2690
|
Monday, September 23, 2024, 16:06 |
Aaron Tam | South Hot-Cell | Repair | TM3 | | Insulator Addition to Water block | September 23, 2024 - C. Fisher
Containment box removed
Insulator installed
New |
|
|
1842
|
Wednesday, December 19, 2018, 14:41 |
Anders Mjos | Conditioning Station | Standard Operation | | No target | Installed Shield Block on TCS | Frank and Anders installed lid on TCS and
started vacuum system yesterday. To run over
the Holidays. Retrieved dose badge from operational |
|
|
536
|
Wednesday, November 06, 2013, 10:41 |
David Wang | South Hot-Cell | Repair | TM2 | | Installed 2 turbopumps on TM2 | Bevan and I installed 2 turbo pumps on
TM2. The o- ring flanges on TM2 had been
cleaned before the installation. |
|
|
1634
|
Thursday, October 05, 2017, 11:04 |
Anders Mjos | ITW | Maintenance | | | Installation of new valve for module move ventilation | David installed the new ball valve and
connections for the SAS project module move
ventilation. SASP0482. Drawing reference |
|
|
1483
|
Thursday, April 06, 2017, 15:16 |
Anders Mjos | Conditioning Station | Maintenance | | | Installation of new break out box to accommodate both ITM:MP2 and TCS:MP1 | Installation by Marshall. Dave M from controls
adjusted circuitry to get TCS:MP1 to start.
Work is being done in preparation |
|
|
1781
|
Wednesday, September 12, 2018, 15:30 |
Isaac Earle | North Hot-Cell | Development | | | Installation of NHC operator-level lighting completed | Installation of of operator-level
lighting in the NHC was completed today according
to drawing IRH1801. 2" x 2" |
|
|
1663
|
Wednesday, November 15, 2017, 08:55 |
David Wang | Conditioning Station | Standard Operation | | | Install shield plug onto TCS and pumping down TCS. | Shielding plug is installed onto TCS. TCS
is being pumped down to keep it under vacuum
for the rest of the year. |
|
|
1102
|
Wednesday, October 14, 2015, 14:49 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Install new high current cables to TM2 | I installed a set of new high current cables
for TM2 Febiad run. The top of TM2
is configured to Febiad mode. See attachments |
|
|
2532
|
Thursday, January 25, 2024, 07:31 |
David Wang | Crane | Standard Operation | | | Inspection oftareg hall crane below hook attachment pins and plates ITA6550-01 | Tom Kauss inspected target hall crane below
hook attachment pins and plates ITA6550-01
yesterday. He certified the use of these |
|
|
2531
|
Thursday, January 25, 2024, 07:27 |
David Wang | Crane | Standard Operation | | | Inspection of target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 | Tom Gauss inspected two target module
lifting frames ITA0494-1997-01 and ITA0494-1997-02
yesterday. He certified the use of these |
|
|
2413
|
Friday, January 27, 2023, 07:18 |
David Wang | Crane | Standard Operation | | | Inspection of target module lifing frame ITA0494-1997-01 and ITA0494-1997-02 | Tom Gauss inspected two target module
lifting frames ITA0494-1997-01 and ITA0494-1997-02
yesterday. He certified the use of these |
|
|
53
|
Wednesday, November 16, 2011, 07:46 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | TaC#1 | Inspection of TaC#1 | Inspection of TaC#1 showed that the oven
was indeed broken on the A+ (left oven leg)
side of the central block. |
|
|
2622
|
Monday, June 24, 2024, 14:37 |
Carla Babcock | South Hot-Cell | Development | TM3 | UCx#44 | Inspection of TM3 and UCx#44 after no-protons run | TM3 and UCx#44 ran in ITE but issues with
the cyclotron prevented proton beam delivery.
Nonetheless, the target was heated and provided |
|
|
2414
|
Friday, January 27, 2023, 07:25 |
David Wang | Crane | Standard Operation | | | Inspection of TH crane below hook attachment pins and plates ITA6550-01 | Tom Kauss inspected target hall crane below
hook attachment pins and plates ITA6550-01
yesterday. He certified the use of these |
|
|
1622
|
Thursday, September 21, 2017, 16:26 |
Anders Mjos | South Hot-Cell | Standard Operation | TM2 | | Inspection of Source Tray | Chad and Anders inspected the Source Tray
today using the camera in the hot cell. A
dark spot was observed on one of the four |
|
|
443
|
Wednesday, September 04, 2013, 19:01 |
Grant Minor | South Hot-Cell | Repair | TM3 | | Inspection / Ante Room Leak Check Results on TM3 Heat Shield lines (3 Sept 2013) | Yesterday, Grant entered the Ante Room
with David Wang to visually inspect the two
sets of failed c-seals from the Heat Shield |
|
|
2294
|
Wednesday, January 19, 2022, 13:26 |
David Wang | Crane | Standard Operation | | | Inpection of Target module lifting frames ITA0494-1997-01 and ITA0494-1997-02. | Tom Gauss inspected two target module
lifting frames ITA0494-1997-01 and ITA0494-1997-02..
He certified the use of these two frames. |
|
|
1562
|
Thursday, June 22, 2017, 11:10 |
chad fisher | South Hot-Cell | Maintenance | | | In cell airline | The in cell airline has preemptively been
replaced. The hose was, as far as I know
the original. |
|
|
718
|
Monday, July 28, 2014, 17:26 |
Ron Kuramoto | ITW | Repair | | | ITW:IV5 Air leak repair | Air leak
was found at the Solenoid control valve located
in the Pre-Separator & DB0 room. The |
|
|
1821
|
Wednesday, November 14, 2018, 16:10 |
Anders Mjos | ITW | Repair | TM2 | UC#25 | ITW:FC5 safety signal troubleshooting | Measured resistance on safety limit switches
for FC5 on Exit Module 2. Determined that
the in connected signal did not work (shows |
|