High active water system is refilled. Air are drained out of system before pump to be started. Following sequence are used to bring the whole system back to operation:
1. close ITE , open ITW. Switch on the pump. Only 2A beam line related 5 water circuits are in loop in ITW. Switch off pump when system pressure is stable above 100 psi.
2. Close ITW, open ITE. Switch on the pump. Only 2A beam line related 5 water circuits are in loop in ITE. Switch off pump when system pressure is stable above 100psi.
3. Open ITW, Open ITE. Switch on pump. both ITW and ITE beam line related water circuits are in loop. Switch off pump when system pressure is stable above 100psi.
4. Close ITE open ITW. Bring ITW target module water circuits back to loop by connecting bypass fittings on to circuits. Only bring one circuit back to system at first. Switch on pump. Wait for system pressure stabilized. Then Close ITW. bring next circuit back to system. Open ITW . wait for pressure stabilized. repeat the process until all water circuit and connected with bypass fittings in ITW.
5. Check possible leak on valves, fittings, and flow sensors in ITW pit.
6. Go to electrical room, check all ITW water signal status.
7. Close ITW, Open ITE. Repeat same procedure as step 4 on ITE target module water circuits.
8. Check possible leak on valves, fittings and flow sensors in ITE pit.
9. Go to electrical room, check all ITE water signal status.
10. Open ITW. At this stage, full ITE station and half of ITW station water circuits are in operation. Check possible leak on pumps, valves, fittings, gauges on water station at TH west end.
11. Keep system in operation. Watch on - tank level , system pressure, and conductivity on resin circuit and whole system. |