ID Date Author Category Type Moduledown Target/Number Subject
  1646   Wednesday, October 18, 2017, 14:54 Anders MjosAssembly/Bench TestStandard Operation  Source tray assembly electrical check

Source tray meggered today by Anders and Keith

GND - MSP OL @ 1000V
MSP - EE OL @ 1000V
EE - GND OL @ 1000V
4x Steerers - GND OL @ 500V

Steerer continuity verified from socket to steerer plates
(looking in the direction of the RIB, labeled top to bottom on sockets)

1 - Top
2 - Left
3 - Right
4 - Bottom

Attachment 1: Steerer_Connections_2017-10-18.pdf
Steerer_Connections_2017-10-18.pdf
  1648   Thursday, October 19, 2017, 14:20 Anders MjosAssembly/Bench TestStandard Operation  Source tray inspection

 Two minor chips in the main 60 kV insulators on the source tray was inspected today by Anders, Tom and Aurelia. The chips are small enough that they should not be a problem. See photos for details.

Attachment 1: Left_Insulator.jpg
Left_Insulator.jpg
Attachment 2: Right_Insulator.jpg
Right_Insulator.jpg
  1650   Monday, October 23, 2017, 13:38 Travis CaveSpent Target VaultStandard Operation UC#21Spent Target move

The spent UC#21 has been moved from the south hot cell to the spent target vault. See attached for details

Attachment 1: Vault_Storage_October_23_2017.pdf
Vault_Storage_October_23_2017.pdf Vault_Storage_October_23_2017.pdf Vault_Storage_October_23_2017.pdf Vault_Storage_October_23_2017.pdf
  1653   Thursday, October 26, 2017, 13:20 Travis CaveSpent Target VaultStandard Operation SiC#30,ZrC#7,Ta#44,TiC#4, and Ta#41Targets moved to mini storage

SiC#30,ZrC#7,Ta#44,TiC#4, and Ta#41 have been moved from the spent target storage to the mini storage. See attached PDF for details of the orders of the pails in the mini vault.

Attachment 1: Mini_Vault_Storage_October_26_2017.pdf
Mini_Vault_Storage_October_26_2017.pdf Mini_Vault_Storage_October_26_2017.pdf Mini_Vault_Storage_October_26_2017.pdf Mini_Vault_Storage_October_26_2017.pdf
  1655   Thursday, November 09, 2017, 08:46 Anders MjosConditioning StationRepair  Communication fiber replaced for HV PLC

 After extensive troubleshooting the communication fiber was found to be damaged and has been replaced by Gelo.

  1660   Monday, November 13, 2017, 13:50 Travis CaveSpent Target VaultStandard Operation Ta#54Spent Target Move

 The spent Ta#54 target has been moved from the south hot cell to the spent target vault. It was placed in Pail #157 and put in spot #5B of the vault.

Attachment 1: Target_Index_2017-11-13.pdf
Target_Index_2017-11-13.pdf
  1663   Wednesday, November 15, 2017, 08:55 David WangConditioning StationStandard Operation  Install shield plug onto TCS and pumping down TCS.

Shielding plug is installed onto TCS. TCS is being pumped down to keep it under vacuum for the rest of the year.

  1664   Friday, December 01, 2017, 16:42 Isaac EarleNorth Hot-CellRepair  NHC manipulator service visit

Pete Dudley, manipulator service technician from CRL, was on site from Nov 27-30 to service the NHC Model N manipulators (See E-log entry #1578 for background).

He began by evaluating the motion selection and electric drive of the manipulator installed on the blue service cart.  This manipulator had chip A0166R01, same as the right side manipulator which had the failure described in E-Log 1578.  Pete noted that the arm was very slow to switch between the different drive directions, and had a significant lag between when the switch for motion was released, and when the motor actually stopped driving.  This was the case with all directions.  Because of this, he suspected that the right arm Z tape broke because when the manipulator reached the switch at the end of travel, the motor did not stop quickly enough causing over tension and snapping the tape.  A newer chip, A0166R04, was removed from the spare master arm (received Spring 2017), and installed into the master arm on the blue cart.  The test was repeated, and this time the motion selection and drive worked as expected.  The situation which previously caused failure was evaluated:  slave end fully extended in Z, master end fully collapsed in Z.  In this configuration the arm was moved back and forth in the Y direction.  No tape failure occurred, and the Z motion tape tension seemed normal.  Y motion drive was attempted, and was not possible, as expected.  This test was repeated in the opposite configuration (slave end fully collapsed, master end fully extended) with the same results.  Full drive speed was used for all tests.

The right side slave arm (with broken Z tape) was then removed and transported to the HCSA.  Using the bench mounted locking plate, the broken Z tape was replaced, and a full inspection and cable/tape tensioning was performed.  Pete accidentally broke the Z tape on the right side master arm while investigating the failure, which was also replaced.

The other two slave arms were also both inspected, tensioned, and tested in the same way.  Then all three were each in turn installed to the master arm #9348 on the blue manipulator transport cart where all mechanical motions and drives were tested (except X, because mounted on cart), the failure situation described above was also tested for all three slave arms.

The left side manipulator was then installed into the wall.  It was necessary to remove the lead sheilding on the thru-tube and machine it down approximtaely 0.070" in order for the arm to fit into the wall tube.  After installation, the manipulator motions and drives were tested again including the X motion, and the failure scenario situation was also re-tested.  Chad used the left side manipulator to remove and re-install the pre-filter mounted on the west side partition wall.  He also confirmed that he could reach the east wall electrical outlets and the outlets, gas fittings in front of the window.

