1039
|
Monday, August 17, 2015, 10:44 |
Anders Mjos | Conditioning Station | Development | TM2 | LP-FEBIAD Test Target (empty) | Conditioning TM2 Source Tray with FEBIAD test target | TGHT, TBHT, ANODE and COIL power tested
(some amps/volts)
Monday, August 17, 2015, 10:43: BIAS/EL/EE |
|
1111
|
Wednesday, October 21, 2015, 11:58 |
Anders Mjos | South Hot-Cell | Development | TM2 | ZrC#7 | Extraction Electrode inspection | The failed extraction electrode was inspected
in the hot cell this morning by Anders and
Chad. The following electrical measurements |
|
1117
|
Friday, November 06, 2015, 14:36 |
Anders Mjos | Conditioning Station | Development | TM3 | FEBIAD test target | Testing TM3 | Friday, November 06, 2015, 14:35: Roughing
Turbos was started around 4pm. Later
it was found that the manual valve for the |
|
1121
|
Tuesday, November 10, 2015, 16:53 |
Anders Mjos | Conditioning Station | Development | TM3 | FEBIAD test target | Testing TM3 | Tuesday, November 10, 2015, 16:53: Roughing
Tuesday, November 10, 2015, 18:24:
TP1S started |
|
1221
|
Wednesday, May 04, 2016, 11:14 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Scope Decision | A meeting was held on May 4, 2016 to determine
the scope of the North Hot Cell project.
The following was agreed upon by those |
|
1294
|
Friday, July 29, 2016, 14:27 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Measurements & Cleanup | The North
Hot Cell was accessed today via the Ante |
|
1307
|
Friday, August 05, 2016, 14:13 |
Isaac Earle | North Hot-Cell | Development | | | Preparations for NHC Ventilation Test | A hole was drilled in the NHC exhaust duct
in the east end of the target hall above
the hatch to the Ante Room. This will |
|
1315
|
Wednesday, August 10, 2016, 14:38 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Ventilation Test Results | Testing was performed on August 9th on
the ISAC nuclear ventilation system to determine
if the existing ventilation system can achieve |
|
1318
|
Friday, August 12, 2016, 10:59 |
Anders Mjos | Conditioning Station | Development | TM3 | | HV Test with Service Chase Panel removed | Water cooling is performed manually with
CP1. RGA is ON since yesterday. EE is not
connected and in conditioning mode. |
|
1345
|
Wednesday, September 07, 2016, 11:39 |
Isaac Earle | North Hot-Cell | Development | | | NHC North / South Wall Gap Measurements | Measurements were taken today of
the NHC north/south wall gap at the location
where the NHC/TCS partition wall will be |
|
1353
|
Thursday, September 15, 2016, 11:05 |
Isaac Earle | North Hot-Cell | Development | | | NHC / SHC feedthrough panel removed | The sheet metal panel covering the NHC/SHC
feedthrough port was removed today using
a slide-hammer to pull out the concrete anchors |
|
1357
|
Tuesday, September 20, 2016, 11:48 |
David Wang | Assembly/Bench Test | Development | | | A silo and blue steel frame are removed out of TH | A silo and blue steel frame are removed
out of TH this morning. They are transferred
through ante room, and moved to experimental |
|
1395
|
Tuesday, November 08, 2016, 14:04 |
Isaac Earle | North Hot-Cell | Development | | | Interference check with TCS turbo pump and proposed NHC duct routing | David Wang and I accessed the NHC today
to check if the proposed duct routing (IRH1618)
will interfere with servicing or replacement |
|
1416
|
Friday, December 09, 2016, 14:58 |
Isaac Earle | North Hot-Cell | Development | | | NHC service area floor and top of roof block painted | The concrete floor in the North Hot
Cell service area and the top of the NHC
roof block in the target hall have been painted |
|
1421
|
Tuesday, January 17, 2017, 13:45 |
Isaac Earle | North Hot-Cell | Development | | | NHC ducting installed | The new ducting section connecting
the existing duct termination in the TCS
space to the NHC partition wall has been |
|
1423
|
Wednesday, January 18, 2017, 11:53 |
Isaac Earle | North Hot-Cell | Development | | | NHC partition wall installation complete | The final panels of the partition
wall were installed today as per drawing
IRH1609. Sealing, finishing, and painting |
|
1435
|
Tuesday, February 07, 2017, 15:57 |
Isaac Earle | North Hot-Cell | Development | | | Ventilation Ducting Gasket Installed | Lead gasket IRH1633 was installed
today according to assembly drawing IRH1618
Rev B. |
|
1436
|
Thursday, February 09, 2017, 09:24 |
David Wang | Conditioning Station | Development | | | Target module window cooling lines at TCS. | Target module window cooling lines
at TCS has been modified to use spare 2 channel
in TCS: WFB1. The old cooling lines used |
|
1437
|
Thursday, February 09, 2017, 14:07 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Shielding Window Gaskets Changed | The North Hot Cell shielding window
gaskets have been changed and the window
has been filled with new oil. Although |
23x |
1440
|
Friday, February 24, 2017, 15:12 |
Isaac Earle | North Hot-Cell | Development | | | NHC interior walls/floor/ceiling re-finished, sealed, and painted | The North Hot Cell interior walls, floor,
and ceiling were re-finished, sealed, and
painted by Omni Coating from Feb 6 - 17 under |
8x |