  1574   Thursday, June 29, 2017, 11:55 David WangConditioning StationRepair  TCS HV cable and feed through installationJohn Chow and I installed new TCS HV cable
and feed through with their mounting panel
back to TCS Faraday cage this Tuesday. ECO-4269
  
  1573   Thursday, June 29, 2017, 11:12 Anders MjosSouth Hot-CellStandard OperationTM4UC#20Post Irradiation Examination (PIE)The target was inspected by Chad and Anders.
Photos are available on DocuShare.
It was noticed that the target tube heater
  
  1572   Wednesday, June 28, 2017, 16:43 Anders MjosConditioning StationStandard OperationTM4Ta#52Conditioning Ta#52NEW HV cable for BIAS installed earlier
this week.
Wednesday, June 28, 2017, 16:42:
 Ta#52.docx 
  1571   Wednesday, June 28, 2017, 10:00 David WangConditioning StationStandard OperationTM4Ta#52TM2 has been connected at TCSI started TCS water system.   
  1570   Wednesday, June 28, 2017, 09:14 Travis CaveConditioning StationStandard OperationTM4Ta#52Electrical CheckResults of electrical check of TM#4 with
Ta#52 at the south hot cell and the conditioning
station under vacuum.
 TM4_Ta52_Elec_chk_SHC_CSvac.PDF 
  1569   Tuesday, June 27, 2017, 14:34 David WangConditioning StationStandard OperationTM4 TM4 vacuum has been connected at TCSTurbo -pumps are started . The vacuum looks
good so far.
  
  1568   Tuesday, June 27, 2017, 10:26 David WangSouth Hot-CellStandard OperationTM4Ta#52Leak check on TM4 HS line at SHCLD base LR:0.0Xe-9 atm.cc/sec. No leak
has been found during the check.  The
HS line will be helium pressurized at TCS
  
  1567   Tuesday, June 27, 2017, 09:14 Travis CaveConditioning StationStandard OperationTM4Ta#52Module move TM#4 with Ta#52 has been moved from
south hot cell to the conditioning station.
  
  1566   Monday, June 26, 2017, 11:47 chad fisherSouth Hot-CellStandard OperationTM4Ta#52UC#20 Removed Ta#52 installedUC#20 has been removed from TM4 and put
in a bucket back-filled with argon. Ta#52
has been installed onto TM4 with new fasteners.
  
  1565   Monday, June 26, 2017, 11:42 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Module move TM#4 with UC#20 has been moved from
the east target station to the south hot
cell. Also the shield plug was remotely installed
  
  1564   Friday, June 23, 2017, 17:28 Isaac EarleNorth Hot-CellDevelopment  NHC module flange and cameras installed The North Hot Cell module support
flange (IRH1152D) was installed on June 21,
2017 using 1/8" rubber sheet as a sealing
 IMG_0231.jpgIMG_0234.jpgIMG_0240.jpgIMG_0245.jpgIMG_0240.jpg 
  1563   Friday, June 23, 2017, 12:08 David WangCraneRepair  TH crane inspection and probem fixing by Gordon crane Gordon crane technician Peter came in today
and checked TH crane. Maico  and I were there
with him. What he found is that brake gap
  
  1562   Thursday, June 22, 2017, 11:10 chad fisherSouth Hot-CellMaintenance  In cell airlineThe in cell airline has preemptively been
replaced. The hose was, as far as I know
the original.
  
  1561   Monday, June 19, 2017, 07:29 David WangConditioning StationStandard OperationTM2 Update TH MS project schedule.Update TH MS project schedule. See attachment
1,2. 
 Target_Hall_shedule_132_Apr_to_Sep.pdfTarget_Hall_shedule_132_Apr_to_Sep.mpp 
  1560   Thursday, June 15, 2017, 11:29 Isaac EarleNorth Hot-CellDevelopment  NHC inlet ducting installedThe North Hot Cell inlet ducting assembly
was installed today in the target hall at
the north end of the NHC roof block.  A
 IMG_0217.jpgIMG_0218.jpgIMG_0219.jpgIMG_0214.jpg 
  1559   Tuesday, June 13, 2017, 13:41 David WangITWStandard OperationTM2 TM2 has been connected in ITW.Yasmine and I connected TM2 in ITW today.
the control page is set to febiad mode. Both
gas line in ITW are opened for febiad run.
  
  1558   Tuesday, June 13, 2017, 11:10 Grant MinorCraneMaintenance  ISAC THall Crane 100% / 125% Load Test Documentation - 2011The ISAC Target Hall Crane was load tested
and re-certified in January 2011 prior to
doing a near-capacity lift for the North
 ISAC_TH_Crane_Load_Test_Norelco_Sept_30_2011.pdfIMG_8722.JPGIMG_8752.JPGIMG_8735.JPGIMG_8745.JPG 
  1557   Tuesday, June 13, 2017, 09:57 Travis CaveITWStandard OperationTM2SiC#36module movedTM#2 with SiC#36 has been moved from the
conditioning station to the west target station.
  
  1556   Monday, June 12, 2017, 13:51 Travis CaveSpent Target VaultStandard Operation  Spent Target moveThe spent Ta#51 target has been moved from
the south hot cell to the spent target vault.
It was placed in pail#149 and put in spot
 Vault_Storage_June_12_2017.pdf 
  1555   Friday, June 09, 2017, 11:21 chad fisherNorth Hot-CellMaintenance  Model 'N' Slave Removal Through RoofIsaac and Chad disengaged the slave end
of the manipulator and performed a slave
removal through the slave removal roof hatch.
  