The right side slave arm was adjusted so that the Y position was moved 1/2 turn of the shaft drive towards the window (this is the maximum adjustment possible before it hits a hard stop).  This was done so that the operator can more easily reach the outlets and air/gas connections inside the cell in front of the window.  Because both the master and slave ends protrude further out from the wall compared to the E-HD manipulators for the SHC, this modification makes the NHC manipulators feel a bit more like the SHC manipualtors for the operator.  After the adjustment, the right side slave arm was installed.  The left side slave arm was removed, adjusted the same as the right side, then reinstalled.  The spare slave arm was also adjusted in the same way.

The right side manipulator was evaluated through all mechanical motions.  We attempted to remove the A0166R04 chip from the left side, and install in the right in order to try the motion drives, however the pins had been damaged from the previous removal/install, and eventually one pin broke so this was abandoned.  CRL will ship us at least three new A0166R04 chips which should arrive in 2-3 weeks.

Upon completion of the work the location of the different arms is as follows:  Right side master #9351, Left side master #9348, Spare master #9763, Right side slave #9349, Left side slave #9764, Spare slave #9352

1512175169704.jpg

 

1512175181553.jpg

  1665   Wednesday, December 06, 2017, 09:33 Anders MjosConditioning StationMaintenance  Running chiller for maintenance tech

 Dakine is on site to do maintenance on the chiller. The tech requested the chiller to operate.

  1667   Tuesday, December 19, 2017, 10:40 Don JacksonCraneMaintenance  Crane Power during winter break

 The power to the crane and controls were turned off using the power switch in the Crane Control room.  The main disconnect switch in the target hall was not touched.

All site power will be off for a period of time during the Christmas break and this removes the crane from any issues when power is restored.

  1668   Tuesday, December 19, 2017, 10:41 Anders MjosCraneMaintenance  Crane powered down

The target hall crane has been powered down by Don today in preparation for the power shutdown over the Holidays.

  1669   Thursday, December 21, 2017, 15:11 Anders MjosConditioning StationMaintenance  Powered down devices

Powered down mechanical pumps in ISAC-I Experimental hall, vacuum gauge and turbo pump controllers in ISAC-I B2 North Hot Cell service area

  1671   Tuesday, January 02, 2018, 10:46 David WangITE/ITW CoolingStandard Operation  Start High active water system.

High active water system  was  checked before restart. A small water leak on resin can supply valve was found. It is fixed. MP1 and MP2 were started and checked separately. System pressure and flow rate are normal.MP1 is in operation now. 

  1673   Tuesday, January 02, 2018, 14:47 Anders MjosConditioning StationStandard Operation  Pumping on secondary vacuum

Tuesday, January 02, 2018, 14:45: TP1S started

  1674   Tuesday, January 02, 2018, 15:17 Anders MjosConditioning StationMaintenance  Tested chiller

Tested all 3 compressors and MP2

  1675   Thursday, January 04, 2018, 13:28 Anders MjosConditioning StationMaintenance  Troubleshooting IG1S

TCS:IG1S is reporting vacuum levels that seem to be too low (1E-10 to 1E-8 Torr). The gauge was connected to the controller for IG1, which showed the same value. A degas was performed for ~5 min.

  1676   Tuesday, January 16, 2018, 06:50 David WangITE/ITW CoolingStandard Operation  Field measurement on old resin tank in silo

The old resin tank has been stored in silo since last year March.  Without crane the tank up, We use the pole monitor measured the field around the bottom of the tank in silo. The average contact field on the bottom is about 4.0msv/hr. @0.5meter , the field is about  900usv/hr. It is still too hot to remove it.

  1678   Wednesday, January 17, 2018, 06:51 David WangConditioning StationStandard Operation  Stop TCS vacuum pumps

I stopped TCS vacuum pumps for coming TM3 move.

  1684   Wednesday, January 31, 2018, 10:32 David WangCraneStandard Operation  Target Hall crane annual inspection.

Gordon crane technician Tom finished annual TH crane inspection today. Everything is normal. The main hoist brake gaps are checked on both side. They are good still.

  1689   Wednesday, February 28, 2018, 14:47 David WangITEStandard Operation  leak check ITE primary and secondary vacuum vessel.

2018-02-27: Anders and I finished leak check on ITE primary and second vacuum vessel seals. LD connected to ITE BV2 valves between. LD, Base Leak rate 1.2 xE-9atm.cc/sec, base pressure 0.0XE-4torr. There is a leak has been found on TM4 service cap KF25 blank off. The o-ring on the blank off will be changed later. It is an easy fix . Other seals are good. The big T tank seal on secondary vessel is leak checked as well. It is still fine.  Helium pressure on TM4 water lines will be fulfilled at TCS to save dose.

2018-02-28 Leak checked ITW today, LD connected to ITW BV2 valves between LD base LR0.0XE-9 atm.cc/sec. base pressure 0.0Xe-4torr. There is leak has been found on exit module 1 service cap  on  topcover plate   o-ring. The leak is located on the south side of east edge on exit 1. This is the side module 2 is close beside. The leak rate is up to middle of E-8atm.cc/sec  range with 1-2 second helium spray. The leak and leak position are double checked and confirmed.  To completely fix this leak, the o-ring for top cover plate need to be replaced on service cap.It will be a major shut down job.  The  leak is close to ITW TP3 so it is less affect on beam line elevation vacuum.  Vacuum group experts will be consulted to see if we could leave it to next year shutdown.  Other seals are good including big T-tank seal on secondary vessel. TM2 source tray will be replaced this yea rso no helium pressure test on water lines is needed at this moment.