52
|
Wednesday, November 16, 2011, 07:44 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | TaC#1 | TaC#1 Removal and inspection | November 15, 2011 removed TaC#1 from TM1
and inspected TM1 for any obivous signs of
trouble (Problems with EE at end of run). |
|
53
|
Wednesday, November 16, 2011, 07:46 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | TaC#1 | Inspection of TaC#1 | Inspection of TaC#1 showed that the oven
was indeed broken on the A+ (left oven leg)
side of the central block. |
|
57
|
Friday, November 18, 2011, 09:56 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UCx#3 | UCx#3 Installation | UCx#3 has been installed on TM1.
Leak check also complete.
Base Leak Rate 0.0 x 10-9 |
|
74
|
Monday, March 12, 2012, 10:03 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UC#3 | UC#3 Removal | UC#3 was removed from TM1 this morning.
Upon removing the oven heater bolts BOTH
legs fell demonstrating that both sides of |
|
76
|
Tuesday, March 13, 2012, 09:42 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UCx#3 | UCx#3 Autopsy | An autopsy was performed on UCx#3 yesterday
afternoon. This autopsy followed the plan
written by Anders. Indeed, both sides of |
|
77
|
Tuesday, March 13, 2012, 09:43 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UCx#3 | UCx#3 to spent vault | UCx#3 was packaged into a spent can, double
bagged and the bag and cans filled with argon
as much as possible. Lid was attached and |
|
86
|
Tuesday, April 17, 2012, 10:15 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Nb#6 | Target inserted into south hot cell | Nb#6 has been inserted into the south hot
cell in preparation for ionstallation onto
TM1. During the pre-insertion inspection |
|
101
|
Tuesday, May 15, 2012, 12:14 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | SiC#26 | SiC#26 removal TM4 degredation | SiC#26 was removed from target module #4
this morning. Target shows the now standard
arc marks on the 9 pin connector housing...pictures |
19x |
105
|
Friday, May 18, 2012, 08:17 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | SiC#27 | SiC#27 Installed | SiC#27 has been installed onto TM4. Fit
was very good. All electrical connections
double checked with mirror. |
|
118
|
Wednesday, June 06, 2012, 13:36 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#38 | Target Change Nb#6 - Ta#38 | Nb#6 was removed from TM1...it looked very
clean.
Ta#38 was installed onto TM1...fit |
|
131
|
Thursday, June 21, 2012, 14:30 |
chad fisher | South Hot-Cell | Repair | TM3 | N/A | TM3 Refurbishment Start | Started refurb of TM3.
Planned activities:
Inspection |
|
132
|
Thursday, June 21, 2012, 14:33 |
chad fisher | South Hot-Cell | Repair | TM3 | N/A | Pictures TM3 June 21st | Here are the pictures from today...there
is video too but it is not uploaded yet. |
8x |
133
|
Monday, June 25, 2012, 07:53 |
chad fisher | South Hot-Cell | Repair | TM3 | N/A | TM3 Refurb. Work | On Friday, June 22 the following work was
carried out.
Further inspection of |
|
153
|
Tuesday, July 31, 2012, 12:24 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | UCx#4 | UCx#4 Installed | Starting at 11:00 am and finishing at 12:10
Ucx#4 previous target was removed and UCx#4
installed and leak checked on TM1. |
|
166
|
Friday, August 31, 2012, 12:10 |
chad fisher | South Hot-Cell | Maintenance | | | Hot Cell Maitenance | Entered south hot cell Wednesday and replaced
the pre-filter air filter as well as the
front two light bulbs. Also removed two bags |
|
170
|
Wednesday, September 05, 2012, 14:36 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | NiO #1 | UOx removal NiO installation | UOx was removed from TM4 yesterday and
NiO#1 installed.
Video was taken. |
|
182
|
Tuesday, September 18, 2012, 13:47 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Nb#7 | Nb #7 install Cover Baseline | Nb #7 was installed and tested today.
Inside face of the containment box
cover was cleaned with methanol and a baseline |
|
194
|
Tuesday, October 09, 2012, 13:44 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UCx#5 | NiO#1 removal UCx#5 installation | NiO#1 was removed this morning.
UCx#5 was inserted into the hot cell
around 1 pm, installed and leak checked and |
|
203
|
Tuesday, November 06, 2012, 11:34 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | | Nb#7 Removal | Attached are pre-removal pictures of NB#7
and the inside face of the containment box
cover before cleaning. |
|
205
|
Tuesday, November 06, 2012, 14:00 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | TiC#3 | TiC#3 Installed | TiC#3 sucessfully installed and ready for
leak and electrical check. |
|