  ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  1758   Wednesday, July 25, 2018, 13:21 Anders MjosITWRepairTM2Nb#8Leak check of ITWITW Entrance Module was leak checked yesterday
with the support of Vacuum Group (Dimo &
Edi). The leak detector was connected to
 Entrance_Module_Leak_2018-07-25.docx 
  1763   Wednesday, August 01, 2018, 15:12 Anders MjosSouth Hot-CellStandard OperationTM2UC#23Target mounted - water leak on HS lineThe heat shield water lines were not purged
ahead of target exchange  in the hot cell.
This resulted in water leaking onto the new
 20180801_180130904_iOS.jpg 
  1790   Monday, September 24, 2018, 10:21 Anders MjosSouth Hot-CellStandard OperationTM2UC#23Post Irradiation Examination (PIE)UC#23 experienced short between target
and heat shield as it was heated during operation.
The inspection of the target after irradiation
 20180924_161322929_iOS.jpg 
  1817   Monday, November 05, 2018, 14:27 Anders MjosConditioning StationStandard OperationTM2UC#25Target module disconnectedFrank and Anders disconnected the water
and electrical connections this afternoon
after the target was conditioned over the
  
  1819   Wednesday, November 07, 2018, 09:50 Anders MjosITWStandard OperationTM2UC#25TM2 connected in ITWTM2 was connected yesterday by Frank and
Anders. The West side panel with IG1S on
Exit Module 2 was replaced with a new SST
  
  1821   Wednesday, November 14, 2018, 16:10 Anders MjosITWRepairTM2UC#25ITW:FC5 safety signal troubleshootingMeasured resistance on safety limit switches
for FC5 on Exit Module 2. Determined that
the in connected signal did not work (shows
 2018-11-13_FC5.pdf 
  1822   Thursday, November 22, 2018, 08:52 Anders MjosITEStandard OperationTM4Ta#57Closed ITE dump waterPaddle wheel signal was tripping proton
beam in ITW. Valved off ITE dump to divert
flow to ITW. Field around valve was about
  
  1823   Thursday, November 22, 2018, 08:53 Anders MjosITWStandard OperationTM2UC#25Block moveFrank and Anders moved blocks from ITE
to ITW yesterday
  
  1824   Thursday, November 22, 2018, 08:55 Anders MjosITWRepairTM2UC#25ITW:FC5 safety signal limit switch installedYesterday Diagnostics group installed a
temporary external limit switch to provide
the in signal to the safety system.
 FC5_limit_switch.jpg 
  1840   Tuesday, December 11, 2018, 14:35 Anders MjosITEStandard OperationTM4UC#26Block moveBlocks were moved from ITW to ITE by Frank
and David. ITE water flow to dump was re-opened
(ITW remains open). A dose badge was installed
  
  1842   Wednesday, December 19, 2018, 14:41 Anders MjosConditioning StationStandard Operation No targetInstalled Shield Block on TCSFrank and Anders installed lid on TCS and
started vacuum system yesterday. To run over
the Holidays. Retrieved dose badge from operational
  
  1843   Wednesday, January 02, 2019, 10:26 Anders MjosConditioning StationStandard Operation  Restarrted TP1SFound pumps off after the holidays. Restarted
roughing pump and TP1S
  
  1878   Friday, March 01, 2019, 08:42 Anders MjosConditioning StationStandard OperationTM2 Conditioning TM2 without source trayBIAS and EZL connected. No water flowing
into the module (water looped on top of module)
Friday, March 01, 2019, 08:20: 10kV
 TM2_BIAS_current_vs_voltage_2019-03.xlsxTM2_HV_Conditioning_2019-03-01.docx 
  1902   Thursday, March 28, 2019, 12:48 Anders MjosConditioning StationRepairTM2dummy febiad test targetTM2 new source tray helium pressure test at TCS.


   
        
            
  
  1996   Tuesday, October 01, 2019, 16:30 Anders MjosConditioning StationStandard OperationTM2Ta#58Conditioning of Ta#58Tuesday, October 01, 2019, 15:15: Started
roughing.
Tuesday, October 01, 2019, 16:30:
  
  2019   Thursday, October 31, 2019, 08:49 Anders MjosConditioning StationRepair  Water leak on non-active cooling water circuitYesterday a leak was discovered in the
ISAC-I experimental hall. The leak appears
to be at the connection between the evaporator
  
  2026   Thursday, November 07, 2019, 10:39 Anders MjosConditioning StationStandard OperationTM2SiC#38Conditioing SiC#38Thursday, November 07, 2019, 10:35: Tested
source to 30 A on TGHT, TBHT and COIL. ANODE
at 100 V.
 SiC#38_ANODE_bias_2019-11-07.PNG 
  2073   Thursday, February 27, 2020, 16:08 Anders MjosNorth Hot-CellMaintenance  Hot Cell EntryChad entered the NHC today to tighten set-screws
on both slave side manipulators and re-align
the West side slave. Work took place using
 NHC_2020-02-27.pdf 
  2090   Thursday, March 19, 2020, 15:48 Anders MjosConditioning StationMaintenance  Filter replacement in water system March 5thFilters were replaced by Curtis von Cube
on March 5th. See work permit for details
I2020-03-05-5
  
  2140   Thursday, August 27, 2020, 09:42 Anders MjosConditioning StationMaintenanceTM2Ta#60Refilled TK2Refilled TCS:TK2 from 10 in to 22 in using
the newly installed valve.
  