remove one fastener |
 |
917
|
Tuesday, May 26, 2015, 11:49 |
Grant Minor | Assembly/Bench Test | Repair | TM2 | | TM2 New Source Tray - Braze & Solder Report - 22 May 2015 | Hello,
For reference, I have attached a list |
6x |
918
|
Tuesday, May 26, 2015, 14:34 |
chad fisher | South Hot-Cell | Repair | TM2 | | Shutter replacement | The shutter in TM2 was successfully replaced
today.
New lock washer and nut were installed |
|
919
|
Wednesday, May 27, 2015, 08:57 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | | Module moved | TM#2 with no source tray has been moved
from the south hot cell to the conditioning
station. |
|
923
|
Tuesday, June 02, 2015, 06:51 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | Target Hall Scheduled Activities April 07 - June 26 2015 | Target Hall schedule weekly update. All
jobs are finished on time so far. |
 |
928
|
Tuesday, June 02, 2015, 14:38 |
David Wang | Conditioning Station | Repair | TM4 | | replace broken TM4 IG1 | TM4 IG1 filament was broken during
last run at ITE. The broken filament
is replaced with a new one today when TM4 |
 |
930
|
Wednesday, June 03, 2015, 11:22 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall Scheduled Activities April 07 - July 21 2015 | I revised the Target Hall schedule to July
21 2015. It is the time new TM2 with ZrC
target started at ITW. |
   |