  RH-ISAC, Page 37 of 138  Not logged in ELOG logo
  ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  2655   Monday, August 12, 2024, 15:55 Aaron TamSouth Hot-CellStandard OperationTM2Ta#67 LP-SISTarget Loading Ta#67 Target loaded onto TM2
Leak check passed
Electrical test passed after loosening
  
  2656   Tuesday, August 13, 2024, 08:39 Frank SongSouth Hot-CellStandard OperationTM2Ta#67electrical check/leak check TM2 with new target Ta#67 had been
electric/leak checked before moving to ITE.
See attachment pls.
 TM2_with_Ta@67_electric_and_leak_check_on_SHC.pdf 
  2657   Tuesday, August 13, 2024, 14:18 Frank SongITEStandard OperationTM2Ta#67Module Connection TM2 with new target Ta#67 was connected
in ITE, all TP are running at their full
speed now.
 TM2_with_Ta#67_connection_in_ITE_20240813.pdf 
  2666   Monday, August 19, 2024, 15:29 Frank SongITW/ITEStandard OperationTM2Ta#67shielding blocks transfer 5 shielding blocks have been transferred
from ITW to ITE, MAA has been secured after
moving.
  
  2695   Tuesday, October 01, 2024, 09:16 Frank SongITEStandard OperationTM2Ta#67module disconnection TM2 with spent target Ta#67 was disconnected
in ITE. see attachment pls.
 TM2_with_spent_target_Ta#67_disconnection_in_ITE_2024-10-01.pdf 
  2697   Tuesday, October 01, 2024, 12:40 Aaron TamSouth Hot-CellStandard OperationTM2Ta#67Target Ta#67 Removed from TM2  October 1, 2024 - Aaron Tam 
Ta#67 LP-SIS removed from TM2
Ta#67 is sitting in SHC awaiting
 9x 
  2702   Thursday, October 10, 2024, 10:24 Aaron TamSouth Hot-CellStandard OperationTM2Ta#67Ta#67 PIE  Post Irradiation Examination
October 9, 2024 - Aaron Tam w/
Chad Fisher, Aurelia Laxdal, and Lucas Backes 
 35x 
  2492   Wednesday, October 04, 2023, 10:41 Frank SongSouth Hot-CellStandard OperationTM2Ta#66electrical check/leak check TM2 with new target Ta#66 had an
electrical check and leak check on SHC. 
 TM2_with_Ta#66_electical_and_leak_check_in_SHC_2023-10-04.pdf 
  2493   Thursday, October 05, 2023, 13:50 Frank SongITWStandard OperationTM2Ta#66Module Connection TM2 with new target Ta#66 was connected
in ITW. 
 TM2_with_Ta#66_connection_in_ITW_2023-10-04.pdf 
  2514   Wednesday, January 03, 2024, 13:55 David WangITWStandard OperationTM2Ta#66Disconnect TM2 in ITW.TM2 has been disconnected in ITW. All water
lines are nitrogen purged. Filled 60 psi
argon to all Tm2 water lines for module storage
 TM2_with_Ta#66_was_disconnected_in_ITW_2024-01-02.pdf 
  2515   Wednesday, January 03, 2024, 14:03 David WangITWStandard OperationTM2Ta#66ITW primary and secondary vacuum vessel leak check and TM2 water lines helium pressure test. ITW primary and secondary vacuum vessel
leak check and TM2 water lines helium pressure
test are done today. No major concern. see
 ITW_2024_shut_down_leak_check.pdf 
  2518   Wednesday, January 10, 2024, 11:24 Travis CaveSpent Target VaultStandard Operation Ta#66Spent Target Move The spent Ta#66 was moved from the
south hot cell to the spent target vault,
it was placed in pail#285 and placed in spot
 Target_Index_2023-01-10.pdf 
  2523   Friday, January 12, 2024, 11:25 David WangSouth Hot-CellStandard OperationTM2Ta#66Ta#66 post operation electrical check at SHCTa#66 post operation electrical check was
done at SHC this Monday. See attachment.
 TM2_Ta66_post__oeration_electrical_check.pdf 
  2524   Wednesday, January 17, 2024, 20:09 Carla BabcockSouth Hot-CellStandard Operation Ta#66Ta#66 post irradiation inspectionOn Jan. 9 we did the PIE on Ta#66. Opened
the heat shield and removed the EE. The inside
of the heat shield was very black with lots
 20240109_100926(1).jpg20240109_101053.jpg20240109_102409.jpg 
  2582   Friday, May 03, 2024, 12:20 Travis CaveSpent Target VaultStandard Operation Ta#66Target repacked The Ta#66 target was repacked after
the parasitic target was removed it was place
in a new pail (#290) and place back in spot
 Target_Index_2024-05-03.pdf 
  2485   Tuesday, August 29, 2023, 14:32 Frank SongNorth Hot-CellStandard OperationTM4Ta#65electrical check/leak check TM4 with new target Ta#65 has been
E/L checked at NHCPost.
 TM4_electric_and_leak_check_after_Ta#65_installed_2023-08-29.pdf 
  2486   Tuesday, August 29, 2023, 14:32 Frank SongNorth Hot-CellStandard OperationTM4Ta#65electrical check/leak check TM4 with new target Ta#65 has been
E/L checked at NHCPost.
 TM4_electric_and_leak_check_after_Ta#65_installed_2023-08-29.pdf 
  2488   Wednesday, September 06, 2023, 08:07 Frank SongITEStandard OperationTM4Ta#65Module Connection TM4 was connected in ITE with new
target Ta#65 installed. see attachment in
detail.
 TM4_with_Ta#65_connection_in_ITE_2023-09-05.pdf 
  2498   Tuesday, November 07, 2023, 13:42 Frank SongSouth Hot-CellStandard OperationTM4Ta#65electrical check with the spent targetTM4 with spent target Ta#65 was electrical
checked right after being moved to SHC. 
 TM4_with_Spent_Target_Ta#65_electrical_check_on_SHC_2023-11-07.pdf 
  2499   Tuesday, November 07, 2023, 13:55 Frank SongITEStandard OperationTM4Ta#65module disconnectionTM4 with spent target Ta#65 was disconnected
in ITE and moved to SHC.
 TM4_with_Spent_Target_Ta#65_disconnection_in_ITE_2023-11-07.pdf 